top of page

Lloyd4U R-42287 Water Main Relocations
(Red Bank Road, Boehne Camp Road, and Schutte Road) 

These relocations are in preparation for road improvements planned for this area as part of the Lloyd4U project. 

Red Bank Road: This involves the replacement of 12" water main with 1170 LF of 12" from University Drive to Pearl Drive and 210 LF of 8" across Red Bank Road south of SR 62.

Boehne Camp Road: This involves the replacement of 8" water main with 920 LF of 12" and 50 LF of 8" from Calle De Oro to S. Boehne Camp Road.

Schutte Road: This involves the replacement of 8" and 12" water main with 1330 LF of 12" water main from West Vernon Drive to Mahrenholz Road.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Clark Dietz, Inc.

Evansville, Indiana

Construction Engineering Services - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Koberstein Contracting

Indianapolis, Indiana

Road Closures and Boil Advisories

Click HERE

Project Update

​​​

  • Recent Progress (August 25 to August 31)

    • Koberstein activated the 12” PVC C-900 water main on North Red Bank Road.

    • Koberstein completed water service relocations on North Red Bank Road.

    • Koberstein completed final main connections on North Red Bank Road.

    • Koberstein continued installation of the 8” C-900 water main in the Southeast corner of the Lloyd Expressway and Red Bank Road (Access Road).

    • Koberstein and Edwards Concrete grout filled the abandoned 8” water main on Boehne Camp.

    • E&B Paving completed installation of HMA base on North Red Bank Road and Boehne Camp.

    • Snyder Construction completed installation of the 24” steel casing at Schutte Road via jack and bore. 

  • Anticipated Activities for Upcoming Week (September 1 to September 7) 

    • Koberstein intends to continue installation of the 8” C-900 water main in the Southeast corner of the Lloyd Expressway and Red Bank Road.

    • E&B Paving intends to begin installation of HMA Surface on North Red Bank Road and Boehne Camp.

Active and Scheduled Closures

Active

  • Boehne Camp Road between Lloyd Expressway and Hogue Road- Closed 

  • Southbound Red Bank Road between University Drive and the Lloyd Expressway- lane restrictions 

  • Access Road from AT&T to Sonic- lane restrictions, access still granted from south side

Scheduled

  • No scheduled closures

Project Schedule

  • Boehne Camp Road

    • Mobilization- Complete

    • Bore across Lloyd Expressway - Complete

    • Bore across South Boehne Camp - Complete

    • Install water main on north Boehne Camp - Complete

    • Testing - Complete

    • Connect services and water main- Complete

    • Restoration 8/20/24 – 9/13/24

  • Red Bank Road

    • Bore across north Red Bank Road- Complete

    • Bore across south Red Bank Road- Complete

    • Bore across Lloyd Expressway 7/30/24 – 9/20/24

    • Install water main north of Lloyd - Complete

    • Testing 8/12/24 - 9/27/24

    • Connect services north of Lloyd 8/19/24 – 9/27/24

    • Install water main south of Lloyd 8/12/24 – 9/6/24

    • Install water main south of Lloyd 9/3/24 – 9/25/24

    • Testing 9/26/24 – 10/2/24

    • Connect services and main south of Lloyd 10/3/24 – 10/21/24

    • Restoration 10/22/24 – 11/9/24

  • Schutte Road

    • Bore across Lloyd Expressway 8/9/24 – 8/29/24

    • Install water main 8/30/24 – 9/30/24

    • Testing 10/1/24 – 10/7/24

    • Connect services 10/8/24 – 10/15/24

    • Restoration 10/16/24 – 10/29/24

bottom of page