top of page

SR 62 from Tekoppel to Wabash

​This project involves the installation of 1,260 LF of 8", 3,710 LF of 12", and 2,940 LF of 24" water main from Tekoppel to 9th Avenue. This relocation is in preparation for road improvements planned for this area as part of the Lloyd4U project. 

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

​

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

​

Project Designer - United Consulting Engineers

Indianapolis, Indiana

​

Construction Engineering Services - American Structurepoint, Inc.

Evansville, Indiana

​

Contractor- Blankenberger Brothers, Inc. 

Cynthiana, IN

​

​

Project Update
  • Recent Progress (March 29 to April 4)

    • Blankenberger completed the installation of new 12” water main on Franklin Street between Lemcke Avenue and Mt. Vernon Avenue.

    • Blankenberger completed the installation of new 12” water main on Lemcke Avenue between Indiana Street and Pennsylvania Street.

    • Blankenberger completed the installation of new 12” water main on Pennsylvania Street between Lemcke Avenue and Rick Davis Way.

    • Blankenberger backfilled the bore pit and receiving pit at Lloyd Expressway and Lemcke Avenue.

    • Blankenberger performed hydrostatic testing and chlorinated the new 12” water main on Lemcke Avenue between Indiana Street and Pennsylvania Street.

    • Blankenberger completed the 2” cut and cap on Leslie Avenue at Forest Avenue.

    • Blankenberger installed the new air relief valve at Pennsylvania Street and Rick Davis Way.

    • Blankenberger performed lawn restoration activities on Indiana Street and Leslie Avenue.

    • Blankenberger removed abandoned valve boxes throughout the project corridor.

​

  • Anticipated Activities for Upcoming Week (April 5 to April 11) 

    • Blankenberger intends to activate the new 12” water main on Lemcke Avenue between Illinois Street and Franklin Street.

    • Blankenberger intends to complete the connection of the new 12” water main to the existing water main on Illinois Street south of Lemcke Avenue.

    • Blankenberger intends to activate the new 12” water main on Lemcke Avenue between Indiana Street and Pennsylvania Street, pending the results of water quality sampling.

    • Blankenberger intends to perform hydrostatic testing and chlorinate the new 12” water main on Franklin Street between Lemcke Avenue and Mt. Vernon Avenue.

    • Blankenberger intends to install new 12” water main on Mt. Vernon Avenue between Franklin Street and Michigan Street.

    • Infrastructure Systems intends to install a new 16”x12” tapping saddle and perform a 12” wet tap at the intersection of Michigan Street and Mt. Vernon Avenue.

    • MAMCO intends to perform milling of the existing HMA surface on Indiana Street between 9th Avenue and Lemcke Avenue.

    • E&B Paving intends to install HMA surface on Indiana Street between 9th Avenue and Lemcke Avenue.

​

Active and Scheduled Closures

Active​​

  • St. Joseph Avenue from Lloyd Expressway to Franklin Street- Lane Restriction​

  • ï‚§9th Avenue from Ohio Street to Indiana Street - Local traffic only 

  • Indiana Street from 9th Ave. to St. Joseph Ave.- Lane Restriction

  • Indiana Street from Lemcke Ave. to St. Joseph Ave. - Local traffic only 

  • 10th Avenue at Indiana Street - Closed 

  • 11th Avenue at Indiana Street - Closed

  • 12th Avenue at Indiana Street - Closed 

  • Lloyd Expressway Off-ramp at Igleheart Avenue - Lane Restriction

  • Lemcke Avenue from St. Joseph Ave. to Franklin Street - Lane Restriction 

  • Lemcke Avenue from Pennsylvania Street to Forest Ave.- Lane Restriction 

  • Franklin Street from St. Joseph Ave. to Sonntag Ave. - Local traffic only 

​

Scheduled​

  • Barker Ave. from Igleheart Ave. to Forest Ave- Lane Restrictions on/after 4/20/26

​

Project Schedule​

  • 9th Avenue – from Pennsylvania Street to Indiana Street

    • Water Main Installation, Jack & Bore - Complete

    • Water Main Installation, Open Cut – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Late June to Early July 2026

  • 9th Avenue – Ohio Street to Pennsylvania Street

    • Water Main Installation –Complete

    • Storm Sewer Installation – May 2026

    • Water Service Line Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Late June to Early July 2026

  • Ohio Street – 9th Avenue to Railroad Crossing (30 Day Full Closure)

    • Water Main Installation – Complete

    • Storm Sewer Installation – May 2026

    • Water Service Line Installation - Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – June 2026

  • Indiana Street – 9th Avenue to Wabash Avenue

    • Water Main Installation – Complete

    • Water Service Line Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Ongoing

  • Indiana Street – Wabash Avenue to 10th Avenue

    • Water Main Installation – Complete

    • Water Service Line Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Ongoing

  • Wabash Avenue – Indiana Street to Lloyd Expressway

    • Water Main Installation – Complete

    • Water Service Line Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Ongoing

  • 10th Avenue, Indiana Street to Lloyd Expressway

    • Water Main Installation – Complete

    • Water Service Line Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Ongoing

  • Indiana Street – 10th Avenue to 12th Avenue

    • Water Main Installation – Complete

    • Water Service Connections – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Ongoing

  • Indiana Street – 12th Avenue to St. Joseph Avenue

    • Water Main Installation - Complete

    • Water Service Connections – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Ongoing

  • 12th Avenue – Indiana Street to Lloyd Expressway

    • Water Main Installation – Complete

    • Water Service Connections – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Ongoing

  • Indiana Street – St. Joseph Avenue to Lemcke Avenue

    • Water Main Installation – Complete

    • Water Service Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Ongoing

  • St. Joseph Avenue – Indiana Street to Lloyd Expressway

    • Water Main Installation, Jack & Bore – Ongoing

    • Water Main Installation, Open Cut – Ongoing

    • Water Service Connections – Late June to Early July 2026

    • Final Connections – Late June to Early July 2026

    • Restoration, Lawns and Pavement – Late June to Early July 2026

  • St. Joseph Avenue – Indiana Street to Illinois Street

    • Water Main Installation, Open Cut – Complete

    • Water Service Connections – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Complete

  • Lemcke Avenue –  Indiana Street to Illinois Street

    • Water Main Installation – Complete

    • Water Service Installation – Ongoing

    • Final Connections – Ongoing

    • Restoration, Lawns and Pavement – Mid May to Late May 2026

  • Lemcke Avenue – Illinois Street to Franklin Street

    • Water Main Installation – Complete

    • Water Service Installation – Ongoing

    • Final Connections – Ongoing

    • Restoration, Lawns and Pavement – Mid May to Late May 2026

  • Lemcke Avenue – Indiana Street to Pennsylvania Street (Lloyd Expressway)

    • Water Main Installation, Jack & Bore – Complete

    • Water Main Installation, Open Cut – Complete

    • Water Service Installation – Complete

    • Final Connections – Ongoing

    • Restoration, Lawns and Pavement – Mid May to Late May 2026

  • Franklin Street - Lemcke Avenue to Mt. Vernon Avenue

    • Water Main Installation – Complete

    • Water Service Installation – Ongoing

    • Final Connections – Ongoing

    • Restoration, Lawns and Pavement – Mid May to Late May 2026

  • Mt. Vernon Avenue – Franklin Street to Michigan Street

    • Water Main Installation – Ongoing

    • Water Service Installation – Mid April to Late April 2026

    • Final Connections – Mid April to Late April 2026

    • Restoration, Lawns and Pavement – Mid May to Late May 2026

  • Pennsylvania Street – Lemcke Avenue to Rick Davis Way

    • Water Main Installation – Complete

    • Water Service Installation – Mid April 2026

    • Final Connections – Mid April 2026

    • Restoration, Lawns and Pavement – Mid May to Late May 2026

  • ​Leslie Avenue, Forest Avenue to Igleheart Avenue

    • Water Main Installation – Complete

    • Water Service Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Ongoing

  • Lloyd Expressway Off Ramp, Barker Avenue to Leslie Avenue 

  • Lloyd Expressway, Leslie Avenue to Igleheart Avenue

    • Water Main Installation, Jack & Bore – Complete

    • Water Main Installation, Directional Drilling – Complete

    • Water Main Installation, Open Cut – Complete

    • Water Service Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Ongoing

  • Barker Avenue at Pennsylvania Street

    • Water Main Installation – Late April 2026

    • Final Connections – Early May 2026

  • Twitter Social Icon

© 2017 American Structurepoint, Inc.

bottom of page