SR 62 from Tekoppel to Wabash




​This project involves the installation of 1,260 LF of 8", 3,710 LF of 12", and 2,940 LF of 24" water main from Tekoppel to 9th Avenue. This relocation is in preparation for road improvements planned for this area as part of the Lloyd4U project.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
​
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
​
Project Designer - United Consulting Engineers
Indianapolis, Indiana
​
Construction Engineering Services - American Structurepoint, Inc.
Evansville, Indiana
​
Contractor- Blankenberger Brothers, Inc.
Cynthiana, IN
​
​
Project Update
-
Recent Progress (March 1 to March 7)
-
Blankenberger verified the locations of the existing utilities on Lemcke Avenue south of Lloyd Expressway.
-
Blankenberger verified the locations of the existing utilities on 9th Avenue between Pennsylvania Avenue and Ohio Street.
-
Blankenberger began excavating the bore pit at Lemcke Avenue and the Lloyd Expressway.
-
Blankenberger installed HMA pavement on Indiana Street from Bell Avenue to Lemcke Avenue.
-
Blankenberger installed HMA pavement on Lemcke Avenue from Indiana Street to Illinois Street.
-
Blankenberger cut and capped the existing 10” water main on Ohio Street.
-
Blankenberger installed steel bollards around the fire hydrant assembly on 10th Street.
-
Blankenberger grout filled the existing 24” water main on 12th Avenue from the Lloyd Expressway to Indiana Street.
-
Blankenberger grout filled the existing 12” water main on Igleheart Avenue.
-
​
-
Anticipated Activities for Upcoming Week (March 8 to March 14)
-
Blankenberger intends to continue excavating the bore pit and the receiving pit at Lemcke Avenue and the Lloyd Expressway.
-
Blankenberger intends to begin installing HMA pavement on Ohio Street between CSX Railroad and 9th Avenue.
-
Blankenberger intends to begin installing HMA pavement at Igleheart Avenue.
-
Blankenberger intends to continue installing HMA pavement throughout the project corridor.
-
Blankenberger intends to connect the new 12” C900 PVC water main to the existing water main on Indiana Street at Bell Avenue.
-
Blankenberger intends to connect the new 12” C900 PVC water main to the existing water main on Indiana Street at Lemcke Avenue.
-
​
Active and Scheduled Closures
Active​​
-
St. Joseph Avenue from Lloyd Expressway to Franklin Street- Lane Restriction​
-
ï‚§9th Avenue from Ohio Street to Indiana Street - Local traffic only
-
Indiana Street from 9th Ave. to St. Joseph Ave.- Lane Restriction
-
Indiana Street from Lemcke Ave. to St. Joseph Ave. - Local traffic only
-
10th Avenue at Indiana Street - Closed
-
11th Avenue at Indiana Street - Closed
-
12th Avenue at Indiana Street - Closed
-
Lloyd Expressway Off-ramp at Igleheart Avenue - Lane Restriction
-
Lemcke Avenue from St. Joseph Ave. to Franklin Street - Lane Restriction
-
Ohio Street, Fulton to Wabash- Closed
​
Scheduled​
-
No additional closures currently scheduled
​
Project Schedule​
-
9th Avenue – from Pennsylvania Street to Indiana Street
-
Water Main Installation, Jack & Bore - Complete
-
Water Main Installation, Open Cut – Complete
-
Final Connections – Complete
-
Restoration, Lawns and Pavement – Ongoing
-
-
9th Avenue – Ohio Street to Pennsylvania Street
-
Water Main Installation –Ongoing
-
Storm Sewer Installation – Early February 2026
-
Water Service Line Installation – Early February 2026
-
Final Connections – February 2026
-
Restoration, Lawns and Pavement – March 2026
-
-
Ohio Street – 9th Avenue to Railroad Crossing (30 Day Full Closure)
-
Water Main Installation – February 2026
-
Storm Sewer Installation – February 2026
-
Water Service Line Installation –February 2026
-
Final Connections – February 2026
-
Restoration, Lawns and Pavement – February 2026
-
-
Indiana Street – 9th Avenue to Wabash Avenue
-
Water Main Installation – Complete
-
Water Service Line Installation – Complete
-
Final Connections – Complete
-
Restoration, Lawns and Pavement – Ongoing
-
-
Indiana Street – Wabash Avenue to 10th Avenue
-
Water Main Installation – Complete
-
Water Service Line Installation – Complete
-
Final Connections – Ongoing
-
Restoration, Lawns and Pavement – Ongoing
-
-
Wabash Avenue – Indiana Street to Lloyd Expressway
-
Water Main Installation – Complete
-
Water Service Line Installation – Complete
-
Final Connections – Complete
-
Restoration, Lawns and Pavement – Ongoing
-
-
10th Avenue, Indiana Street to Lloyd Expressway
-
Water Main Installation – Complete
-
Water Service Line Installation – Complete
-
Final Connections – Complete
-
Restoration, Lawns and Pavement – Ongoing
-
-
Indiana Street – 10th Avenue to 12th Avenue
-
Water Main Installation – Complete
-
Water Service Connections – Complete
-
Final Connections – Complete
-
Restoration, Lawns and Pavement – Ongoing
-
-
Indiana Street – 12th Avenue to St. Joseph Avenue
-
Water Main Installation - Complete
-
Water Service Connections – Complete
-
Final Connections – Complete
-
Restoration, Lawns and Pavement – Ongoing
-
-
12th Avenue – Indiana Street to Lloyd Expressway
-
Water Main Installation – Complete
-
Water Service Connections – Complete
-
Final Connections – Ongoing
-
Restoration, Lawns and Pavement – Ongoing
-
-
Indiana Street – St. Joseph Avenue to Lemcke Avenue
-
Water Main Installation – Complete
-
Water Service Installation – February 2026
-
Final Connections – February 2026
-
Restoration, Lawns and Pavement – March 2026
-
-
St. Joseph Avenue – Indiana Street to Lloyd Expressway
-
Water Main Installation, Jack & Bore – Ongoing
-
Water Main Installation, Open Cut – Ongoing
-
Water Service Connections – March 2026
-
Final Connections – March 2026
-
Restoration, Lawns and Pavement – March 2026
-
-
St. Joseph Avenue – Indiana Street to Illinois Street
-
Water Main Installation, Open Cut – Ongoing
-
Water Service Connections – Early February 2026
-
Final Connections – Early January 2026
-
Restoration, Lawns and Pavement – February 2026
-
-
Lemcke Avenue – Indiana Street to Illinois Street
-
Water Main Installation – Ongoing
-
Water Service Installation – February 2026
-
Final Connections – February 2026
-
Restoration, Lawns and Pavement – March 2026​
-
-
Lemcke Avenue – Illinois Street to Franklin Street
-
Water Main Installation – February 2026
-
Water Service Installation – February 2026
-
Final Connections – February 2026
-
Restoration, Lawns and Pavement – March 2026
-
-
Lemcke Avenue – Indiana Street to Pennsylvania Street (Lloyd Expressway)
-
Water Main Installation, Jack & Bore – February 2026
-
Water Main Installation, Open Cut – February 2026
-
Water Service Installation – February 2026
-
Final Connections – February 2026
-
Restoration, Lawns and Pavement – March 2026
-
-
Franklin Street & Mt. Vernon Avenue – Lemcke Avenue to Michigan Street
-
Water Main Installation – March 2026
-
Water Service Installation – March 2026
-
Final Connections – March 2026
-
Restoration, Lawns and Pavement – March 2026​
-
-
Pennsylvania Street – Lemcke Avenue to Rick Davis Way
-
Water Main Installation – March 2026
-
Water Service Installation – March 2026
-
Final Connections – March 2026
-
Restoration, Lawns and Pavement – March 2026
-
-
​Leslie Avenue, Forest Avenue to Igleheart Avenue
-
Water Main Installation – Complete
-
Water Service Installation – Complete
-
Final Connections – Ongoing
-
Restoration, Lawns and Pavement – February 2026​
-
-
Lloyd Expressway Off Ramp, Barker Avenue to Leslie Avenue
-
Lloyd Expressway, Leslie Avenue to Igleheart Avenue
-
Water Main Installation, Jack & Bore – Complete
-
Water Main Installation, Directional Drilling – Complete
-
Water Main Installation, Open Cut – Complete
-
Water Service Installation – Complete
-
Final Connections – Ongoing
-
Restoration, Lawns and Pavement – March 2026
-
