top of page

Oak Hill Road, Eastwood Drive to Millersburg Road

The proposed improvements include the relocation of approximately 4,900 feet of water main along Oak Hill Road between Eastwood Drive and Millersburg Road as part of the multiple phase road improvements  project by the Vanderburgh County Engineers Office.  The project is expected to include new fire hydrants, gate valves and 46 service connections.  

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - United Consulting Engineers

Indianapolis, Indiana

Construction Engineering Services - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Koberstein Contracting

Evansville, Indiana

Project Update
  •     Recent Progress (November 24 to November 30)
    •    Koberstein completed the installation of the new 8” ancillary water main on Eastview Drive, west of Oak Hill Rd.
    •    Koberstein began installing the new 12” C900 PVC water main on Oak Hill Rd. between 7415 Oak Hill Rd. and Heseman Avenue.
    •    Koberstein performed hydrostatic testing and chlorinated the new 12” C900 PVC water main on Oak Hill Rd. between Voigt Rd. and 7415 Oak Hill Rd.

  •     Anticipated Activities for Upcoming Week (December 1 to December 7)  
    •    Koberstein intends to continue installing new 12” C900 PVC water main on Oak Hill Rd. between 7415 Oak Hill Rd. and Heseman Avenue.
    •    Koberstein intends to activate the new 12” C900 PVC water main on Oak Hill Rd. between Voigt Rd. and 7415 Oak Hill Rd., pending the results of water quality sampling.
    •    Koberstein intends to begin connecting the new ¾”-1” water service connections on Oak Hill Rd. between Voigt Rd. and 7415 Oak Hill Rd., pending the results of water quality sampling.
     

     

Active and Scheduled Closures
  • Active

    •     Oak Hill Road between Voigt Road and William L. Brooks Drive (Closed, Local Traffic Only)

      • Please note this is a Vanderburgh County Road reconstruction project including road improvements and utility relocations that are not affiliated with Evansville Water & Sewer Utility.

Scheduled

  • No additional closures scheduled in the immediate future. 

Project Schedule

  • Phase 1 (Eastwood to Voigt Rd)

    • ​Install water main- April 9 to June 17, 2024​​

    • Service and tie-in connections -  June 18 to July 3, 2024

  • Phase 2 (Voigt Rd to Millersburg Rd)

    • Install water main November 1, 2024 to January 2, 2025​

    • Service and tie-in connections - January 3 to January 29, 2025

bottom of page