top of page

Red Bank Road Water Main Replacement 

U1025 Red Bank Road (13)
U1025 Red Bank Road (13)

press to zoom
U1025 Red Bank Road (12)
U1025 Red Bank Road (12)

press to zoom
U1025 Red Bank Road (4)
U1025 Red Bank Road (4)

press to zoom
U1025 Red Bank Road (13)
U1025 Red Bank Road (13)

press to zoom
1/10

This project would include the installation of over 16,000 feet of new 12” and 16” water main pipe. Related improvements would include new valves and fire hydrants along Upper Mount Vernon Road to New Harmony Road, east of Red Bank Road and on Red Bank Road.

This project is anticipated to begin in November 2021 with an estimated completion date of November 2022. 

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - United Consulting Engineers

Indianapolis, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Miller Pipeline, LLC

Indianapolis, Indiana

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Project Update

 

Recent Progress (January 22 to January 28)

  • Miller Pipeline completed installation of 16” PVC C-900 water main on New Harmony Rd between N. Red Bank Rd and Resurrection Dr, pipe run 14.

  • Miller Pipeline started installation of 16” PVC C-900 water main on New Harmony Rd between Resurrection Dr and Big Cynthiana Rd, pipe run 15. 

  • SpectraTech completed full depth sealing of the existing structure at 3019 N. Red Bank.  

  • Miller Pipeline completed the fire hydrant assembly at 5601 New Harmony and the intersection of Resurrection Dr and New Harmony Rd. 

 Anticipated Activities for Upcoming Week (January 29 to February 4)

  • ABC Saw Cutting intends to perform advanced saw cutting on New Harmony Rd between Resurrection Dr to just east of Big Cynthiana Rd.

  • Miller Pipeline intends to pot hole existing utilities between Resurrection Dr to just east of Big Cynthiana Rd on New Harmony Rd. 

  • Miller Pipeline intends to continue installation of 16” PVC C-900 water main on New Harmony Rd between Resurrection Dr and Big Cynthiana Rd, pipe run 15. 

Project Schedule

Red Bank Road, from West Haven Drive to New Harmony Road

  • Water Main Installation - Complete

  • Water Service Line Installation (individual customer outages) - Complete

  • Water Main Final Connections (water main outages) - Complete

  • Restoration (pavement patching, lawn seeding) - April 2023

New Harmony Road, from Red Bank Road to Big Cynthiana Road

  • Water Main Installation - January 2023 to March 2023

  • Water Service Line Installation (individual customer outages) - February 2023 to March 2023

  • Water Main Final Connections (water main outages) - March 2023

  • Restoration (pavement patching, lawn seeding) - April 2023

bottom of page