SR 62 from Tekoppel to Wabash




​This project involves the installation of 1,260 LF of 8", 3,710 LF of 12", and 2,940 LF of 24" water main from Tekoppel to 9th Avenue. This relocation is in preparation for road improvements planned for this area as part of the Lloyd4U project.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
​
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
​
Project Designer - United Consulting Engineers
Indianapolis, Indiana
​
Construction Engineering Services - American Structurepoint, Inc.
Evansville, Indiana
​
Contractor- Blankenberger Brothers, Inc.
Cynthiana, IN
​
​
Project Update
-
Recent Progress (October 19 to October 25)
-
Blankenberger continued to install 3/4" water service on Indiana street between Wabash Avenue and 12th Avenue.
-
Blankenberger continued to install the new 8" PVC C900 water main on 10th Avenue.
-
-
Anticipated Activities for Upcoming Week (October 19 to October 25)
-
Blankenberger intends to install 3/4" water service on Indiana street between Wabash Avenue and 12th Avenue.
-
Blankenberger intends to install the new 8" PVC C900 water main on 12th Avenue.
-
​
Active and Scheduled Closures
Active​​
-
St. Joseph Avenue from Lloyd Expressway to Illinois Street- Lane Restriction​
-
ï‚§9th Avenue from Ohio Street to Indiana Street - Closed
-
Indiana Street from 9th Ave. to St. Joseph Ave.- Lane Restriction
-
Indiana Street from Lemcke Ave. to St. Joseph Ave. -Closed
-
10th Avenue at Indiana Street - Closed
-
11th Avenue at Indiana Street - Closed
-
12th Avenue at Indiana Street - Closed
​
Scheduled
-
No additional closures scheduled at this time.
​
Project Schedule​
-
9th Avenue – from Pennsylvania Street to Indiana Street
-
Water Main Installation, Jack & Bore - Complete
-
Water Main Installation, Open Cut – Complete
-
Final Connections – Complete
-
Restoration, Lawns and Pavement – Late October 2025​​
-
-
9th Avenue – Ohio Street to Pennsylvania Street
-
Water Main Installation –December 2025
-
Storm Sewer Installation – December 2025
-
Water Service Line Installation – December 2025
-
Final Connections – December 2025
-
Restoration, Lawns and Pavement – December 2025​
-
-
Ohio Street – 9th Avenue to Railroad Crossing (30 Day Full Closure)
-
Water Main Installation – December 2025
-
Storm Sewer Installation – December 2025
-
Water Service Line Installation –December 2025
-
Final Connections – December 2025
-
Restoration, Lawns and Pavement – December 2025​
-
-
Indiana Street – 9th Avenue to Wabash Avenue
-
Water Main Installation – Complete
-
Water Service Line Installation – Complete
-
Final Connections – Complete
-
Restoration, Lawns and Pavement – Late October 2025​
-
-
Indiana Street – Wabash Avenue to 10th Avenue
-
Water Main Installation – Complete
-
Water Service Line Installation – Complete
-
Final Connections – October 2025
-
Restoration, Lawns and Pavement – Late October 2025​
-
-
Wabash Avenue – Indiana Street to Lloyd Expressway
-
Water Main Installation – Complete
-
Water Service Line Installation – Complete
-
Final Connections – Complete
-
Restoration, Lawns and Pavement – Late October 2025​​
-
-
10th Avenue, Indiana Street to Lloyd Expressway
-
Water Main Installation – Mid October 2025
-
Water Service Line Installation – Late October 2025
-
Final Connections – Late October 2025
-
Restoration, Lawns and Pavement – Late October 2025​​
-
-
Indiana Street – 10th Avenue to 12th Avenue
-
Water Main Installation – Complete
-
Water Service Connections – Ongoing
-
Final Connections – Late October
-
Restoration, Lawns and Pavement – Late October 2025​
-
-
Indiana Street – 12th Avenue to St. Joseph Avenue
-
Water Main Installation - Complete
-
Water Service Connections – Mid October 2025
-
Final Connections – Late Ocotber 2025
-
Restoration, Lawns and Pavement – Late October 2025​
-
-
12th Avenue – Indiana Street to Lloyd Expressway
-
Water Main Installation – Late November 2025
-
Water Service Connections – Early December 2025
-
Final Connections – Early December 2025
-
Restoration, Lawns and Pavement – Mid December 2025​​
-
-
Indiana Street – St. Joseph Avenue to Lemcke Avenue
-
Water Main Installation – Complete
-
Water Service Installation –Mid October 2025
-
Final Connections – Mid October 2025
-
Restoration, Lawns and Pavement – January 2026​
-
-
St. Joseph Avenue – Indiana Street to Lloyd Expressway
-
Water Main Installation, Jack & Bore – Ongoing
-
Water Main Installation, Open Cut – Ongoing
-
Water Service Connections – November 2025
-
Final Connections – November 2025
-
Restoration, Lawns and Pavement – November 2025​
-
-
Lemcke Avenue – Indiana Street to Illinois Street
-
Water Main Installation – Late October 2025
-
Water Service Installation – Early November 2025
-
Final Connections – Early November 2025
-
Restoration, Lawns and Pavement – January 2026​
-
-
Lemcke Avenue – Illinois Street to Franklin Street
-
Water Main Installation – Early November 2025
-
Water Service Installation – Mid November 2025
-
Final Connections – Mid November 2025
-
Restoration, Lawns and Pavement – January 2026​
-
-
Lemcke Avenue – Indiana Street to Pennsylvania Street (Lloyd Expressway)
-
Water Main Installation, Jack & Bore – Mid October 2025
-
Water Main Installation, Open Cut – Early November 2025
-
Water Service Installation – Mid November 2025
-
Final Connections – Mid November 2025
-
Restoration, Lawns and Pavement – January 2026​
-
-
Franklin Street & Mt. Vernon Avenue – Lemcke Avenue to Michigan Street
-
Water Main Installation – Mid November 2025
-
Water Service Installation – Early December 2025
-
Final Connections – Early December 2025
-
Restoration, Lawns and Pavement – January 2026​
-
-
Pennsylvania Street – Lemcke Avenue to Rick Davis Way
-
Water Main Installation – Late October 2025
-
Water Service Installation – Mid November 2025
-
Final Connections – Mid November 2025
-
Restoration, Lawns and Pavement – January 2025​​
-
-
​Leslie Avenue, Forest Avenue to Igleheart Avenue
-
Water Main Installation – Early November 2025
-
Water Service Installation – Mid November 2025
-
Final Connections – Mid November 2025
-
Restoration, Lawns and Pavement – January 2026​
-
-
Lloyd Expressway Off Ramp, Barker Avenue to Leslie Avenue
-
Lloyd Expressway, Leslie Avenue to Igleheart Avenue
-
Water Main Installation, Jack & Bore – Complete
-
Water Main Installation, Directional Drilling – Complete
-
Water Main Installation, Open Cut – Ongoing
-
Water Service Installation – Mid October 2025
-
Final Connections – Mid October 2025
-
Restoration, Lawns and Pavement – January 2026
-

