Wansford Yard Lift Station Phase 1-BC  Water Main Replacement

This project includes the installation of approximately 2,400 feet of new 8” water main pipe, 19 new gate valves, 6 fire hydrant assemblies, 24 water service replacements and related improvements on Sherman Avenue from Negley Avenue to  Stanley Avenue and on Kentucky Avenue/Cardinal Drive from Olmstead Avenue to Bedford Avenue.

Project Team

 

Project Owner
Evansville Water & Sewer Utility
Evansville, Indiana

Design and Construction Engineering Team

Commonwealth Engineers, Inc.
Evansville, Indiana

 

American Structurepoint, Inc. 
Evansville, Indiana

Powers Engineering, Inc. 

Evansville, Indinana

CHA Consulting
Evansville, Indiana

 

CTL Engineering
Indianapolis, Indiana

Contractor
MAC Construction and Excavating, Inc. 
New Albany, Indiana

Road Closures and Boil Advisories

Click HERE

Project Update
  • Recent Progress (September 3 to September 9)

    • MAC began mobilizing equipment and materials to the project site.

    • Professional Concrete performing advanced sawcutting of the existing pavement on Sherman Avenue and Parkland Avenue

  • Anticipated Activities for Upcoming Week (September 10 to September 16)

    • MAC intends to continue mobilizing equipment and materials to the project site.

    • MAC intends to begin the installation of the new 8” C900 PVC water main on Sherman Avenue between Negley Avenue and Stanley Avenue.

Road Closures and Lane Restrictions 
  • Planned

    • No road closures are currently planned.

Project Schedule

  • Sherman Avenue, from Diamond Avenue to Negley Avenue

    • Sewer Main Installation – Mid September to Late September 2023

    • Pavement Restoration – Early December to Mid December 2023

  • Sherman Avenue, from Negley Avenue to Parkland Avenue

    • Water Main Installation - Ongoing

    • Sewer Main Installation – Late September to Early October 2023

    • Pavement Restoration – Early December to Mid December 2023

  •   Parkland Avenue, from Sherman Avenue to Stringtown Road

    • Sewer Main Installation – Early October to Mid October 2023

    • Pavement Restoration – Early December to Mid December 2023

  •  Stringtown Road at Parkland Avenue

    • ​Sewer Main Installation – Mid October to Late October 2023

    • Pavement Restoration – Early December 2023 to Mid December 2023

  •  Parkland Avenue, from Stringtown Road to Evans Avenue

    • Sewer Main Installation – Early November to Mid November 2023

    • Pavement Restoration – Early December to Mid December 2023

  • Evans Avenue, from Parkland Avenue to Olmstead Avenue

    • ​Sewer Main Installation – Mid November to Late November 2023

    • Pavement Restoration – Early December to Mid December 2023

  •  Olmstead Avenue, from Evans Avenue to Kentucky Avenue

    • Sewer Main Installation - Early January to Late March 2024

    • Pavement Restoration – Late March to Mid April 2024

  •  Kentucky Avenue, from Olmstead Avenue to Idlewild Drive

    • Sewer Main Installation - Early January to Late March 2024

    • Pavement Restoration – Late March to Mid April 2024

  •   Cardinal Drive, from Idlewild Drive to Bedford Avenue

    • ​Water Main Installation – Mid April to Late July 2024

    • Sewer Main Installation – Early August to Mid October 2024

    • Pavement Restoration – Mid October to Mid November 2024

  • Pigeon Creek Crossing at Cardinal Drive

    • Sewer Main Installation – Mid September to Early November 2023

    • Restoration – Early November 2023

  • Sanitary Easement, from Pigeon Creek to Schallers Lane to Wansford Yard Lift Station

    • ​Sewer Main Installation – Early August to Mid October 2024

    • Gravity Sewer Installation – Late September 2023

  • Pfeiffer Road Crossing (by Trenchless Bore)

    • ​Gravity Sewer Installation – ONGOING