20" Line Stop, SR 62 and Lemcke Ave.

This project involves inserting a 20" line stop at Lemcke Ave. to abandon the 20" cast iron water main from Tekoppel to Addison. This relocation is in preparation for road improvements planned for this area as part of the Lloyd4U project.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Evansville Water & Sewer Utility

Evansville, Indiana

Construction Engineering Services - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Koberstein Contracting

Evansville, Indiana

Road Closures and Boil Advisories

Click HERE

Project Update

  • Recent Progress

    • Koberstein potholed existing utilities on 5/28/24. 

  • Upcoming Work

    • Koberstein will restrain existing water main once materials arrive on site.

Active and Scheduled Closures

Active

  • No active road closures

Scheduled

  • No additional closures scheduled in the immediate future. 

Project Schedule

  • Pothole existing utilities- May 29, 2024

  • Procure Materials - May 30 to July 8, 2024

  • Restrain existing water main - June 10-14, 2024

  • Perform 20" Line stop/ Cut & cap - July 9- 10, 2024

  • Abandon existing main - July 12- 18, 2024

  • Site Restoration July 19 - 23, 2024