Schutte Road, Broadway Avenue to USI Tank Water Main Replacement

This project consists of the installation of approximately 5,300 feet of 4" to 12" water main pipe, 33 gate valves, 12 fire hydrants and 34 water service replacements. The installation would occur on Schutte Road between Broadway Avenue and Clark Lane in western Vanderburgh County. 

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Clark Dietz, Inc.

Evansville, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Miller Pipeline, LLC 

Indianapolis, Indiana

Boil Advisory Information

Click HERE for the latest boil advisory information

Project Update

 

Recent Progress (May 14 to May 20)

  • Miller Pipeline activated the main and then started service relocations on chlorination run 1, stations 8+25 to 19+75.

  • Miller Pipeline hydrostatically tested and chlorinated chlorination run 2 stations 19+75 to 33+75 up to Pine Ridge Drive.

  • Miller Pipeline made repairs to the existing storm culvert at station 22+25.

 Anticipated Activities for Upcoming Week (May 21 to May 27)

  • Miller Pipeline intends to complete service relocations on chlorination run 1, stations 8+25 to 19+75.

  • Miller Pipeline intends to activate and start service relocations on chlorination run 2, stations 19+75 to 33+75 to Pine Ridge Drive, pending water quality testing.

  • Miler Pipeline intends to install the stream crossing leakage and sampling structure at station 14+60.

  • Miller Pipeline intends to make final connections to the existing main on Rich Lynn Drive.

  • Miller Pipeline intends to begin pot holing existing utilities in chlorination run 3.  

Project Schedule

Schutte Road, Broadway Avenue to Pine Ridge Drive

  • Water Main Installation - April 2023 to Mid June 2023

  • Water Service Line Installation (individual customer outages) - Early June 2023 to Early July 2023

  • Water Main Final Connections (water main outages) - July 2023

  • Restoration (pavement patching, lawn seeding) - July 2023

Schutte Road, Pine Ridge Drive to Locust Tree Lane

  • ​Water Main Installation - June 2023 to August 2023

  • ​Water Service Line Installation (individual customer outages) - July 2023 to August 2023

  • Water Main Final Connections (water main outages) - Late August 2023 to Early September 2023

  • Restoration (pavement patching, lawn seeding) - September 2023