Wansford Yard Lift Station Phase 1-BC  Water Main Replacement

This project includes the installation of approximately 2,400 feet of new 8” water main pipe, 19 new gate valves, 6 fire hydrant assemblies, 24 water service replacements and related improvements on Sherman Avenue from Negley Avenue to  Stanley Avenue and on Kentucky Avenue/Cardinal Drive from Olmstead Avenue to Bedford Avenue.

Project Team

 

Project Owner
Evansville Water & Sewer Utility
Evansville, Indiana

Design and Construction Engineering Team

Commonwealth Engineers, Inc.
Evansville, Indiana

 

American Structurepoint, Inc. 
Evansville, Indiana

Powers Engineering, Inc. 

Evansville, Indinana

CHA Consulting
Evansville, Indiana

 

CTL Engineering
Indianapolis, Indiana

Contractor
MAC Construction and Excavating, Inc. 
New Albany, Indiana

Road Closures and Boil Advisories

Click HERE

Project Update
  • Recent Progress (April 7 to April 13)

    • MAC completed the installation of HMA base on Sherman Avenue between Negley Avenue and Stanley Avenue.

    • MAC completed the installation of new 8” C900 PVC water main on Kentucky Avenue and Cardinal Drive.

    • MAC performed hydrostatic testing and chlorinated the new 8” C900 PVC water main on Kentucky Avenue and Cardinal Drive.

  • Anticipated Activities for Upcoming Week (April 14 to April 20)

    • MAC intends to activate the new ¾”-1” water services on Kentucky Avenue and Cardinal Drive, between Olmstead Avenue and Bedford Avenue, pending the results of water quality sampling.

    • MAC intends to begin connecting new ¾”-1” water services on Kentucky Avenue and Cardinal Drive, between Olmstead Avenue and Bedford Avenue, pending the results of water quality sampling.

Active and Scheduled Road Closures
  • Active

    • Sherman Avenue and Parkland Avenue between Diamond Avenue and Stringtown Road – Local Traffic Only

    • Parkland Avenue, Evans Avenue, and Olmstead Avenue between Stringtown Road and Kentucky Avenue – Local Traffic Only

    • Kentucky Avenue between Olmstead Avenue and Idlewild Avenue – Local Traffic Only

    • Cardinal Drive between Idlewild Avenue and Bedford Avenue – Local Traffic Only

    • Sherman Avenue from Negley Avenue to Stanley Avenue - Closed on 4/9/24

  • Scheduled ​​​

    • Sherman Avenue from Diamond Avenue to Negley Avenue - Closed on/after 4/24/24

Project Schedule

  • Sherman Avenue, from Diamond Avenue to Negley Avenue

    • Sewer Main Installation – Complete

    • Pavement Restoration – Early March to Mid March 2024

  • Sherman Avenue, from Negley Avenue to Parkland Avenue​

    • Water Main Installation - Complete

    • Sewer Main Installation – Complete

    • Pavement Restoration – Early March to Mid March 2024

  •   Parkland Avenue, from Sherman Avenue to Stringtown Road

    • Sewer Main Installation – Complete

    • Pavement Restoration – Early March to Mid March 2024

  •  Stringtown Road at Parkland Avenue

    • Sewer Main Installation – Complete

    • Pavement Restoration – Early March to Mid March 2024

  • Parkland Avenue, from Stringtown Road to Evans Avenue

    • Sewer Main Installation – Complete

    • Pavement Restoration – Early March to Mid March 2024

  • Evans Avenue, from Parkland Avenue to Olmstead Avenue

    • Sewer Main Installation – Complete

    • Pavement Restoration – Early March to Mid March 2024

  • Olmstead Avenue, from Evans Avenue to Kentucky Avenue

    • Sewer Main Installation - Ongoing

    • Pavement Restoration – Late March to Mid April 2024

  • Kentucky Avenue, from Olmstead Avenue to Idlewild Drive (including Tulip Avenue)​​

    • Sewer Main Installation - ONGOING

    • Water Main Installation – Mid April to Late July 2024

    • Pavement Restoration – Late March to Mid April 2024

  • Cardinal Drive, from Idlewild Drive to Bedford Avenue

    • Water Main Installation – Mid April to Late July 2024

    • Sewer Main Installation – Early August to Mid October 2024

    • Pavement Restoration – Mid October to Mid November 2024

  • Pigeon Creek Crossing at Cardinal Drive

    • Sewer Main Installation – Complete

    • Restoration – Complete

  • Sanitary Easement, from Pigeon Creek to Schallers Lane to Wansford Yard Lift Station

    • Sewer Main Installation – Early August to Mid October 2024

    • Gravity Sewer Installation – ONGOING

  • Pfeiffer Road Crossing (by Trenchless Bore)

    • Gravity Sewer Installation – ONGOING