Mesker Park Phase 1 Water Main Replacement

This includes the installation of approximately 2,500 feet of water main pipe, 6 fire hydrants, 10 gate valves and 10 services. The installation is planned along Mesker Park Drive, south of Diamond Avenue to Wimberg Avenue.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Three i Design

Evansville, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Blankenberger Brothers, Inc.

Cynthianan, Indiana

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Project Update

 

Recent Progress (March 19 to March 25

  • Powers Welding completed installation of 12” PVC RJ C-900 between Wimberg Avenue and Buchanan Road via directional bore.   

Anticipated Activities for Upcoming Week (March 26 to April 1)

  • Blankenberger intends to complete installation of the 8” PVC C-900 at Buchanan Road.

  • Blankenberger intends to hydrostatically test and chlorinate the 12” PVC C-900 main between Wimberg Avenue and Buchanan Road.

  • Blankenberger intends to start service relocations from 1545 Mesker Park Drive to Wimberg Avenue, stations 17+20 to 23+25.