top of page

SR 62 from Tekoppel to Wabash

​This project involves the installation of 1,260 LF of 8", 3,710 LF of 12", and 2,940 LF of 24" water main from Tekoppel to 9th Avenue. This relocation is in preparation for road improvements planned for this area as part of the Lloyd4U project. 

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

​

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

​

Project Designer - United Consulting Engineers

Indianapolis, Indiana

​

Construction Engineering Services - American Structurepoint, Inc.

Evansville, Indiana

​

Contractor- Blankenberger Brothers, Inc. 

Cynthiana, IN

​

​

Project Update
  • Recent Progress (October 18 to October 24)

    • Road Safe installed pavement markings on Ohio Street, Franklin Street, and Mt. Vernon Street.

    • Blankenberger installed concrete curb and sidewalk at the intersection of Ohio St. and 9th St.

    • Blankenberger began installing HMA base on 9th St. between Ohio St. and Pennsylvania St.

    • Blankenberger performed grading and restoration work on Pennsylvania St. between 9th St. and Wabash Ave.

​

  • Anticipated Activities for Upcoming Week (October 25 to October 31) 

    • Blankenberger intends to complete grout filling and water main abandonment on Pennsylvania Street between 9th Street and Wabash Avenue, and on 9th Street between Pennsylvania Street and Indiana Street.

    • Blankenberger intends to continue performing concrete and HMA restoration on 9th Street between Ohio Street and Indiana Street.

    • Blankenberger intends to complete the installation of storm sewer inlet STR. No. 29.

​

Active and Scheduled Closures

Active​​​

  • 9th Avenue from Ohio Street to Indiana Street- Closed

​

Scheduled​

  • No additional closures scheduled at this time. 

​

Project Schedule​

  • 9th Avenue – from Pennsylvania Street to Indiana Street

    • Water Main Installation, Jack & Bore - Complete

    • Water Main Installation, Open Cut – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Complete

  • 9th Avenue – Ohio Street to Pennsylvania Street

    • Water Main Installation –Complete

    • Storm Sewer Installation – November 2026

    • Water Service Line Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – November 2026

  • Ohio Street – 9th Avenue to Railroad Crossing (30 Day Full Closure)

    • Water Main Installation – Complete

    • Storm Sewer Installation – Complete

    • Water Service Line Installation - Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Complete

  • Indiana Street – 9th Avenue to Wabash Avenue

    • Water Main Installation – Complete

    • Water Service Line Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Complete

  • Indiana Street – Wabash Avenue to 10th Avenue

    • Water Main Installation – Complete

    • Water Service Line Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Complete

  • Wabash Avenue – Indiana Street to Lloyd Expressway

    • Water Main Installation – Complete

    • Water Service Line Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Complete

  • 10th Avenue, Indiana Street to Lloyd Expressway

    • Water Main Installation – Complete

    • Water Service Line Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Complete

  • Indiana Street – 10th Avenue to 12th Avenue

    • Water Main Installation – Complete

    • Water Service Connections – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Complete

  • Indiana Street – 12th Avenue to St. Joseph Avenue

    • Water Main Installation - Complete

    • Water Service Connections – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Complete

  • 12th Avenue – Indiana Street to Lloyd Expressway

    • Water Main Installation – Complete

    • Water Service Connections – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Complete

  • Indiana Street – St. Joseph Avenue to Lemcke Avenue

    • Water Main Installation – Complete

    • Water Service Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Complete

  • St. Joseph Avenue – Indiana Street to Ohio Street

    • Water Main Installation, Open Cut – Complete

    • Water Service Connections –Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Complete

  • St. Joseph Avenue – Indiana Street to Illinois Street

    • Water Main Installation, Open Cut – Complete

    • Water Service Connections – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Complete

  • Lemcke Avenue –  Indiana Street to Illinois Street

    • Water Main Installation – Complete

    • Water Service Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Complete

  • Lemcke Avenue – Illinois Street to Franklin Street

    • Water Main Installation – Complete

    • Water Service Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Complete

  • Lemcke Avenue – Indiana Street to Pennsylvania Street (Lloyd Expressway)

    • Water Main Installation, Jack & Bore – Complete

    • Water Main Installation, Open Cut – Complete

    • Water Service Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Complete

  • Franklin Street - Lemcke Avenue to Mt. Vernon Avenue

    • Water Main Installation – Complete

    • Water Service Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Complete

  • Mt. Vernon Avenue – Franklin Street to Michigan Street

    • Water Main Installation – Complete

    • Water Service Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Complete

  • Pennsylvania Street – Lemcke Avenue to Rick Davis Way

    • Water Main Installation – Complete

    • Water Service Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Late June 2026

  • ​Leslie Avenue, Forest Avenue to Igleheart Avenue

    • Water Main Installation – Complete

    • Water Service Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Complete

  • Lloyd Expressway Off Ramp, Barker Avenue to Leslie Avenue 

  • Lloyd Expressway, Leslie Avenue to Igleheart Avenue

    • Water Main Installation, Jack & Bore – Complete

    • Water Main Installation, Directional Drilling – Complete

    • Water Main Installation, Open Cut – Complete

    • Water Service Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Complete

  • Barker Avenue at Pennsylvania Street

    • Water Main Installation – Complete

    • Final Connections – Complete

    • Restoration, Lawns and Pavement – Complete

VISITOR COUNT

208,953

  • Twitter Social Icon

© 2017 American Structurepoint, Inc.

bottom of page