Harmony Way & Franklin Heights Neighborhood Water Main Improvements 

harmony way
harmony way

harmony way
harmony way

1/1

This project includes the installation of approximately 12,000 feet of new 16"-4" water main pipe along Harmony Way and within the Franklin Heights Neighborhood as well as related improvements throughout the project area.

Construction is anticipated to begin in Spring 2021.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Black & Veatch

Evansville, IN

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Miller Pipeline,LLC

Indianapolis, IN

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Project Updates will be posted weekly as construction progresses. 

Project Schedule

The project schedule will be posted as information is received from the Contractor.