Stanley Avenue, Governor to Kerth Water Main Replacement

This project includes the installation of approximately 5,600 feet of 8” water main pipe and related improvements along Stanley Avenue between Governor Street and Kerth Avenue

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - United Consulting

Indianapolis, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor: Deig Brothers Lumber and Construction Co.,Inc.

Evansville, Indiana

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Project Update

 

Recent Progress 

  • The preconstruction meeting was held on February 28, 2023. 

Anticipated Activities for Upcoming Week 

  • No work is anticipated onsite.   The project is scheduled to begin in late May. 