top of page

Work In Your Area - Construction Phase

 

Stanley Avenue, Governor Street to Kerth Avenue

This project would include the installation of approximately 5,600 feet of 8” water main pipe and related improvements along Stanley Avenue between Gpvernor Street and Kerth Avenue.

Click Here for Project Updates

 

Speaker Road, James Avenue and Nolan Avenue

This project would include the installation of approximately 2,900 feet of 8” diameter water main pipe. The installation would occur on Speaker Road between Broadway Avenue and Nolan Avenue, and James Avenue and Nolan Avenue west of Speaker Road.

Click Here for Project Updates

 

Evans & Louisiana Water Main Replacement
This project includes the installation of approximately 1,400 feet of water main pipe. The installation would occur on Lousisana Street, East of Evans Avenue and within a dedicated easement, north of Louisiana Street.

Click Here for Project Updates

Tupman Road Water Main Replacement

This project includes the installation of approximately 2,000 feet of water main pipe. Related improvements include valves and fire hydrants throughout the project area. Improvements are planned on Tupman Road, north of Upper Mount Vernon Road, and Mattingly Court, west of Tupman Road. 

Click Here for Project Updates

 

Mesker Park Phase I Water Main Replacement

This project would include the installation of approximately 2,500 feet of water main pipe, 6 fire hydrants, 10 gate valves and 10 services. The installation is planned along Mesker Park Drive, south of Diamond Avenue to Wimberg Avenue.

Click Here for Project Updates

Schutte Road, Broadway Avenue to USI Tank

This project consists of the installation of approximately 5,300 feet of 4" to 12" water main pipe, 33 gate valves, 12 fire hydrants and 34 water service replacements. The installation would occur on Schutte Road between Broadway Avenue and Clark Lane in western Vanderburgh County. 

Click Here for Project Updates

 

Sonntag Avenue, Goldmoor Road to Maryland Avenue

This project would include the installation of approximately 1,200 feet of water main pipe along Sonntag Avenue, between Goldmoor Road and Maryland Avenue. Related improvements include valves and fire hydrants throughout the project area.

Click Here for Project Updates

Gayne Street, West of Van Ness Avenue

This project would include the installation of approximately 300 feet of water main pipe along Gayne Street, west of Van Ness Avenue. Related improvements include valves and fire hydrants throughout the project area.

Click Here for Project Updates

Strueh Hendricks Road Connection to Broadway Avenue 

This project will install approximately 1,330 feet of new 12” water main along Strueh Hendricks Road in western Vanderburgh County, connecting an existing dead end main to an existing water main on Broadway Avenue.  The purpose of the project is to improve water distribution and quality in and around the project area. 

Click Here for Project Updates

Toyota Trinity Storm Water Park CSS Separation Project

This project includes the installation of a new storm water collection system to separate
the storm water from the combined sanitary sewer in downtown Evansville.  This work will consist of the construction of approximately 4,400 linear feet of 12” to 36” storm sewers, 29 new storm sewer manholes and inlets, as well as the installation of a 1 million gallon subsurface detention basin at the site of the former Holy Trinity Catholic Church located at the intersection of NW 3rd Street and Vine Street.

 

The project will also include the replacement of existing water mains within the storm sewer collection system project area and consists of the replacement of approximately 4,500 linear feet of 6” to 20” water mains, 60 valves, 9 fire hydrants, 19 water service relocations and restoration. 
Click Here for Project Updates

Walnut Road, South of Campbell 

This project includes the relocation of  approximately 370 feet of new 8” water main pipe in advance of  new bridge improvements on Walnut Road in Vanderburgh County.  

Click Here for Project Updates

Walnut Street Reconstruction, Phase 2

This project includes the installation of approximately 8,000 feet of new 8” water main pipe, 14 new fire hydrants and 130 new water service connections on Walnut Street from Weinbach Avenue to Vann Avenue in conjunction with new road improvements in the corridor.  

Click Here for Project Updates

 
Charlotte Avenue and Russell Avenue

This project includes the installation of approximately 2,800 feet of new 8” and 12” water main pipe and related improvements on Charlotte Avenue, Russell Avenue and Bement Avenue area.

Click Here for Project Updates

 
Claremont, Bosse, and Craig Avenues

This project includes the installation of approximately 8,800 feet of new 8” and 12” water main pipe and related improvements throughout the project area.

Click Here for Project Updates

Schroeder Road to Volkman Tank

This project includes the installation of approximately 5,000 feet of new water main pipe extending west from the Volkman Tank to Schroeder Road and west along Schroeder Road to US 41. Related upgrades throughout the project area include new hydrants and valves.

Click Here for Project Updates

West Maryland Street, Harmony to Wessel

This project includes the installation of approximately 2,300 feet of 8” diameter water main pipe and related upgrades along the south side of West Maryland Street.

Construction is anticipated to begin in Fall 2021.

Click Here for Project Updates

Kansas Road, Phase 2

This project will replace approximately 3,800 feet of 4” to 12” water main pipe along Kansas Road between Petersburg Road and Cayes Drive and on Petersburg Road near the intersection of Kanas Road as part of the second phase of the road improvements project being performed by the Vanderburgh County Engineer’s Office.  Additional improvements include 15 new gate valves,  7 new fire hydrants and service replacements. 

Click Here to Contact Us for Project Updates

Red Bank Road

This project includes the installation of over 16,000 feet of new 12” and 16” water main pipe. Related improvements include new valves and fire hydrants along Upper Mount Vernon Road to New Harmony Road, east of Red Bank Road and on Red Bank Road.

Construction is anticipated to begin in late Summer 2021. 

Click Here for Project Updates

 
Hogue Road, Red Bank Road to Williams Road

This project includes the installation of over 8,000 feet of 8" diameter water main pipe and related improvements along Hogue Road on Evansville's west side.      

Construction is anticipated to begin in Summer 2021.  

Click Here for Project Updates

Harmony Way and Franklin Heights Neighborhood

This project includes the installation of over 9,000 feet of 12" diameter water main pipe.  Other improvements may include new valves and fire hydrants as well as new service connections throughout the project area.   

Construction is anticipated to begin in Spring 2021.   

Click Here for Project Updates

First Avenue
This project is estimated to include 7,900 feet of new 4” to 36” water main pipe and related improvements throughout the project area, which consists of First Avenue, between Morgan Avenue and Colonial Avenue, and along the railroad tracks west of First Avenue, near Morgan Avenue. 
Click Here for Project Updates

Click Here for the Completed Projects Page

bottom of page