Stanley Avenue, Governor to Kerth Water Main Replacement

This project includes the installation of approximately 5,600 feet of 8” water main pipe and related improvements along Stanley Avenue between Governor Street and Kerth Avenue

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - United Consulting

Indianapolis, Indiana

Construction Engineering Services - American Structurepoint, Inc.

Evansville, Indiana

Contractor: Deig Brothers Lumber and Construction Co.,Inc.

Evansville, Indiana

Road Closures and Boil Advisories

Click HERE

Project Update

 

  • Recent Progress (August 27 to September 2)

    • Deig Brothers completed the installation of compacted aggregate on Stanley Avenue between Governor Street and Stringtown Road.

    • CE Hughes completed the milling of existing asphalt pavement on Stanley Avenue between Governor Street and Stringtown Road.

    • E&B Paving completed the installation of HMA pavement on Stanley Avenue between Governor Street and Stringtown Road.

  • Anticipated Activities for Upcoming Week (September 3 to September 9) 

    • Deig intends to continue installing 8” C900 PVC water main on Stanley Avenue between Stringtown Road and Kentucky Avenue.

  • Active and Scheduled Road Closures

    • Active

      • Stanley Avenue, from Stringtown Road to Kentucky Avenue– Local Traffic Only

    • Scheduled

      • No upcoming closures scheduled at this time.

Project Schedule

Stanley Avenue, from Governor Street to Stringtown Road

Water Services Installation – Complete

Final Connections – Complete

Restoration (Lawns and Pavement) – Complete

 

Stringtown Road at Stanley Avenue

Water Main Installation – Complete

Restoration – Complete

 

Stanley Avenue, from Stringtown Road to Evans Avenue

Water Main Installation – Ongoing

Water Services Installation – Ongoing

Final Connections – Mid December to Mid January 2023

Restoration (Lawns and Pavement) – Mid December to Mid January 2023

 

Stanley Avenue, from Evans Avenue to Stanley Place

Water Main Installation – Ongoing

Water Services Installation – Late September to Mid October 2023

Final Connections – Mid December to Mid January 2023

Restoration (Lawns and Pavement) –Mid December to Mid January 2023

 

Stanley Avenue, from Stanley Place to Kentucky Avenue

Water Main Installation – Late September to Mid October 2023

Water Services Installation – Late September to Mid October 2023

Final Connections –Mid December to Mid January 2023

Restoration (Lawns and Pavement) – Mid December to Mid January 2023

Kentucky Avenue at Stanley Avenue

Water Main Installation – Mid October 2023

Pavement Restoration – Early November 2023

 

Stanley Avenue, from Kentucky Avenue to New York Avenue

Water Main Installation –Early October to Early November 2023

Water Services Installation – Mid October 2023 to Early November 2023

Final Connections – 2023 Mid December to Mid January 2023

Restoration (Lawns and Pavement) – Mid December to Mid January 2023

 

Stanley Avenue, from New York Avenue to Kerth Avenue

Water Main Installation – Early November 2023 to Mid November 2023

Water Services Installation – Early November to Mid November 2023

Final Connections – Mid November to Mid December 2023

Restoration (Lawns and Pavement) – Mid December to Mid January 2023