This includes the installation of approximately 2,500 feet of water main pipe, 6 fire hydrants, 10 gate valves and 10 services. The installation is planned along Mesker Park Drive, south of Diamond Avenue to Wimberg Avenue.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Three i Design

Evansville, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Blankenberger Brothers, Inc.

Cynthianan, Indiana

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Project Update

 

Recent Progress (May 14 to May 20

  • Blankenberger continued concrete pavement restoration on Mesker Park Drive between Wimberg Avenue and Buchanan Road.

  • Blankenberger activated the new 8” PVC C900 water main between Wimberg Avenue and Buchanan Road on Mesker Park Drive.

  • Blankenberger began water service relocations between Wimberg Avenue and Buchanan Road.  

Anticipated Activities for Upcoming Week (May 21 to May 27)

  • Blankenberger intends to continue concrete pavement restoration on Mesker Park Drive between Wimberg Avenue and Buchanan Road.

  • Blankenberger intends to complete water service relocations between Wimberg Avenue and Buchanan Road.

  • Blankenberger intends to make final connections to the existing 8” main on Buchanan Road.

  • Blankenberger intends to make final connections to the existing 8” main on Mesker Park Drive at Buchanan Road