Charlotte Avenue and Russell Avenue Water Main Replacement

U1071 Charlotte Russell (1)
U1071 Charlotte Russell (1)

press to zoom
U1071 Charlotte Russell (2)
U1071 Charlotte Russell (2)

press to zoom
U1071 Charlotte Russell (3)
U1071 Charlotte Russell (3)

press to zoom
1/3

This project includes the installation of approximately 2,800 feet of new 8” and 12” water main pipe and related improvements on Charlotte Avenue, Russell Avenue and Bement Avenue area.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Beam,Longest & Neff

Evansville, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor: Blankenberger Brothers, Inc.

Cynthiana, Indiana

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (June 19 to June 25) 

  • Blankenberger continued installing new 8” C900 PVC water main on Russell between Ruby and Albert.

  • Blankenberger began installing concrete pavement base on Charlotte between Bement and Ruby, and on Russell between Bement and Charlotte

Anticipated Activities for Upcoming Week (June 26 to July 2)

  • Blankenberger intends to complete the installation of new 8” C900 PVC water main on Russell between Ruby and Albert.

  • Blankenberger intends to complete the installation of concrete pavement base on Charlotte between Bement and Ruby.

  • Blankenberger intends to continue installing concrete pavement base on Russell between Bement and Charlotte.

Project Schedule

  • ​Bement Avenue – Russel Avenue to Charlotte Avenue

    • Water Main Installation – Complete

    • Water Service Connections – May 2022

    • Final Connections – May 2022

    • Restoration – May 2022

  • ​Charlotte Avenue – Bement Avenue to Russell Avenue

    • Water Main Installation – Complete

    • Water Service Connections – May 2022

    • Final Connections – May 2022

    • Restoration – Late May 2022

  • ​Russell Avenue – Bement Avenue to Charlotte Avenue

    • Water Main Installation – May 2022

    • Water Service Connections – May 2022

    • Final Connections – June 2022

    • Restoration – July 2022

  • ​Russell Avenue – Charlotte Avenue to Albert Avenue

    • Water Main Installation – June 2022

    • Water Service Connections – June 2022

    • Final Connections – June 2022

    • Restoration – July 2022