Toyota Trinity Storm Water Park CSS Separation Project
This project includes the installation of a new storm water collection system to separate
the storm water from the combined sanitary sewer in downtown Evansville. This work will consist of the construction of approximately 4,400 linear feet of 12” to 36” storm sewers, 29 new storm sewer manholes and inlets, as well as the installation of a 1 million gallon subsurface detention basin at the site of the former Holy Trinity Catholic Church located at the intersection of NW 3rd Street and Vine Street.
The project will also include the replacement of existing water mains within the storm sewer collection system
project area and consists of the replacement of approximately 4,500 linear feet of 6” to 20” water mains, 60 valves, 9 fire hydrants, 19 water service relocations and restoration.
Project Team
Project Owner
Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager
Evansville, Indiana
Project Designers
Evansville, Indiana
United Consulting
Indianapolis, Indiana
Construction Manager
Evansville, Indiana
Contractor
Blankenberger Brothers, Inc.
Cynthiana, Indiana
Project Update
Recent Progress (July 3 to July 9)
-
A preconstruction meeting was held on July 8.
Anticipated Activities for Upcoming Week (July 10 to July 16)
-
No work onsite anticipated.
Project Schedule
Project schedule will be updated once update is provided by the Contractor.