top of page

Lloyd4U R-42287 Water Main Relocations
(Red Bank Road, Boehne Camp Road, and Schutte Road) 

These relocations are in preparation for road improvements planned for this area as part of the Lloyd4U project. 

Red Bank Road: This involves the replacement of 12" water main with 1170 LF of 12" from University Drive to Pearl Drive and 210 LF of 8" across Red Bank Road south of SR 62.

Boehne Camp Road: This involves the replacement of 8" water main with 920 LF of 12" and 50 LF of 8" from Calle De Oro to S. Boehne Camp Road.

Schutte Road: This involves the replacement of 8" and 12" water main with 1330 LF of 12" water main from West Vernon Drive to Mahrenholz Road.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Clark Dietz, Inc.

Evansville, Indiana

Construction Engineering Services - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Koberstein Contracting

Indianapolis, Indiana

Road Closures and Boil Advisories

Click HERE

Project Update

  • Recent Progress

    • The preconstruction meeting for this project was held 5/29/24. 

  • Upcoming Work

    • Materials are currently being ordered and work is expected to begin in early July. 

Active and Scheduled Closures

Active

  • No active road closures

Scheduled

  • No additional closures scheduled in the immediate future. 

Project Schedule

  • TBD

bottom of page