Corbierre Ave. Ph. 1, Tekoppel to Ingle

This project involves the replacement of 8" water main with 1,042 LF of 8" from Tekoppel Avenue to Ingle Avenue. This relocation is in preparation for road improvements planned for this area as part of the Lloyd4U project.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

​

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

​

Project Designer - Lochmueller Group

Evansville, Indiana

​

Construction Engineering Services - American Structurepoint, Inc.

Evansville, Indiana

​

Contractor- Ragle, Inc.

Newburgh, Indiana

​

​

Road Closures and Boil Advisories

Click HERE

Project Update
  •     Recent Progress (March 2 to March 8)
    •    Ragle completed installation of the 8” C-900 water main on Corbierre Ave to Walker Ave.

​

  •     Anticipated Activities for the Upcoming Week (March 9 to March 15)  
    •    Ragle intends to hydrostatically test and chlorinate the new 8” water main between Tekoppel Ave and Walker Ave on Corbierre Ave.   

     

Active and Scheduled Closures

Active​

  • Corbierre between Tekoppel and Ingle

​

Scheduled

  • ​No additional closures scheduled in the immediate future. 

​

Project Schedule​

  • Install and test water main from Tekoppel to Walker - February 5 to March 14, 2025

  • Install and test water main from Walker to Ingle - March 17 to March 28, 2025

  • Install services on new water main - March 31 to April 11, 2025

  • Abandon existing water main - April 14 to April 18, 2025