top of page

SR 62 from Tekoppel to Wabash

​This project involves the installation of 1,260 LF of 8", 3,710 LF of 12", and 2,940 LF of 24" water main from Tekoppel to 9th Avenue. This relocation is in preparation for road improvements planned for this area as part of the Lloyd4U project. 

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

​

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

​

Project Designer - United Consulting Engineers

Indianapolis, Indiana

​

Construction Engineering Services - American Structurepoint, Inc.

Evansville, Indiana

​

Contractor- Blankenberger Brothers, Inc. 

Cynthiana, IN

​

​

Project Update
  • Recent Progress (February 8 to February 14)

    • Blankenberger completed the installation of the new 12” C900 PVC water man on Ohio Street between 9th Avenue and the CSX Railroad Crossing.

    • Blankenberger performed hydrostatic testing and chlorinated the new 12” C900 PVC water man on Ohio Street between 9th Avenue and the CSX Railroad Crossing.

    • Blankenberger activated the new 12” C900 PVC water main on St. Joseph Avenue between Indiana Street and Illinois Street.

    • Blankenberger installed new ¾”-1” water service connections on St. Joseph Avenue between Indiana Street and Illinois Street.

    • Blankenberger completed the connection of the new 24” ductile iron water main to the existing 24” and 6” water mains at the intersection of Indiana Street and 12th Avenue.

    • Blankenberger installed new water pressure reducing valves and tandem water meter setters on Leslie Avenue.

    • Blankenberger chlorinated the new 12” C900 PVC water main on Indiana Street between           St. Joseph Avenue and Lemcke Avenue.

    • Blankenberger verified existing utilities at the intersection of Ohio Street and 9th Avenue.

​

  • Anticipated Activities for Upcoming Week (February 15 to February 21) 

    • Blankenberger intends to install HMA pavement restoration on St. Joseph Avenue between Indiana Street and Illinois Street.

    • Blankenberger intends to connect the new 12” C900 PVC water main to the existing 12” water main on St. Joseph Avenue between Indiana Street and Illinois Street.

    • Blankenberger intends to complete Phase 4 and Phase 5 of the Igleheart to Leslie Construction Sequencing.

    • Blankenberger intends to activate the new 12” C900 PVC water main on Indiana Street between St. Joseph Avenue and Lemcke Avenue, pending the results of water quality sampling.

    • Blankenberger intends to begin installing new water service connections on Indiana Street between St. Joseph Avenue and Lemcke Avenue, pending the results of water quality sampling.

​

Active and Scheduled Closures

Active​​

  • St. Joseph Avenue from Lloyd Expressway to Franklin Street- Lane Restriction​

  • ï‚§9th Avenue from Ohio Street to Indiana Street - Local traffic only 

  • Indiana Street from 9th Ave. to St. Joseph Ave.- Lane Restriction

  • Indiana Street from Lemcke Ave. to St. Joseph Ave. - Local traffic only 

  • 10th Avenue at Indiana Street - Closed 

  • 11th Avenue at Indiana Street - Closed

  • 12th Avenue at Indiana Street - Closed 

  • Lloyd Expressway Off-ramp at Igleheart Avenue - Lane Restriction

  • Lemcke Avenue from St. Joseph Ave. to Franklin Street - Lane Restriction 

  • Ohio Street, Fulton to Wabash- Closed 

​

Scheduled​

  • No additional closures currently scheduled

​

Project Schedule​

  • 9th Avenue – from Pennsylvania Street to Indiana Street

    • Water Main Installation, Jack & Bore - Complete

    • Water Main Installation, Open Cut – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Ongoing

  • 9th Avenue – Ohio Street to Pennsylvania Street

    • Water Main Installation –Ongoing

    • Storm Sewer Installation – Early February 2026

    • Water Service Line Installation – Early February 2026

    • Final Connections – February 2026

    • Restoration, Lawns and Pavement – March 2026

  • Ohio Street – 9th Avenue to Railroad Crossing (30 Day Full Closure)

    • Water Main Installation – February 2026

    • Storm Sewer Installation – February 2026

    • Water Service Line Installation –February 2026

    • Final Connections – February 2026

    • Restoration, Lawns and Pavement – February 2026

  • Indiana Street – 9th Avenue to Wabash Avenue

    • Water Main Installation – Complete

    • Water Service Line Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Ongoing

  • Indiana Street – Wabash Avenue to 10th Avenue

    • Water Main Installation – Complete

    • Water Service Line Installation – Complete

    • Final Connections – Ongoing

    • Restoration, Lawns and Pavement – Ongoing

  • Wabash Avenue – Indiana Street to Lloyd Expressway

    • Water Main Installation – Complete

    • Water Service Line Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Ongoing

  • 10th Avenue, Indiana Street to Lloyd Expressway

    • Water Main Installation – Complete

    • Water Service Line Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Ongoing

  • Indiana Street – 10th Avenue to 12th Avenue

    • Water Main Installation – Complete

    • Water Service Connections – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Ongoing

  • Indiana Street – 12th Avenue to St. Joseph Avenue

    • Water Main Installation - Complete

    • Water Service Connections – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Ongoing

  • 12th Avenue – Indiana Street to Lloyd Expressway

    • Water Main Installation – Complete

    • Water Service Connections – Complete

    • Final Connections – Ongoing

    • Restoration, Lawns and Pavement – Ongoing

  • Indiana Street – St. Joseph Avenue to Lemcke Avenue

    • Water Main Installation – Complete

    • Water Service Installation – February 2026

    • Final Connections – February 2026

    • Restoration, Lawns and Pavement – March 2026

  • St. Joseph Avenue – Indiana Street to Lloyd Expressway

    • Water Main Installation, Jack & Bore – Ongoing

    • Water Main Installation, Open Cut – Ongoing

    • Water Service Connections – March 2026

    • Final Connections – March 2026

    • Restoration, Lawns and Pavement – March 2026

  • St. Joseph Avenue – Indiana Street to Illinois Street

    • Water Main Installation, Open Cut – Ongoing

    • Water Service Connections – Early February 2026

    • Final Connections – Early January 2026

    • Restoration, Lawns and Pavement – February 2026

  • Lemcke Avenue –  Indiana Street to Illinois Street

    • Water Main Installation – Ongoing

    • Water Service Installation – February 2026

    • Final Connections – February 2026

    • Restoration, Lawns and Pavement – March 2026​

  • Lemcke Avenue –  Illinois Street to Franklin Street

    • Water Main Installation – February 2026

    • Water Service Installation – February 2026

    • Final Connections – February 2026

    • Restoration, Lawns and Pavement – March 2026

  • Lemcke Avenue – Indiana Street to Pennsylvania Street (Lloyd Expressway)

    • Water Main Installation, Jack & Bore – February 2026

    • Water Main Installation, Open Cut – February 2026

    • Water Service Installation – February 2026

    • Final Connections – February 2026

    • Restoration, Lawns and Pavement – March 2026

  • Franklin Street & Mt. Vernon Avenue – Lemcke Avenue to Michigan Street

    • Water Main Installation – March 2026

    • Water Service Installation – March 2026

    • Final Connections – March 2026

    • Restoration, Lawns and Pavement – March 2026​

  • Pennsylvania Street – Lemcke Avenue to Rick Davis Way

    • Water Main Installation – March 2026

    • Water Service Installation – March 2026

    • Final Connections – March 2026

    • Restoration, Lawns and Pavement – March 2026

  • ​Leslie Avenue, Forest Avenue to Igleheart Avenue

    • Water Main Installation – Complete

    • Water Service Installation – Complete

    • Final Connections – Ongoing

    • Restoration, Lawns and Pavement – February 2026​

  • Lloyd Expressway Off Ramp, Barker Avenue to Leslie Avenue 

  • Lloyd Expressway, Leslie Avenue to Igleheart Avenue

    • Water Main Installation, Jack & Bore – Complete

    • Water Main Installation, Directional Drilling – Complete

    • Water Main Installation, Open Cut – Complete

    • Water Service Installation – Complete

    • Final Connections – Ongoing

    • Restoration, Lawns and Pavement – March 2026

  • Twitter Social Icon

© 2017 American Structurepoint, Inc.

bottom of page