South Evergreen Acres
 This project involves the replacement of 4" and 6” water main with 5,280 LF of 8” water main in South Evergreen Acres Neighborhood.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
​
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
​
Project Designer - Three i Design
Evansville, Indiana
​
Construction Engineering Services - American Structurepoint, Inc.
Evansville, Indiana
​
Contractor- Infrastructure Systems, Inc.
Orleans, Indiana
​
​
Project Update
​​
-
 Recent Progress (January 5 to January 11)
• Infrastructure Systems completed the installation of the new 8” C900 PVC R.J. water main by trenchless bore on Pine Place between 413 Pine Place (STA. 20+90) and 401 Pine Place (STA. 24+40).
• Infrastructure Systems continued installing new 8” C900 PVC water main by open cut on Pine Place west of Larch Lane.
​
-
 Anticipated Activities for Upcoming Week (January 12 to January 18)
• Infrastructure Systems intends to complete the installation of the new 8” C900 PVC R.J. water main by trenchless bore on Pine Place between 316 Pine Place (STA. 26+90) and 401 Pine Place (STA. 25+80).
• Infrastructure Systems intends to continue installing new 8” C900 PVC water main by open cut on Pine Place west of Larch Lane.
• Infrastructure Systems intends to begin installing new ¾”-1” water service connections on Pine Creek Drive between Old State Road and 8103 Pine Creek Drive (STA. 59+45).
Active and Scheduled Closures
• Active
-
Pine Creek Drive from Old State Rd. to Heather Place- Local Traffic Only
-
Heather Place from Pine Creek Drive to Pine Place- Local Traffic Only ​
-
Heather Court from Pine Place to Dead End- Local Traffic Only
-
Pine Place from Heather Place to Larch Lane - Local Traffic Only
-
Larch Lane, W. Evergreen Road to Holly Hill Drive – Local Traffic Only
​
• Scheduled
-
No additional closures scheduled at this time.
​
Project Schedule​
-
Pine Creek Dr. from 8201 Pine Creek Dr. to Old State Road
-
Water Main installation ONGOING
-
Water Service Connections from 2/3/25 - 2/7/25
-
Final Connections from 11/25/24 – 11/29/24
-
Restoration from 3/3/25 - 3/7/25
-
-
​Pine Creek Dr. from Heather Place to 8201 Pine Creek Dr.
-
Water Main installation ONGOING
-
Water Service Connections from 2/10/25 - 2/14/25
-
Final Connections from 12/9/24 - 12/13/24
-
Restoration from 3/3/25 - 3/7/25
-
-
Heather Place from Pine Place to Pine Creek Drive
-
​Water Main installation ONGOING
-
Water Service Connections from 2/10/25 - 2/14/25
-
Final Connections from 12/16/24 - 12/20/24
-
Restoration from 3/10/25 - 3/14/25
-
-
Heather Court from Pine Place to cul-de-sac
-
​Water Main installation ONGOING
-
Water Service Connections from 2/17/25 - 2/21/25
-
Final Connections from 1/6/25 - 1/10/25
-
Restoration from 3/10/25 - 3/14/25
-
-
Pine Place from Larch Lane to Heather Place
-
​Water Main installation ONGOING
-
Water Service Connections from 2/17/25 - 2/21/25
-
Final Connections from 12/16/24 - 12/20/24
-
Restoration from 3/17/25 - 3/21/25
-
-
Pine Place from Larch Lane to cul-de-sac
-
​Water Main installation ONGOING
-
Water Service Connections from 2/24/25 - 2/28/25
-
Final Connections from 1/13/25 - 1/17/25
-
Restoration from 3/17/25 - 3/21/25
-
-
Larch Lane from Pine Place to 8235 Larch Lane
-
Water Main installation from 1/20/25 - 1/24/25
-
Water Service Connections from 3/3/25 - 3/7/25
-
Final Connections from 1/20/25 - 1/24/25
-
Restoration from 3/24/25 - 3/28/25
-
-
Larch Lane from Evergreen Road to Pine Place
-
​Water Main installation from 1/6/25 - 1/31/25
-
Water Service Connections from 3/3/25 - 3/7/25
-
Final Connections from 1/27/25 - 1/31/25
-
Restoration from 3/24/25 - 3/28/25
-