Work In Your Area - Design Phase

First Avenue, Eichel Avenue to Colonial Avenue

This project is estimated to include 7,900 feet of new 4” to 36” water main pipe and related improvements throughout the project area.

Construction is anticipated to begin in Summer 2020.

Kansas Road, Petersburg Road to Green River Road

This project would include the installation of 7,800 feet of new 12" diameter water main pipe and related upgrades.

Construction is scheduled to begin in Summer 2020.

Covert Avenue, Hawthorne Avenue to Vann Avenue

This project is estimated to include the relocation of 120 linear feet of 6" diameter Ductile Iron and 8" diameter C-900 PVC water main as well as related upgrades throughout the project area including new hydrants, valves and grading and restoration of all adjoining driveways, alleys, private walkouts, and lawns. The construction area consists of Covert Avenue at the intersections of Hawthorne Avenue and McConnell Avenue.

Upper Mount Vernon Road, Red Bank Road and New Harmony Road

This project would include the installation of over 16,000 feet of new 12” and 16” water main pipe. Related improvements would include new valves and fire hydrants along Upper Mount Vernon Road to New Harmony Road, east of Red Bank Road and on Red Bank Road.

Construction is anticipated to begin in Fall 2020. 

Harmony Way and Franklin Heights Neighborhood

This project includes the installation of over 9,000 feet of 12" diameter water main pipe.  Other improvements may include new valves and fire hydrants as well as new service connections throughout the project area.   

Construction is anticipated to begin in Fall 2020.   

Hogue Road, Red Bank Road to Williams Road

This project includes the installation of over 8,000 feet of 8" diameter water main pipe and related improvements along Hogue Road on Evansville's west side.      

Construction is anticipated to begin in Fall 2020.  

New Harmony Road, Allens Lane to Harmony Way

This project includes the installation of approximately 2,400 feet of 12" diameter water main pipe.    

Construction is anticipated to begin in Fall 2020.   

Walnut Street, US 41 to Weinbach Avenue

This project and would include the installation of new water main pipe in various locations within the corridor and will connect previously renewed areas of water main throughout the area.

Construction dates are currently under review.

Construction is anticipated to begin in Fall 2020.  

US 41, St. George Road to Lynch Road

This project would include the installation of 5,400 feet of 16” diameter water main pipe. Related improvements include valves and fire hydrants along US 41 between St. George Road and Lynch Road.

Construction is anticipated to begin in late Fall 2020.  

Schmitt Lane, Whetstone Lane, and Bexley Court

This project would include the installation of approximately 4,800 feet of new 8” water main pipe and related upgrades throughout the project area.

Construction is anticipated to begin in Fall 2020. 

Fendrich Neighborhood Area

This project would include the installation of over 6,000 feet of new 8” diameter water main pipe and would connect previously renewed areas of water main throughout the area.

Design and construction dates are currently being reviewed.

Construction is anticipated to begin in Spring 2021.  

Walnut Street, Weinbach Avenue to Vann Avenue

This project and would include the installation of new water main pipe in various locations within the corridor and will connect previously renewed areas of water main throughout the area.

Construction dates are currently under review.

Construction is anticipated to begin in Summer 2021.  

Walnut Street, Martin Luther King Jr. Blvd to US 41

This project and would include the installation of new water main pipe in various locations within the corridor and will connect previously renewed areas of water main throughout the area.

Construction dates are currently under review.

Construction is anticipated to begin in Summer 2022.  

Schroeder Road to Volkman Tank

This project would include the installation of approximately 5,000 feet of new water main pipe extending west from the Volkman Tank to Schroeder Road and west along Schroeder Road to US 41. Related upgrades throughout the project area include new hydrants and valves.

Construction dates are being evaluated. 

Kerth Avenue, St. George Road to Christ Road

This project would include the installation of approximately 1,300 feet of 8" diameter water main pipe.

Construction dates are currently being evaluated.

Southeast Side Neighborhood, Phase I Water Main Replacements

This project would include the installation of approximately 10,000 feet of new 4” and 8” water main pipe throughout the neighborhood between Hawthorne Avenue and Vann Avenue to the West and East, and Covert Avenue and Graham Avenue to the North and South.

Construction is anticipated to begin in Winter 2020.

Allens Lane Phase I

This project would include the installation of approximately 3,500 feet of new 8" water main pipe along Allens Lane from Mesker Park Drive to New Harmony Road and New Harmony Road south of Allens Lane. Related improvements throughout the project area.

Construction is anticipated to begin in Winter 2020.

Bartels Road and Evergreen Road

This project would include the installation of approximately 2,400 feet of 8" water main pipe.

Construction is anticipated to begin in Winter 2021.

Rosewood Drive, Weaver to Herrmann & Karch Drive

This project would include the installation of approximately 2,260 feet of new water main pipe. Related improvements include new valves and fire hydrants throughout the project area.

Construction is anticipated to begin in Spring 2021.

Grove Street, South of Allens Lane

This project would include the installation of approximately 2,700 feet of 8” diameter water main pipe. The installation would occur on Grove Street, south of Allens Lane.

Construction is anticipated to begin in Spring 2021. 

  • Twitter Social Icon

© 2017 American Structurepoint, Inc.