Schutte Road, Broadway Avenue to USI Tank Water Main Replacement




This project consists of the installation of approximately 5,300 feet of 4" to 12" water main pipe, 33 gate valves, 12 fire hydrants and 34 water service replacements. The installation would occur on Schutte Road between Broadway Avenue and Clark Lane in western Vanderburgh County.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - Clark Dietz, Inc.
Evansville, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor- Miller Pipeline, LLC
Indianapolis, Indiana

Boil Advisory Information
Click HERE for the latest boil advisory information
Project Update
Recent Progress (May 14 to May 20)
-
Miller Pipeline activated the main and then started service relocations on chlorination run 1, stations 8+25 to 19+75.
-
Miller Pipeline hydrostatically tested and chlorinated chlorination run 2 stations 19+75 to 33+75 up to Pine Ridge Drive.
-
Miller Pipeline made repairs to the existing storm culvert at station 22+25.
Anticipated Activities for Upcoming Week (May 21 to May 27)
-
Miller Pipeline intends to complete service relocations on chlorination run 1, stations 8+25 to 19+75.
-
Miller Pipeline intends to activate and start service relocations on chlorination run 2, stations 19+75 to 33+75 to Pine Ridge Drive, pending water quality testing.
-
Miler Pipeline intends to install the stream crossing leakage and sampling structure at station 14+60.
-
Miller Pipeline intends to make final connections to the existing main on Rich Lynn Drive.
-
Miller Pipeline intends to begin pot holing existing utilities in chlorination run 3.
Project Schedule
Schutte Road, Broadway Avenue to Pine Ridge Drive
-
Water Main Installation - April 2023 to Mid June 2023
-
Water Service Line Installation (individual customer outages) - Early June 2023 to Early July 2023
-
Water Main Final Connections (water main outages) - July 2023
-
Restoration (pavement patching, lawn seeding) - July 2023
Schutte Road, Pine Ridge Drive to Locust Tree Lane
-
Water Main Installation - June 2023 to August 2023
-
Water Service Line Installation (individual customer outages) - July 2023 to August 2023
-
Water Main Final Connections (water main outages) - Late August 2023 to Early September 2023
-
Restoration (pavement patching, lawn seeding) - September 2023