Red Bank Road Water Main Replacement 

U1025 Red Bank Road (7)
U1025 Red Bank Road (7)

press to zoom
U1025 Red Bank Road (8)
U1025 Red Bank Road (8)

press to zoom
U1025 Red Bank Road (4)
U1025 Red Bank Road (4)

press to zoom
U1025 Red Bank Road (7)
U1025 Red Bank Road (7)

press to zoom
1/5

This project would include the installation of over 16,000 feet of new 12” and 16” water main pipe. Related improvements would include new valves and fire hydrants along Upper Mount Vernon Road to New Harmony Road, east of Red Bank Road and on Red Bank Road.

This project is anticipated to begin in November 2021 with an estimated completion date of November 2022. 

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - United Consulting Engineers

Indianapolis, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Miller Pipeline, LLC

Indianapolis, Indiana

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (September 11 to September 17)

  • Miller Pipeline began installing new 12” C900 PVC water main on Red Bank Road between West Haven Drive and Weathervane Lane.

  • Miller Pipeline completed the connection of new ¾”-1” water services on Red Bank Road between Barbara Jane Lane and Melody Lane.

  • Miller Pipeline completed the connection of the new 12” C900 PVC water main to the existing water main on Red Bank Raod at West Haven Drive.

  • Miller Pipeline cut and capped the existing water main in Red Bank Road at Upper Mt. Vernon Road.

  • Miller Pipeline installed HMA base on Red Bank Road between Upper Mt. Vernon Road and Barbara Jane Lane.

  • Miller Pipeline grout filled the abandoned 6” water main on Red Bank between Upper Mt. Vernon Road and Barbara Jane Lane.

 Anticipated Activities for Upcoming Week (September 18 to September 24)

  • Miller Pipeline intends to continue installing new 12” C900 PVC water main on Red Bank Road between West Haven Drive and Weathervane Lane.

Project Schedule

Upper Mt. Vernon Road, from Vanness Avenue to Red Bank Road​

  • Water Main Installation - Complete

  • Water Service Line Installation (individual customer outages) - Complete

  • Water Main Final Connections (water main outages) - Complete

  • Restoration (pavement patching, lawn seeding) - Complete

Red Bank Road, from Upper Mt. Vernon Road to New Harmony Road

  • Water Main Installation - May to August 2022

  • Water Service Line Installation (individual customer outages) - June to September 2022

  • Water Main Final Connections (water main outages) - July to September 2022

  • Restoration (pavement patching, lawn seeding) - September 2022

New Harmony Road, from Red Bank Road to Big Cynthiana Road

  • Water Main Installation - September 2022

  • Water Service Line Installation (individual customer outages) - October 2022

  • Water Main Final Connections (water main outages) - October 2022

  • Restoration (pavement patching, lawn seeding) - November 2022