Red Bank Road Water Main Replacement
This project would include the installation of over 16,000 feet of new 12” and 16” water main pipe. Related improvements would include new valves and fire hydrants along Upper Mount Vernon Road to New Harmony Road, east of Red Bank Road and on Red Bank Road.
This project is anticipated to begin in November 2021 with an estimated completion date of November 2022.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - United Consulting Engineers
Indianapolis, IN
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor- Miller Pipeline, LLC
Indianapolis, IN

Road Closures
Click HERE for updated road closures.

Boil Advisory Information
Click HERE for the latest boil advisory information

Alerts and Announcements
Click HERE for alerts and announcements.
Project Update
Recent Progress (June 19 to June 25)
-
Miller Pipeline continued installing new 12” C900 PVC water main on Red Bank between 1700 N. Red Bank Road (STA. 96+20) and Barbara Jane Lane – Test Section #6.
-
Miller Pipeline began installing HMA base on Red Bank between Upper Mt. Vernon Rd. and 1406 Red Bank Rd. (STA. 105+90) – Test Section #4.
Anticipated Activities for Upcoming Week (June 26 to July 2)
-
Miller Pipeline intends to complete the installation of new 12” C900 PVC water main on Red Bank between 1700 N. Red Bank Road (STA. 96+20) and Barbara Jane Lane – Test Section #6.
-
Miller Pipeline intends to activate the new 12” C900 PVC water main on Red Bank between 1406 N. Red Bank Road (STA. 105 +90) and 1700 N. Red Bank Road (STA. 96+20) – Test Section #5.
-
Miller Pipeline intends to begin connecting new ¾”-1” water services on Red Bank between 1406 N. Red Bank Road (STA. 105 +90) and 1700 N. Red Bank Road (STA. 96+20) – Test Section #5.
-
Miller Pipeline intends to complete the installation of HMA base on Red Bank between Upper Mt. Vernon and 1406 N. Red Bank Road (STA. 105+90) – Test Section #4.
Project Schedule
Upper Mt. Vernon Road, from Vanness Avenue to Red Bank Road
-
Water Main Installation - Complete
-
Water Service Line Installation (individual customer outages) - Complete
-
Water Main Final Connections (water main outages) - Complete
-
Restoration (pavement patching, lawn seeding) - Complete
Red Bank Road, from Upper Mt. Vernon Road to New Harmony Road
-
Water Main Installation - May to August 2022
-
Water Service Line Installation (individual customer outages) - June to September 2022
-
Water Main Final Connections (water main outages) - July to September 2022
-
Restoration (pavement patching, lawn seeding) - September 2022
New Harmony Road, from Red Bank Road to Big Cynthiana Road
-
Water Main Installation - September 2022
-
Water Service Line Installation (individual customer outages) - October 2022
-
Water Main Final Connections (water main outages) - October 2022
-
Restoration (pavement patching, lawn seeding) - November 2022