Toyota Trinity Storm Water Park CSS Separation Project

This project includes the installation of a new storm water collection system to separate
the storm water from the combined sanitary sewer in downtown Evansville.  This work will consist of the construction of approximately 4,400 linear feet of 12” to 36” storm sewers, 29 new storm sewer manholes and inlets, as well as the installation of a 1 million gallon subsurface detention basin at the site of the former Holy Trinity Catholic Church located at the intersection of NW 3rd Street and Vine Street.

 

The project will also include the replacement of existing water mains within the storm sewer collection system project area and consists of the replacement of approximately 4,500 linear feet of 6” to 20” water mains, 60 valves, 9 fire hydrants, 19 water service relocations and restoration. 
Click Here for Project Updates

Walnut Road, South of Campbell 

This project includes the relocation of  approximately 370 feet of new 8” water main pipe in advance of  new bridge improvements on Walnut Road in Vanderburgh County.  

Click Here for Project Updates

Walnut Street Reconstruction, Phase 2

This project includes the installation of approximately 8,000 feet of new 8” water main pipe, 14 new fire hydrants and 130 new water service connections on Walnut Street from Weinbach Avenue to Vann Avenue in conjunction with new road improvements in the corridor.  

Click Here for Project Updates

 
Charlotte Avenue and Russell Avenue

This project includes the installation of approximately 2,800 feet of new 8” and 12” water main pipe and related improvements on Charlotte Avenue, Russell Avenue and Bement Avenue area.

Click Here for Project Updates

 
Claremont, Bosse, and Craig Avenues

This project includes the installation of approximately 8,800 feet of new 8” and 12” water main pipe and related improvements throughout the project area.

Click Here for Project Updates

 
Alta Vista Drive
This project includes the replacement of approximately 100 linear feet of the existing water main on Alta Vista Drive with new 8" C-900 PVC pipe for the Vanderburgh County Highway Department. 
Click Here for Project Updates
Schroeder Road to Volkman Tank

This project includes the installation of approximately 5,000 feet of new water main pipe extending west from the Volkman Tank to Schroeder Road and west along Schroeder Road to US 41. Related upgrades throughout the project area include new hydrants and valves.

Click Here for Project Updates

West Maryland Street, Harmony to Wessel

This project includes the installation of approximately 2,300 feet of 8” diameter water main pipe and related upgrades along the south side of West Maryland Street.

Construction is anticipated to begin in Fall 2021.

Click Here for Project Updates

Kansas Road, Phase 2

This project will replace approximately 3,800 feet of 4” to 12” water main pipe along Kansas Road between Petersburg Road and Cayes Drive and on Petersburg Road near the intersection of Kanas Road as part of the second phase of the road improvements project being performed by the Vanderburgh County Engineer’s Office.  Additional improvements include 15 new gate valves,  7 new fire hydrants and service replacements. 

Click Here to Contact Us for Project Updates

Red Bank Road

This project includes the installation of over 16,000 feet of new 12” and 16” water main pipe. Related improvements include new valves and fire hydrants along Upper Mount Vernon Road to New Harmony Road, east of Red Bank Road and on Red Bank Road.

Construction is anticipated to begin in late Summer 2021. 

Click Here for Project Updates

 
Hogue Road, Red Bank Road to Williams Road

This project includes the installation of over 8,000 feet of 8" diameter water main pipe and related improvements along Hogue Road on Evansville's west side.      

Construction is anticipated to begin in Summer 2021.  

Click Here for Project Updates

Harmony Way and Franklin Heights Neighborhood

This project includes the installation of over 9,000 feet of 12" diameter water main pipe.  Other improvements may include new valves and fire hydrants as well as new service connections throughout the project area.   

Construction is anticipated to begin in Spring 2021.   

Click Here for Project Updates

North Kerth Avenue, St. George Road to Christ Road

This project included the installation of approximately 1,300 feet of 8" diameter water main pipe.

Construction is anticipated to begin in Spring 2021.

Click Here for Project Updates

Allens Lane Phase I

This project includes the installation of approximately 3,500 feet of new 8" water main pipe along Allens Lane from Mesker Park Drive to New Harmony Road and New Harmony Road south of Allens Lane as well as related improvements throughout the project area.

Construction is anticipated to begin in Spring 2021.

Click Here for Project Updates

Southeast Side Neighborhood, Phase I Water Main Replacements

This project included the installation of approximately 10,000 feet of new 4” and 8” water main pipe throughout the neighborhood between Hawthorne Avenue and Vann Avenue to the West and East, and Covert Avenue and Graham Avenue to the North and South.

Construction is anticipated to begin in Spring 2021.

Click Here for Project Updates

Fendrich Neighborhood Area

This project includes the installation of over 6,000 feet of new 8” diameter water main pipe and will connect previously renewed areas of water main throughout the area.

Design and construction dates are currently being reviewed.

Click Here for Project Updates

Rosewood Drive, Weaver to Herrmann & Karch Drive

This project includes the installation of approximately 2,260 feet of new water main pipe. Related improvements include new valves and fire hydrants throughout the project area.

Click Here for Project Updates

New Harmony Road, Allens Lane to Harmony Way

This project includes the installation of approximately 2,400 feet of 12" diameter water main pipe.    

Click Here for Project Updates

Grove Street, South of Allens Lane

This project includes the installation of approximately 2,700 feet of 8” diameter water main pipe. The installation will occur on Grove Street, south of Allens Lane.

Click Here for Project Updates

Bartels Road and Evergreen Road

This project includes the installation of approximately 1,200 feet of 8" water main pipe.

Click Here for Project Updates

 
First Avenue
This project is estimated to include 7,900 feet of new 4” to 36” water main pipe and related improvements throughout the project area, which consists of First Avenue, between Morgan Avenue and Colonial Avenue, and along the railroad tracks west of First Avenue, near Morgan Avenue. 
Click Here for Project Updates

Columbia Phase I, Fares, Columbia to Morgan 

This project is estimated to include the installation of approximately 9,500 feet of new water main and related upgrades throughout the project area including new hydrants, valves and service connections. .

Click Here for Project Updates