Mesker Park Phase 1 Water Main Replacement



This includes the installation of approximately 2,500 feet of water main pipe, 6 fire hydrants, 10 gate valves and 10 services. The installation is planned along Mesker Park Drive, south of Diamond Avenue to Wimberg Avenue.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - Three i Design
Evansville, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor- Blankenberger Brothers, Inc.
Cynthianan, Indiana

Road Closures
Click HERE for updated road closures.

Boil Advisory Information
Click HERE for the latest boil advisory information
Project Update
Recent Progress (March 19 to March 25)
-
Powers Welding completed installation of 12” PVC RJ C-900 between Wimberg Avenue and Buchanan Road via directional bore.
Anticipated Activities for Upcoming Week (March 26 to April 1)
-
Blankenberger intends to complete installation of the 8” PVC C-900 at Buchanan Road.
-
Blankenberger intends to hydrostatically test and chlorinate the 12” PVC C-900 main between Wimberg Avenue and Buchanan Road.
-