Harmony Way & Franklin Heights Neighborhood Water Main Improvements




This project includes the installation of approximately 12,000 feet of new 16"-4" water main pipe along Harmony Way and within the Franklin Heights Neighborhood as well as related improvements throughout the project area.
Construction is anticipated to begin in Spring 2021.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - Black & Veatch
Indianapolis, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor- Miller Pipeline,LLC
Indianapolis, Indiana

Road Closures
Click HERE for updated road closures.

Boil Advisory Information
Click HERE for the latest boil advisory information
Project Update
This project is substantially complete and is currently in the punchlist phase. If you have concerns about your specific property, please contact us at 812-402-4509.