Evans & Louisiana Water Main Replacement
This project includes the installation of approximately 1,400 feet of water main pipe. The installation will occur on Lousisana Street, East of Evans Avenue and within a dedicated easement, north of Louisiana Street.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - Crawford, Murphy & Tilly, Inc.
Evansville, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor: Koberstein Contracting.,Inc.
Evansville, Indiana
Project Update
Recent Progress (January 22 to January 28)
-
Professional Concrete saw cut the watermain trench from 8+60 to near 0+00.
-
Koberstein installed 12” C900 Water Main on Chrysler Rd from 8+60 to 7+50
Anticipated Activities for Upcoming Week (January 29 to February 4)
-
Koberstein will continue to install 12” C900 Water Main on Chrysler Rd from 7+50 towards E. Louisiana Street.