Work in Your Area - Completed Projects
Covert Avenue, Hawthorne Avenue to Vann Avenue
This project included the relocation of 120 linear feet of 6" diameter Ductile Iron and 8" diameter C-900 PVC water main as well as related upgrades throughout the project area including new hydrants, valves and grading and restoration of all adjoining driveways, alleys, private walkouts, and lawns. The construction area consisted of Covert Avenue at the intersections of Hawthorne Avenue and McConnell Avenue.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - Evansville Water & Sewer Utility
Evansville, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor- BMB, Inc.
Newburgh, IN
Broadway Avenue
This project included the installation of over 11,000 feet of 6"- 12" diameter Ductile Iron and C-900 PVC water main pipe along Broadway Avenue from Schutte Road to Red Bank Road, as well as along Frey Road from Broadway Avenue to the end of the public roadway. Related improvements included new valves and 26 fire hydrants throughout the corridor.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - Clark Dietz, Inc.
Indianapolis, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor- BMB, Inc.
Newburgh, IN
Dexter Avenue and Jackson Avenue
This project included 1,000 LF of new 6" and 8" diameter water main as well as related upgrades throughout the project area including new hydrants and valves. The construction area consisted of Jackson Avenue from South Villa Drive to South Dexter Drive and South Dexter Drive from Jackson Avenue to Taylor Avenue.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - Evansville Water & Sewer Utility
Evansville, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor- BMB, Inc.
Newburgh, Indiana
Eichel Avenue
This project included approximately 1,100 feet of 12" ductile iron and C-900 PVC water main pipe and related improvements, including new fittings, valves, connections to existing water mains, service connection extensions and surface restoration, along Eichel Avenue from North Fares Avenue to US 41 and North Fares Avenue from Eichel Avenue to E Morgan Avenue.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - Evansville Water & Sewer Utility
Indianapolis, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor- BMB, Inc.
Newburgh, Indiana
President's Neighborhood
This project involved the installation of approximately 21,000 feet of new 4”-8” PVC C900 and ductile iron water main pipe in the Presidents Neighborhood. Work included the installation of water main valves, 30 hydrant assemblies, 630 service taps and service lines, and connections to existing water mains.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - United Consulting
Indianapolis, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractors -Deig Brothers Lumber and Construction Co., Inc.
Evansville, Indiana (Central Phase)
Infrastructure Systems, Inc.
Orleans, Indiana (West Phase, East Phase)
Washington Avenue and SE Second Street
This project involved the installation of approximately 1,950 feet of new 8”-16” PVC C900 and ductile iron water main pipe in the Haynies Corner Arts District. Work included the installation of water main valves, hydrant assemblies, 30 service taps and service lines, and connections to existing water mains. Work areas included new installations on Washington Avenue from SE Eighth Street to SE Second Street. Areas also included SE Second between Blackford Avenue and Adams Avenue, Adam Avenue between SE First Street and Parrett Street, and on Parrett Street from Washington Avenue to SE Third Street.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - Evansville Water & Sewer Utility
Evansville, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor - Deig Brothers Lumber and Construction Co., Inc.
Evansville, Indiana
Lodge Avenue from Walnut Street to Riverside Drive
This project involved the installation of approximately 13,000 feet of new 4”-12” PVC C900 and ductile iron water main pipe along Lodge Avenue from Riverside Drive to Lincoln Avenue, Lincoln Avenue from Lodge Avenue to Willow Road, Willow Road from Lincoln Avenue to Walnut Street, and along Bellemeade Avenue from Lodge Avenue to Bennighof Avenue. Work included the installation of water main valves, hydrant assemblies, service taps, service lines, meter pits, approximately 30 connections to existing water mains and retiring of existing water main facilities. This project was completed in June of 2019.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - Commonwealth Engineers, Inc.
Evansville, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor - Ragle, Inc.
Newburgh, Indiana
St. George Road and Melody Hill Water Main Installation
This project involved various water main improvements and upgrades in the Melody Hill area. Additional upgrades were planned for the existing water main along St. George Road between Twickingham Drive and Oak Hill Road. The approximate completed installation resulted in over 14,000 feet of new 8" water main pipe. This project was completed in June of 2019.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - Crawford, Murphy & Tilly, Inc.
Evansville, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor - Infrastructure Systems Inc.,
Orleans, Indiana
Vanderburgh Neighborhood Water Line Replacement, Phase I & II
The project involved the construction of approximately 8,600 linear feet of new 4", 6", and 8" C-900 PVC water main including new fire hydrants, valves and residential service connections in the Vanderburgh Neighborhood. This project was completed in April of 2019.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer, Phase I - CHA
Evansville, Indiana
Project Designer, Phase II - Wessler Engineering
Evansville, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor, Phase I - Infrastructure Systems Inc.
Orleans, Indiana
Contractor, Phase II - BMB, Inc.
Evansville, Indiana
West Mill Road and Mohr Road Water Main Replacement
The project involved the construction of approximately 3,500 feet of 12" water main. Project areas included Mill Road between Kratzville Road and St. Joseph Avenue and Mohr Road between St. Joseph Avenue and Kratzville Road. Additional work involved water service modifications to customers on Westchester Drive, St. Joseph Avenue between Mill and Mohr as well as customers within the Westbrook Mobile Home Park and Mill Creek Estates. This project was completed in March of 2019.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - HNTB Corporation
Indianapolis, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor - Infrastructure Systems Inc.,
Orleans, Indiana
Green River Road Phases VI and VII Water Relocation
This project included the replacement of approximately 10,000 feet of 12” and 8” PVC C-900 pipe and ductile iron water main pipe, 136 feet of trenchless 24” steel casing installation with carrier, 30 gate valves, 22 fire hydrant assemblies with valves, 1 air relief assembly, and 45 water service relocations. Work will also include traffic control, granular backfill and pavement restoration. The project area included North Green River Road between Rathbone Drive and State Road 57 in Daylight, Indiana, as well as cross streets within this corridor.
This project was completed in February of 2019.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - Evansville Water & Sewer Utility
Evansville, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor - Blankenberger Brothers, Inc.
Cynthiana, Indiana
Mount Auburn Road Water Main Replacement
The project involved the replacement of approximately 2,500 feet of 4” and 6” water mains with 4”, 6” and 8” C900 PVC mains. New water service connections, gate valves and fire hydrants were also installed on this project. Work areas included Mt. Auburn Road between Bismark Avenue and Optimist Drive.
This project was completed in December of 2018.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - Crawford Murphy & Tilly, Inc.
Indianapolis, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor - BMB, Inc.
Evansville, Indiana
Chestnut Street from Second Street to Fourth Street
Water main upgrades for this project included the installation of 600 feet 12" water main pipe and related improvements on Chestnut Street. This project was completed in the Fall of 2018.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - HNTB Corporation
Indianapolis, Indiana
Project Designer - VS Engineering, Inc.
Evansville, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor - Deig Brothers Lumber & Construction Co., Inc.
Evansville, Indiana
St. James Boulevard from Morgan Avenue to Keck Avenue
This project involved the installation of approximately 1,700 feet of 8" water main pipe. Construction was completed in April of 2018.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - HNTB Corporation
Indianapolis, Indiana
Project Designer - Evansville Water & Sewer Utility
Evansville, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor - Blankenberger Brothers, Inc.
Cynthiana, Indiana
Heidelbach Avenue from Morgan to Olmstead
This project involved the installation of approximately 5,400 feet of 12" water main pipe and related improvements. Upgrades were installed on Heidelbach Avenue between Morgan Avenue and Richardt Avenue and between Negley Avenue and Olmstead Avenue. The new water main continued on Olmstead Avenue to Stringtown Road. Construction was completed in August of 2018.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - HNTB Corporation
Indianapolis, Indiana
Project Designer - Wessler Engineering, Inc.
Evansville, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor - Kieffer Brothers Construction Co., Inc.
Mt. Carmel, Illinois
Keck Avenue, Grand to Stringtown Water Main Replacement
This project included the installation of approximately 2,370 feet of 8"- 12” PVC C-900 pipe, gate valves, fire hydrant assemblies w/ valves and approximately seventy (70) water service relocations. The project area was located on Keck Avenue, between Stringtown Road and Grand Avenue. Work also included asphalt pavement patching, sidewalk patching, ADA ramp improvements, and related lawn restoration. Work was completed in April of 2018.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - HNTB Corporation
Indianapolis, Indiana
Project Designer - Evansville Water & Sewer Utility
Evansville, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor - Ragle, Inc.
Newburgh, Indiana
Western Terrace Subdivision Water Main Replacement Project, Phase II
This project involved the second phase of water main upgrades and included approximately 6,000 feet of 8" water main pipe and affects multiple streets within the Western Terrace Subdivision located off Upper Mount Vernon Road on Evansville's west side. Construction was completed in June of 2018.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - HNTB Corporation
Indianapolis, Indiana
Project Designer - Clark Dietz, Inc.
Evansville, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor - Jerry Aigner Construction, Inc.
Boonville, Indiana
Weinbach Water Main Replacement, Pollack Avenue to Lloyd Expressway
This project required the installation of approximately 13,700 feet of new 4”-12” PVC and ductile iron water main pipe, generally along Weinbach Avenue from Division Street (Lloyd Expressway) to Kathleen Avenue (0.10 miles south of Pollack Avenue). The improvements included the installation of water main pipe and valves, fire hydrant assemblies, service taps, service lines, meter pits, over 50 connections to existing water mains, retiring of water main facilities, storm and sanitary pipe removal and replacement, final grading and seeding, temporary erosion and sediment control as well as related pavement patching. Work was completed in August of 2018. Click Here for information on the Weinbach Road Diet Project
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - HNTB Corporation
Indianapolis, Indiana
Project Designer - Commonwealth Engineers, Inc.
Evansville, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor - Ragle, Inc.
Newburgh, Indiana
Lant Circle and Bayard Park Water Main Replacement
This project replaced approximately 3,800 feet of 4"-8" PVC and ductile iron pipe. The improvements were generally located along Lant Circle from Lodge Avenue to Bayard Park Drive, then east along Bayard Park Drive to Weinbach Avenue. Rotherwood Avenue from Bayard Park Drive to Lincoln Avenue also received water main upgrades. The overall project included the installation of new valves, fire hydrants and multiple new water service connections. The work was completed in May of 2018.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - HNTB Corporation
Indianapolis, Indiana
Project Designer - Three i Design, Inc.
Evansville, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor - Deig Brothers Lumber & Construction, Inc.
Evansville, Indiana
Hi Rail Pedestrian Trail Water Installation Project
The Hi Rail Pedestrian Trail Water Installation Project was generally located along a Right of Way corridor immediately west of US Highway 41, between Ravenswood Drive and Gum Street and intended to provide connections for water mains that currently terminate at the ends of the streets adjacent to US Highway 41. The project was comprised of approximately 1,950 feet of 16" diameter water main and 700 feet of 8" diameter water main. The project was completed in April 2018.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - HNTB Corporation
Indianapolis, Indiana
Project Designer - Evansville Water & Sewer Utility
Evansville, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor - Blankenberger Brothers, Inc.
Cynthiana, Indiana
Stringtown Road, Louisiana Street to Morgan Avenue
The Stringtown Road Water Line Relocation Project replaced approximately 1,500 feet of 16" water main using open cut techniques. This relocation project allowed the existing water main on Stringtown Road to be removed from service. The work included water main relocation, water service reconnections, fire hydrant installations, related appurtenances and site restoration. Work on the project began in April 2017, and was completed on September 1, 2017.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - HNTB Corporation
Indianapolis, Indiana
Project Designer - Powers Engineering
Evansville, Indiana
Project Designer - United Consulting
Indianapolis, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor - Deig Brothers Lumber and Construction
Evansville, Indiana
Olive Street Water Main Replacement Project
The Evansville Water and Sewer Utility Board awarded the Olive, Sycamore and John Street Water Main Completion Project to Deig Brothers Lumber and Construction Company, Inc. on February 19, 2019.
For Information contact Cris Cottom, Water Capital Project Manager, EWSU: 812-421-2120 x 2203
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana