Stanley Avenue, Governor to Kerth Water Main Replacement


This project includes the installation of approximately 5,600 feet of 8” water main pipe and related improvements along Stanley Avenue between Governor Street and Kerth Avenue
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - United Consulting
Indianapolis, Indiana
Construction Engineering Services - American Structurepoint, Inc.
Evansville, Indiana
Contractor: Deig Brothers Lumber and Construction Co.,Inc.
Evansville, Indiana

Road Closures and Boil Advisories
Click HERE
Project Update
-
Recent Progress (August 27 to September 2)
-
Deig Brothers completed the installation of compacted aggregate on Stanley Avenue between Governor Street and Stringtown Road.
-
CE Hughes completed the milling of existing asphalt pavement on Stanley Avenue between Governor Street and Stringtown Road.
-
E&B Paving completed the installation of HMA pavement on Stanley Avenue between Governor Street and Stringtown Road.
-
-
Anticipated Activities for Upcoming Week (September 3 to September 9)
-
Deig intends to continue installing 8” C900 PVC water main on Stanley Avenue between Stringtown Road and Kentucky Avenue.
-
-
Active and Scheduled Road Closures
-
Active
-
Stanley Avenue, from Stringtown Road to Kentucky Avenue– Local Traffic Only
-
-
Scheduled
-
No upcoming closures scheduled at this time.
-
-
Project Schedule
Stanley Avenue, from Governor Street to Stringtown Road
Water Services Installation – Complete
Final Connections – Complete
Restoration (Lawns and Pavement) – Complete
Stringtown Road at Stanley Avenue
Water Main Installation – Complete
Restoration – Complete
Stanley Avenue, from Stringtown Road to Evans Avenue
Water Main Installation – Ongoing
Water Services Installation – Ongoing
Final Connections – Mid December to Mid January 2023
Restoration (Lawns and Pavement) – Mid December to Mid January 2023
Stanley Avenue, from Evans Avenue to Stanley Place
Water Main Installation – Ongoing
Water Services Installation – Late September to Mid October 2023
Final Connections – Mid December to Mid January 2023
Restoration (Lawns and Pavement) –Mid December to Mid January 2023
Stanley Avenue, from Stanley Place to Kentucky Avenue
Water Main Installation – Late September to Mid October 2023
Water Services Installation – Late September to Mid October 2023
Final Connections –Mid December to Mid January 2023
Restoration (Lawns and Pavement) – Mid December to Mid January 2023
Kentucky Avenue at Stanley Avenue
Water Main Installation – Mid October 2023
Pavement Restoration – Early November 2023
Stanley Avenue, from Kentucky Avenue to New York Avenue
Water Main Installation –Early October to Early November 2023
Water Services Installation – Mid October 2023 to Early November 2023
Final Connections – 2023 Mid December to Mid January 2023
Restoration (Lawns and Pavement) – Mid December to Mid January 2023
Stanley Avenue, from New York Avenue to Kerth Avenue
Water Main Installation – Early November 2023 to Mid November 2023
Water Services Installation – Early November to Mid November 2023
Final Connections – Mid November to Mid December 2023
Restoration (Lawns and Pavement) – Mid December to Mid January 2023