Harmony Way & Franklin Heights Neighborhood Water Main Improvements 

harmony way pic
harmony way pic

press to zoom
W11109
W11109

press to zoom
harmony way
harmony way

press to zoom
harmony way pic
harmony way pic

press to zoom
1/3

This project includes the installation of approximately 12,000 feet of new 16"-4" water main pipe along Harmony Way and within the Franklin Heights Neighborhood as well as related improvements throughout the project area.

Construction is anticipated to begin in Spring 2021.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Black & Veatch

Evansville, IN

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Miller Pipeline,LLC

Indianapolis, IN

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (September 12 to September 18) 

  • Miller Pipeline completed the construction of the new 8” and 16” C900 PVC water main at the intersection of Harmony Way and W. Maryland Street, west of Harmony Way (Phase 1-2B). 

  • Miller Pipeline installed HMA Base at the intersection of New Harmony Way and W. Maryland St. (Phase 1-2A and Phase 1-2B). 

  • Miller Pipeline reopened the intersection of Harmony Way and W. Maryland St. (Phase 1-2A and Phase 1-2B). 

 
Anticipated Activities for Upcoming Week (September 19 to September 25) 

  • Miller Pipeline intends to close Harmony Way between W. Maryland St. and Upper Mt. Vernon Rd. (Phase 1-C). 

  • Miller Pipeline intends to begin installing new 16” C900 PVC water main on Harmony Way between W. Maryland Street and Columbia St. 

Project Schedule

Phase 1-1

Harmony Way, from Schoenfield Ave. to W. Maryland Street

  • Water Main Installation - Complete

  • Water Service Line Installation (individual customer outages) - Complete

  • Water Main Final Connections (water main outages) - Complete

  • Restoration (pavement patching, lawn seeding) - Ongoing

 

Phase 1-2A

Harmony Way at W. Maryland Street (East)

  •  Water Main Installation – Early September 2021

  • Water Main Final Connections (water main outages) – Early September 2021

  • Restoration (pavement patching, lawn seeding) – Mid September 2021

 

Phase 1-2B

Harmony Way at W. Maryland Street (West)

  • Water Main Installation – Mid September 2021

  • Water Main Final Connections (water main outages) – Mid September 2021

  • Restoration (pavement patching, lawn seeding) – Mid September 2021

 

Phase 1-3

Harmony Way, from W. Maryland Street to Upper Mt. Vernon Road

  • Water Main Installation – Mid September 2021

  • Water Service Line Installation (individual customer outages) – Mid October 2021

  • Water Main Final Connections (water main outages) – Mid October 2021

  • Restoration (pavement patching, lawn seeding) – Late October 2021

 

Phase 2

W. Virginia Street, from Harmony Way to Wills Avenue

Wills Avenue from W. Virginia Street to W. Michigan Street

  • Water Main Installation – Early November 2021

  • Water Service Line Installation (individual customer outages) – Mid November 2021

  • Water Main Final Connections (water main outages) – Mid November 2021

  • Restoration (pavement patching, lawn seeding) – Early December 2021

 

Phase 3

Riggs Avenue, from Igleheart Avenue to W. Franklin Street

Rupper Avenue, from Igleheart Avenue to W. Franklin Street

W. Michigan Street, from Riggs Avenue to Rupper Avenue

Igleheart Avenue, from Riggs Avenue to N. Tunis Avenue

  • Water Main Installation – Early December 2021

  • Water Main Final Connections (water main outages) – Mid December 2021

  • Restoration (pavement patching, lawn seeding) – Late December 2021

 

Phase 4

Harmony Way, from Upper Mt. Vernon Road to W. Michigan Street

W. Michigan Street, from Harmony Way to Schreeder Avenue

W. Franklin Street, from Schreeder Avenue to W. Franklin Street

W. Franklin Street, from Schreeder Avenue to N. Barker Avenue

N. Barker Avenue, from W. Franklin Street to Igleheart Avenue

Igleheart Avenue, from N. Barker Avenue to N. Tunis Avenue

W. Indiana Street, from N. Barker Avenue West to the Dead End

  • Water Main Installation – Late December 2021

  • Water Service Line Installation (individual customer outages) – Late January 2022

  • Water Main Final Connections (water main outages) – Early February 2022

  • Restoration (pavement patching, lawn seeding) – Mid February 2022