   This project involves the replacement of 4" and 6” water main with 5,280 LF of 8” water main in South Evergreen Acres Neighborhood. 

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

​

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

​

Project Designer - Three i Design

Evansville, Indiana

​

Construction Engineering Services - American Structurepoint, Inc.

Evansville, Indiana

​

Contractor- Infrastructure Systems, Inc.

Orleans, Indiana

​

​

Project Update

​​

  •     Recent Progress (January 5 to January 11)
    •    Infrastructure Systems completed the installation of the new 8” C900 PVC R.J. water main by trenchless bore on Pine Place between 413 Pine Place (STA. 20+90) and 401 Pine Place (STA. 24+40).
    •    Infrastructure Systems continued installing new 8” C900 PVC water main by open cut on Pine Place west of Larch Lane.

​

  •     Anticipated Activities for Upcoming Week (January 12 to January 18)  
    •    Infrastructure Systems intends to complete the installation of the new 8” C900 PVC R.J. water main by trenchless bore on Pine Place between 316 Pine Place (STA. 26+90) and 401 Pine Place (STA. 25+80). 
    •    Infrastructure Systems intends to continue installing new 8” C900 PVC water main by open cut on Pine Place west of Larch Lane.
    •    Infrastructure Systems intends to begin installing new ¾”-1” water service connections on Pine Creek Drive between Old State Road and 8103 Pine Creek Drive (STA. 59+45).

     

Active and Scheduled Closures

•    Active

  • Pine Creek Drive from Old State Rd. to Heather PlaceLocal Traffic Only 

  • Heather Place from Pine Creek Drive to Pine PlaceLocal Traffic Only  â€‹

  • Heather Court from Pine Place to Dead EndLocal Traffic Only 

  • Pine Place from Heather Place to Larch Lane - Local Traffic Only 

  • Larch Lane, W. Evergreen Road to Holly Hill Drive – Local Traffic Only

​

•    Scheduled

  • No additional closures scheduled at this time. 

​

Project Schedule​

  • Pine Creek Dr. from 8201 Pine Creek Dr. to Old State Road 

    • Water Main installation ONGOING

    • Water Service Connections from 2/3/25 - 2/7/25

    • Final Connections from 11/25/24 – 11/29/24

    • Restoration from 3/3/25 - 3/7/25

  • ​Pine Creek Dr. from Heather Place to 8201 Pine Creek Dr.

    • Water Main installation ONGOING

    • Water Service Connections from 2/10/25 - 2/14/25

    • Final Connections from 12/9/24 - 12/13/24

    • Restoration from 3/3/25 - 3/7/25

  • Heather Place from Pine Place to Pine Creek Drive 

    • ​Water Main installation ONGOING

    • Water Service Connections from 2/10/25 - 2/14/25

    • Final Connections from 12/16/24 - 12/20/24

    • Restoration from 3/10/25 - 3/14/25

  • Heather Court from Pine Place to cul-de-sac 

    • ​Water Main installation ONGOING

    • Water Service Connections from 2/17/25 - 2/21/25

    • Final Connections from 1/6/25 - 1/10/25

    • Restoration from 3/10/25 - 3/14/25

  • Pine Place from Larch Lane to Heather Place

    • ​Water Main installation ONGOING

    • Water Service Connections from 2/17/25 - 2/21/25

    • Final Connections from 12/16/24 - 12/20/24

    • Restoration from 3/17/25 - 3/21/25

  • Pine Place from Larch Lane to cul-de-sac

    • ​Water Main installation ONGOING

    • Water Service Connections from 2/24/25 - 2/28/25

    • Final Connections from 1/13/25 - 1/17/25

    • Restoration from 3/17/25 - 3/21/25

  • Larch Lane from Pine Place to 8235 Larch Lane  

    • Water Main installation from 1/20/25 - 1/24/25

    • Water Service Connections from 3/3/25 - 3/7/25

    • Final Connections from 1/20/25 - 1/24/25

    • Restoration from 3/24/25 - 3/28/25

  • Larch Lane from Evergreen Road to Pine Place 

    • ​Water Main installation from 1/6/25 - 1/31/25

    • Water Service Connections from 3/3/25 - 3/7/25

    • Final Connections from 1/27/25 - 1/31/25

    • Restoration from 3/24/25 - 3/28/25