Work In Your Area - Design Phase

Southeast Side Neighborhood, Phase I Water Main Replacements

This project would include the installation of approximately 10,000 feet of new 4” and 8” water main pipe throughout the neighborhood between Hawthorne Avenue and Vann Avenue to the West and East, and Covert Avenue and Graham Avenue to the North and South.

Construction is anticipated to begin in Spring 2021.

Harmony Way and Franklin Heights Neighborhood

This project includes the installation of over 9,000 feet of 12" diameter water main pipe.  Other improvements may include new valves and fire hydrants as well as new service connections throughout the project area.   

Construction is anticipated to begin in Spring 2021.   

Bellaire Avenue, Oak Hill Road to Weinbach Avenue

This project would include the installation of approximately 820 feet of water main pipe along Bellaire Avenue between Oak Hill Road and Weinbach Avenue.

Construction is anticipated to begin in Spring 2021.

Fendrich Neighborhood Area

This project would include the installation of over 6,000 feet of new 8” diameter water main pipe and would connect previously renewed areas of water main throughout the area.

Design and construction dates are currently being reviewed.

Construction is anticipated to begin in Spring 2021.  

Kerth Avenue, St. George Road to Christ Road

This project would include the installation of approximately 1,300 feet of 8" diameter water main pipe.

Construction is anticipated to begin in Spring 2021.

Allens Lane Phase I

This project would include the installation of approximately 3,500 feet of new 8" water main pipe along Allens Lane from Mesker Park Drive to New Harmony Road and New Harmony Road south of Allens Lane as well as related improvements throughout the project area.

Construction is anticipated to begin in Summer 2021.

Hogue Road, Red Bank Road to Williams Road

This project includes the installation of over 8,000 feet of 8" diameter water main pipe and related improvements along Hogue Road on Evansville's west side.      

Construction is anticipated to begin in Summer 2021.  

Upper Mount Vernon Road, Red Bank Road and New Harmony Road

This project would include the installation of over 16,000 feet of new 12” and 16” water main pipe. Related improvements would include new valves and fire hydrants along Upper Mount Vernon Road to New Harmony Road, east of Red Bank Road and on Red Bank Road.

Construction is anticipated to begin in late Summer 2021. 

Schroeder Road to Volkman Tank

This project would include the installation of approximately 5,000 feet of new water main pipe extending west from the Volkman Tank to Schroeder Road and west along Schroeder Road to US 41. Related upgrades throughout the project area include new hydrants and valves.

Construction is anticipated to begin in Fall 2021. 

West Maryland Street, Harmony to Wessel

This project would include the installation of approximately 2,300 feet of 8” diameter water main pipe and related upgrades along the south side of West Maryland Street.

Construction is anticipated to begin in Fall 2021.

Claremont, Bosse, and Craig Avenues

This project would include the installation of approximately 8,800 feet of new 8” and 12” water main pipe and related improvements throughout the project area.

Construction is anticipated to begin in Fall 2021.

Senate Avenue, Petersburg Road, Feltman Drive, and Campground Road

This project would include the installation of approximately 6,700 feet of 4” to 12” water main pipe. Related improvements include valves and fire hydrants throughout the project area.

Construction is anticipated to begin in Fall 2021.

US 41, St. George Road to Lynch Road

This project would include the installation of 5,400 feet of 16” diameter water main pipe. Related improvements include valves and fire hydrants along US 41 between St. George Road and Lynch Road.

Construction is anticipated to begin in 2022.  

Walnut Street, Weinbach Avenue to Vann Avenue

This project and would include the installation of new water main pipe in various locations within the corridor and will connect previously renewed areas of water main throughout the area.

Construction dates are currently under review.

Construction is anticipated to begin in Fall 2021.  

Peerless Road, Upper Mt. Vernon Road to Moye Drive

This project would include the installation of approximately 5,000 feet of 12” and 16" diameter water main pipe. The installation would occur along Peerless Road from Moye Drive to Upper Mount Vernon Road, as well as along Upper Mount Vernon Road from Peerless Road to West Wind Drive.

Construction is anticipated to begin in 2022.

Evans and Louisiana

This project would include the installation of approximately 1,400 feet of water main pipe. The installation would occur on Evans Street, north of Louisiana Street.

Construction is anticipated to begin in 2022

Lincoln Booster Station and Water Main Replacement

This project would include the rehabilitation or replacement of the existing Lincoln Booster Station to meet current and future capacity demands. The Lincoln Booster Station is located near the northeast corner of Lincoln Avenue and Green River Road in Knight Township.  The project will also include the replacement of existing water mains along Lincoln Avenue from the booster station to Newburgh Road.

Construction is anticipated to begin in 2021.

  • Twitter Social Icon

© 2017 American Structurepoint, Inc.