Claremont, Bosse and Craig Water Main Replacement

U1026 Claremont (1)
U1026 Claremont (1)

press to zoom
U1026 Claremont (4)
U1026 Claremont (4)

press to zoom
U1026 Claremont (3)
U1026 Claremont (3)

press to zoom
1/4

This project includes the installation of approximately 8,800 feet of new 8” and 12” water main pipe and related improvements throughout the project area.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Clark Dietz, Inc. 

Evansville, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Infrastructure Systems, Inc.

Orleans, IN

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

Recent Progress (June 19 to June 25) 

  • Infrastructure Systems completed the installation of new 8” C900 PVC water main on Claremont between Dreier and Sonntag.

  • Infrastructure Systems began installing new 8” C900 PVC water main on Claremont between Sonntag and Barker.

  • Infrastructure Systems began connecting new ¾”-2” water services on Bosse between Claremont and Schaeffer.

  • Infrastructure Systems performed hydrostatic testing and chlorinated the new 8” C900 PVC water main on Claremont between Dreier and Sonntag.

 Anticipated Activities for Upcoming Week (June 26 to July 2) 

  • Infrastructure Systems Systems intends to begin the installation of new 24” steel casing pipe by jack and bore on Barker at the CSX Railroad crossing.

  • Infrastructure Systems intends to continue installing new 8” C900 PVC water main on Claremont between Sonntag and Barker.

  • Infrastructure Systems intends to begin installing new 8” C900 PVC water main on Claremont between Barker and Center.

  • Infrastructure Systems intends to complete the connection of new ¾”-2” water services on Bosse between Claremont and Schaeffer.

Project Schedule

  • S. Bosse Avenue - Schaeffer Avenue to Claremont Avenue

    • Water Main Installation – Complete

    • Water Service Connections – Early July 2022

    • Final Connections – Early July 2022

    • Restoration – Mid July 2022 to Late July 2022

  • ​Claremont Avenue – S. Bosse Avenue to S. Tekoppel Avenue

    • Water Main Installation – June 2022

    • Water Service Connections – Early July 2022

    • Final Connections – Mid August 2022

    • Restoration – Late August 2022

  • ​Craig Avenue – Claremont Avenue to Carpenter Creek

    • Water Main Installation – Early August 2022

    • Water Service Connections – Mid August 2022

    • Final Connections – Mid August 2022

    • Restoration – Late August 2022

  • ​Claremont Avenue – S. Bosse Avenue to Boehne Avenue

    • Water Main Installation – Complete

    • Water Service Connections – Complete

    • Final Connections – Complete

    • Restoration – Complete

  • ​Boehne Avenue – South of Claremont Avenue

    • Water Main Installation – Complete

    • Water Service Connections – Late June 2022

    • Final Connections – Early July 2022

    • Restoration – Mid July 2022 to Late July 2022

  • ​Boehne Avenue – North of Claremont Avenue

    • Water Main Installation – Complete

    • Water Service Connections – Late June 2022 

    • Final Connections – Early July 2022

    • Restoration – Mid July 2022 to Late July 2022

  • ​Claremont Avenue – S. Tekoppel Avenue to S. Barker Avenue

    • Water Main Installation – July 2022

    • Water Service Connections – August 2022

    • Final Connections – Mid September 2022

    • Restoration – Late September 2022

  • Claremont Avenue – S. Barker Ave. to Ray Becker Parkway

    • Water Main Installation – Late June 2022 to Early July 2022

    • Water Service Connections – Early August 2022

    • Final Connections – Mid September 2022

    • Restoration – Early October 2022

  • Barker Avenue CSX Railroad Bore

    • Water Main Installation – Late June 2022 to Late July 2022

    • Restoration – Early August 2022
       

  • ​S. Barker Avenue – CSX Railroad to Claremont Avenue

    • Water Main Installation – Late June 2022

    • Water Service Connections – Late August 2022

    • Final Connections – Mid September 2022

    • Restoration – Early October 2022

  • ​S. Barker Avenue – B Street to Claremont Avenue

    • Water Main Installation – Early July 2022 to Mid July 2022

    • Water Service Connections – Early September 2022

    • Final Connections – Mid September 2022

    • Restoration – Mid October 2022