This project includes the installation of approximately 12,000 feet of new 16"-4" water main pipe along Harmony Way and within the Franklin Heights Neighborhood as well as related improvements throughout the project area.

Construction is anticipated to begin in Spring 2021.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Black & Veatch

Indianapolis, IN

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Miller Pipeline,LLC

Indianapolis, IN

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (January 2 to January 8) 

  • Miller Pipeline completed the installation of new 8” C900 PVC water main on Rupper Avenue between W. Franklin Street and Igleheart Avenue. 

  • Miller Pipeline performed hydrostatic testing and chlorinated the new 8” C900 PVC water main on Rupper Avenue between W. Franklin St. and Igleheart Avenue. 

  • Miller Pipeline completed the connection of new ¾”-1” water services on Harmony Way between Droll Avenue and W. Virginia Street. 

  • Miller Pipeline installed HMA base on Harmony Way between Mt. Vernon Avenue and W. Virginia Street. 

  • Traffic markings and lane striping have been completed on Harmony Way between Schoenfield Avenue and Mt. Vernon Avenue. 

 
Anticipated Activities for Upcoming Week (January 9 to January 15

  • Miller Pipeline intends to begin installing new 8” C900 PVC water main on Riggs Avenue between W. Franklin Street and Igleheart Avenue. 

  • Miller Pipeline intends to begin connecting new ¾”-1” water services on Rupper Avenue between W. Franklin Street and Igleheart Avenue pending the results of water quality sampling. 

Project Schedule

Phase 1-1

Harmony Way, from Schoenfield Ave. to W. Maryland Street

  • Water Main Installation - Complete

  • Water Service Line Installation (individual customer outages) - Complete

  • Water Main Final Connections (water main outages) - Complete

  • Restoration (pavement patching, lawn seeding) - Ongoing

 

Phase 1-2A

Harmony Way at W. Maryland Street (East)

  •  Water Main Installation – Complete

  • Water Main Final Connections (water main outages) – Complete

  • Restoration (pavement patching, lawn seeding) – Ongoing

 

Phase 1-2B

Harmony Way at W. Maryland Street (West)

  • Water Main Installation – Complete

  • Water Main Final Connections (water main outages) – Complete

  • Restoration (pavement patching, lawn seeding) – Ongoing

 

Phase 1-3

Harmony Way, from W. Maryland Street to Upper Mt. Vernon Road

  • Water Main Installation – Complete

  • Water Service Line Installation (individual customer outages) – Ongoing

  • Water Main Final Connections (water main outages) – Ongoing

  • Restoration (pavement patching, lawn seeding) – Ongoing

 

Phase 2

W. Virginia Street, from Harmony Way to Wills Avenue

Wills Avenue from W. Virginia Street to W. Michigan Street

  • Water Main Installation – Early December 2021

  • Water Service Line Installation (individual customer outages) – Mid December 2021

  • Water Main Final Connections (water main outages) – Mid November 2021

  • Restoration (pavement patching, lawn seeding) – Early January 2022

 

Phase 3

Riggs Avenue, from Igleheart Avenue to W. Franklin Street

Rupper Avenue, from Igleheart Avenue to W. Franklin Street

W. Michigan Street, from Riggs Avenue to Rupper Avenue

Igleheart Avenue, from Riggs Avenue to N. Tunis Avenue

  • Water Main Installation – Early December 2021

  • Water Main Final Connections (water main outages) – Mid December 2021

  • Restoration (pavement patching, lawn seeding) – Late December 2021

 

Phase 4

Harmony Way, from Upper Mt. Vernon Road to W. Michigan Street

W. Michigan Street, from Harmony Way to Schreeder Avenue

W. Franklin Street, from Schreeder Avenue to W. Franklin Street

W. Franklin Street, from Schreeder Avenue to N. Barker Avenue

N. Barker Avenue, from W. Franklin Street to Igleheart Avenue

Igleheart Avenue, from N. Barker Avenue to N. Tunis Avenue

W. Indiana Street, from N. Barker Avenue West to the Dead End

  • Water Main Installation – Late December 2021

  • Water Service Line Installation (individual customer outages) – Late January 2022

  • Water Main Final Connections (water main outages) – Early February 2022

  • Restoration (pavement patching, lawn seeding) – Mid February 2022