top of page

Wansford Yard Lift Station Phase 1-BC  Water Main Replacement

This project includes the installation of approximately 2,400 feet of new 8” water main pipe, 19 new gate valves, 6 fire hydrant assemblies, 24 water service replacements and related improvements on Sherman Avenue from Negley Avenue to  Stanley Avenue and on Kentucky Avenue/Cardinal Drive from Olmstead Avenue to Bedford Avenue.

Project Team

 

Project Owner
Evansville Water & Sewer Utility
Evansville, Indiana

Design and Construction Engineering Team

Commonwealth Engineers, Inc.
Evansville, Indiana

 

American Structurepoint, Inc. 
Evansville, Indiana

Powers Engineering, Inc. 

Evansville, Indinana

CHA Consulting
Evansville, Indiana

 

CTL Engineering
Indianapolis, Indiana

Contractor
MAC Construction and Excavating, Inc. 
New Albany, Indiana

Road Closures and Boil Advisories

Click HERE

Project Update
  • Recent Progress (November 26 to December 2)

    • MAC continued installing new 30” C900 PVC force main on Olmstead Avenue between Evans Avenue and Kentucky Avenue​

  • Anticipated Activities for Upcoming Week (December 3 to December 9)

    • MAC intends to continue installing 30" PVC force main on Olmstead Avenue between Evans Avenue and Kentucky Avenue.

Active and Scheduled Road Closures
  • Active

    • Sherman Ave. and Parkland Ave. between Diamond Avenue and Stringtown Road – Local Traffic Only

    • Parkland Ave., Evans Ave., and Olmstead Ave. between Stringtown Road and Kentucky Avenue – Local Traffic Only

  • Scheduled​​​

    • No additional closures scheduled at this time. 

Project Schedule

  • Sherman Avenue, from Diamond Avenue to Negley Avenue

    • Sewer Main Installation – Complete

    • Pavement Restoration – Early December to Mid December 2023

  • Sherman Avenue, from Negley Avenue to Parkland Avenue

    • Water Main Installation - Complete

    • Sewer Main Installation – Complete

    • Pavement Restoration – Early December to Mid December 2023

  •   Parkland Avenue, from Sherman Avenue to Stringtown Road

    • Sewer Main Installation – Complete

    • Pavement Restoration – Early December to Mid December 2023

  •  Stringtown Road at Parkland Avenue

    • Sewer Main Installation – Complete

    • Pavement Restoration – Ongoing

  • Parkland Avenue, from Stringtown Road to Evans Avenue

    • Sewer Main Installation – Ongoing

    • Pavement Restoration – Early December to Mid December 2023

  • Evans Avenue, from Parkland Avenue to Olmstead Avenue

    • Sewer Main Installation – Mid November to Late November 2023

    • Pavement Restoration – Early December to Mid December 2023

  • Olmstead Avenue, from Evans Avenue to Kentucky Avenue

    • Sewer Main Installation - Early January to Late March 2024

    • Pavement Restoration – Late March to Mid April 2024

  • Kentucky Avenue, from Olmstead Avenue to Idlewild Drive (including Tulip Avenue)​​

    • Sewer Main Installation - Early January to Late March 2024

    • Water Main Installation – Mid April to Late July 2024

    • Pavement Restoration – Late March to Mid April 2024

  • Cardinal Drive, from Idlewild Drive to Bedford Avenue

    • Water Main Installation – Mid April to Late July 2024

    • Sewer Main Installation – Early August to Mid October 2024

    • Pavement Restoration – Mid October to Mid November 2024

  • Pigeon Creek Crossing at Cardinal Drive

    • Sewer Main Installation – Complete

    • Restoration – Complete

  • Sanitary Easement, from Pigeon Creek to Schallers Lane to Wansford Yard Lift Station

    • Sewer Main Installation – Early August to Mid October 2024

    • Gravity Sewer Installation – ONGOING

  • Pfeiffer Road Crossing (by Trenchless Bore)

    • Gravity Sewer Installation – ONGOING

bottom of page