Oak Hill Road, Eastwood Drive to Millersburg Road

The proposed improvements include the relocation of approximately 4,900 feet of water main along Oak Hill Road between Eastwood Drive and Millersburg Road as part of the multiple phase road improvements  project by the Vanderburgh County Engineers Office.  The project is expected to include new fire hydrants, gate valves and 46 service connections.  

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - United Consulting Engineers

Indianapolis, Indiana

Construction Engineering Services - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Koberstein Contracting

Evansville, Indiana

Project Update
  • Recent Progress (June 16 to June 22)

    • Koberstein removed all abandoned fire hydrants and valve boxes on the abandoned main between Eastwood Drive and Voigt Road on Oak Hill Road.

    • Koberstein removed the abandoned main between Eastwood Drive and Voigt Road.

  • Anticipated Activities for Upcoming Week (June 23 to June 29) 

    • No work will be performed on the water main; water main is complete on Oak Hill Road between Eastwood Drive and Voigt Road.

    • No additional updates will be provided until water main installation begins on Phase 2 on Oak Hill Road between Voigt Road and Millersburg Road

Active and Scheduled Closures
  • Active

    • Oak Hill Road between Heckel Road and Millersburg Road (Closed to Thru Traffic)

    • Oak Hill Road between Eastwood Drive and Voigt Road (Closed, Local Traffic Only)

      • Please note this is a Vanderburgh County Road reconstruction project including road improvements and utility relocations that are not affiliated with Evansville Water & Sewer Utility.

Scheduled

  • No additional closures scheduled in the immediate future. 

Project Schedule

  • Phase 1 (Eastwood to Voigt Rd)

    • ​Install water main- April 9 to June 17, 2024​​

    • Service and tie-in connections -  June 18 to July 3, 2024

  • Phase 2 (Voigt Rd to Millersburg Rd)

    • Install water main November 15, 2024 to January 2, 2025​

    • Service and tie-in connections - January 3 to January 29, 2025