Walnut Street Reconstruction, Phase 3
The proposed improvements include the relocation of approximately 4,270 feet of water main on Walnut Street between US41 and Martin Luther King Jr. Boulevard in downtown Evansville in conjunction with the City of Evansville Engineer’s Office road improvement project. The project is expected to include approximately seven fire hydrants, six gate valves and thirty-one service connections. Approximately 4,060 feet of existing water main will be abandoned at the conclusion of the project.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - Lochmueller Group
Evansville, IN
Construction Engineering Services - American Structurepoint, Inc.
Evansville, Indiana
Contractor- Blankenberger Brothers, Inc.
Cynthiana, IN
Road Closures & Boil Advisories
Click HERE
Project Update
-
Recent Progress (September 8, 2024, to September 14, 2024)
-
BBI installed water main towards Chestnut.
-
-
Anticipated Activities for Upcoming Week (September 23, 2024, to September 27, 2024)
-
BBI will continue to install water main towards Chestnut.
-
BBI will test water main at Governor.
-
Active and Scheduled Closures
Active
-
Please note this is an INDOT/City of Evansville Road reconstruction project including road improvements and utility relocations that are not affiliated with Evansville Water & Sewer Utility.