Senate, Petersburg, Weaver and Campground Water Main Replacements
This project includes the installation of approximately 6,700 feet of 4” to 12” water main pipe. Related improvements include valves and fire hydrants throughout the project area.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - Commonwealth Engineers, Inc.
Evansville, Indiana
Construction Engineering Services - American Structurepoint, Inc.
Evansville, Indiana
Contractor- Deig Brothers Construction
Evansville, Indiana
Road Closures and Boil Advisories
Click HERE
Project Update
-
Recent Progress (April 7 to April 13)
-
Deig Brothers continued installing the new 8” C900 PVC water main on Feltman Road, north of Petersburg Road.
-
-
Anticipated Activities for Upcoming Week (April 14 to April 20)
-
Deig Brothers intends to activate the new 12” C900 PVC water main on Petersburg Road between Stringtown Road and Senate Avenue.
-
Deig Brothers intends to begin connecting new ¾”-1” water services on Petersburg Road between Stringtown Road and Senate Avenue.
-
Deig Brothers intends to complete the installation of the new 8” C900 PVC water main on Feltman Drive, north of Petersburg Road.
-
Deig Brothers intends to perform hydrostatic testing and chlorinate the new 8” C900 PC water main on Feltman Drive, north of Petersburg Road.
-
Active and Scheduled Closures
Active
-
W. Campground Rd., from Old State Road to Stringtown Road – Local Traffic Only
-
Petersburg Road, from Stringtown Road to Senate Avenue – CLOSED at Feltman Drive
-
W. Campground Road and Stringtown Road Intersection – Local Traffic Only
-
Feltman Road, north of Petersburg Road - Local Traffic Only
Scheduled
-
No scheduled closures.
Project Schedule
Phase 1 & 2 (Campground Road from Old State Road to Stringtown Road)
February 6, 2024 - Install traffic control
February 12 to March 13, 2024 - Install water main and services
March 14 to April 1, 2024- Restoration
Phase 3 (Petersburg Road from Stringtown Road to Senate Avenue, including Feltman Road)
April 1, 2024 - Install traffic control
April 2 to May 14, 2024 – Install water main and services
May 15 to May 20, 2024- Restoration
Phase 4 (Senate Avenue from Petersburg Road to east of Weaver, including Weaver Road)
May 21, 2024 - Install traffic control
May 27 to August 30, 2024 – Install water main and services
September 2 to September 11, 2024- Restoration