Hogue Road Water Main Improvements 

W11110 Hogue Road
W11110 Hogue Road

press to zoom
W11110 Hogue Road (8)
W11110 Hogue Road (8)

press to zoom
W11110 Hogue Road (7)
W11110 Hogue Road (7)

press to zoom
1/6

This project includes the installation of approximately 8,000 feet of new 4"-12" water main pipe along Hogue Road as well as related improvements throughout the project area.

Construction is anticipated to begin in Summer 2021.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Black & Veatch

Indianapolis, IN

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Infrastructure Systems, Inc.

Orleans, IN

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

Recent Progress (June 19 to June 25)

  • Infrastructure Systems completed hydrostatic testing and chlorinated the main on Hogue Road between 5700 Hogue Road (station 52+80) to 409 Red Bank Road (Station 79+50).

  • Infrastructure Systems began paving HMA Base on Hogue Road between Boehne Camp Road and Red Bank Road.

 Anticipated Activities for Upcoming Week (June 26 to July 2) 

  • Infrastructure Systems intends to start new ¾” to 1” water service relocations between 5700 Hogue Road (station 52+80) to Red Bank Road (station 79+50) pending water quality testing.

  • Infrastructure Systems intends to continue paving HMA Base and start HMA surface on Hogue Road between Williams Road and Miller Road.

Project Schedule

  • Hogue Road – Williams Road to Boehne Camp Road

    • Water Main Installation - Complete

    • Water Service Line Installation (individual customer outages) - Complete

    • Water Main Final Connections (water main outages) - Complete

    • Restoration (pavement patching, lawn seeding) - Ongoing

  • Hogue Road and Boehne Camp Road Intersection

    • Complete

  • Hogue Road and Boehne Camp Road Intersection

    • Water Main Installation - Late April to June 2022

    • Water Service Line Installation (individual customer outages) - Mid May to Late June 2022

    • Water Main Final Connections (water main outages) - Late June 2022

    • Restoration (pavement patching, lawn seeding) - Early July 2022