Red Bank Road Water Main Replacement
This project would include the installation of over 16,000 feet of new 12” and 16” water main pipe. Related improvements would include new valves and fire hydrants along Upper Mount Vernon Road to New Harmony Road, east of Red Bank Road and on Red Bank Road.
This project is anticipated to begin in November 2021 with an estimated completion date of November 2022.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - United Consulting Engineers
Indianapolis, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor- Miller Pipeline, LLC
Indianapolis, Indiana

Road Closures
Click HERE for updated road closures.

Boil Advisory Information
Click HERE for the latest boil advisory information
Project Update
Recent Progress (January 22 to January 28)
-
Miller Pipeline completed installation of 16” PVC C-900 water main on New Harmony Rd between N. Red Bank Rd and Resurrection Dr, pipe run 14.
-
Miller Pipeline started installation of 16” PVC C-900 water main on New Harmony Rd between Resurrection Dr and Big Cynthiana Rd, pipe run 15.
-
SpectraTech completed full depth sealing of the existing structure at 3019 N. Red Bank.
-
Miller Pipeline completed the fire hydrant assembly at 5601 New Harmony and the intersection of Resurrection Dr and New Harmony Rd.
Anticipated Activities for Upcoming Week (January 29 to February 4)
-
ABC Saw Cutting intends to perform advanced saw cutting on New Harmony Rd between Resurrection Dr to just east of Big Cynthiana Rd.
-
Miller Pipeline intends to pot hole existing utilities between Resurrection Dr to just east of Big Cynthiana Rd on New Harmony Rd.
-
Miller Pipeline intends to continue installation of 16” PVC C-900 water main on New Harmony Rd between Resurrection Dr and Big Cynthiana Rd, pipe run 15.
Project Schedule
Red Bank Road, from West Haven Drive to New Harmony Road
-
Water Main Installation - Complete
-
Water Service Line Installation (individual customer outages) - Complete
-
Water Main Final Connections (water main outages) - Complete
-
Restoration (pavement patching, lawn seeding) - April 2023
New Harmony Road, from Red Bank Road to Big Cynthiana Road
-
Water Main Installation - January 2023 to March 2023
-
Water Service Line Installation (individual customer outages) - February 2023 to March 2023
-
Water Main Final Connections (water main outages) - March 2023
-
Restoration (pavement patching, lawn seeding) - April 2023