Red Bank Road Water Main Replacement 

U1025 Red Bank Road (4)
U1025 Red Bank Road (4)

press to zoom
U1025 Red Bank Road (6)
U1025 Red Bank Road (6)

press to zoom
U1025 Red Bank Road (5)
U1025 Red Bank Road (5)

press to zoom
1/3

This project would include the installation of over 16,000 feet of new 12” and 16” water main pipe. Related improvements would include new valves and fire hydrants along Upper Mount Vernon Road to New Harmony Road, east of Red Bank Road and on Red Bank Road.

This project is anticipated to begin in November 2021 with an estimated completion date of November 2022. 

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - United Consulting Engineers

Indianapolis, IN

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Miller Pipeline, LLC

Indianapolis, IN

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (June 19 to June 25)

  • Miller Pipeline continued installing new 12” C900 PVC water main on Red Bank between 1700 N. Red Bank Road (STA. 96+20) and Barbara Jane Lane – Test Section #6.

  • Miller Pipeline began installing HMA base on Red Bank between Upper Mt. Vernon Rd. and 1406 Red Bank Rd. (STA. 105+90) – Test Section #4.

 Anticipated Activities for Upcoming Week (June 26 to July 2)

  • Miller Pipeline intends to complete the installation of new 12” C900 PVC water main on Red Bank between 1700 N. Red Bank Road (STA. 96+20) and Barbara Jane Lane – Test Section #6.

  • Miller Pipeline intends to activate the new 12” C900 PVC water main on Red Bank between 1406 N. Red Bank Road (STA. 105 +90) and 1700 N. Red Bank Road (STA. 96+20) – Test Section #5.

  • Miller Pipeline intends to begin connecting new ¾”-1” water services on Red Bank between 1406 N. Red Bank Road (STA. 105 +90) and 1700 N. Red Bank Road (STA. 96+20) – Test Section #5.

  • Miller Pipeline intends to complete the installation of HMA base on Red Bank between Upper Mt. Vernon and 1406 N. Red Bank Road (STA. 105+90) – Test Section #4.

Project Schedule

Upper Mt. Vernon Road, from Vanness Avenue to Red Bank Road​

  • Water Main Installation - Complete

  • Water Service Line Installation (individual customer outages) - Complete

  • Water Main Final Connections (water main outages) - Complete

  • Restoration (pavement patching, lawn seeding) - Complete

Red Bank Road, from Upper Mt. Vernon Road to New Harmony Road

  • Water Main Installation - May to August 2022

  • Water Service Line Installation (individual customer outages) - June to September 2022

  • Water Main Final Connections (water main outages) - July to September 2022

  • Restoration (pavement patching, lawn seeding) - September 2022

New Harmony Road, from Red Bank Road to Big Cynthiana Road

  • Water Main Installation - September 2022

  • Water Service Line Installation (individual customer outages) - October 2022

  • Water Main Final Connections (water main outages) - October 2022

  • Restoration (pavement patching, lawn seeding) - November 2022