SR 62 from Tekoppel to Wabash




-
St. Joseph Avenue from Lloyd Expressway to north of Indiana Street - Closed nightly from 7/21/25 - 7/25/25
-
Closure will be from 6:30 PM - 6:00 AM nightly
-
​
This project involves the installation of 1,260 LF of 8", 3,710 LF of 12", and 2,940 LF of 24" water main from Tekoppel to 9th Avenue. This relocation is in preparation for road improvements planned for this area as part of the Lloyd4U project.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
​
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
​
Project Designer - United Consulting Engineers
Indianapolis, Indiana
​
Construction Engineering Services - American Structurepoint, Inc.
Evansville, Indiana
​
Contractor- Blankenberger Brothers, Inc.
Cynthiana, IN
​
​
Project Update
​​
-
Recent Progress (June 29 to July 5)
-
Blankenberger completed the installation of new 24” ductile iron water main on Indiana Street between 10th Avenue and 11th Avenue.
-
Blankenberger began installing new 24” ductile iron water main on Indiana Street between 11th Avenue and 12th Avenue.
-
Blankenberger re-chlorinated the new 24” ductile iron water main on Indiana Street between S. 9th Avenue and Wabash Avenue.
-
Blankenberger continued installing new 12” C900 PVC water main on 9th Avenue between Pennsylvania Street and Ohio Street.
-
​
-
Anticipated Activities for Upcoming Week (July 6 to July 12)
-
Blankenberger intends to complete the installation of new 24” ductile iron water main on Indiana Street between 11th Avenue and 12th Avenue.
-
Blankenberger intends to begin installing new 24” ductile iron water main on Indiana Street between 12th Avenue and St. Joseph Avenue.
-
Blankenberger intends to activate the new 24” ductile iron water main on Indiana Street between 9th Avenue and Wabash Avenue.
-
Blankenberger intends to begin installing new ¾”-1” water service connections on Indiana Street between 9th Avenue and Wabash Avenue.
-
Blankenberger intends to connect the new 24” water main to the existing 4” water main at the intersection of Indiana Street and Wabash Avenue.
-
Blankenberger intends to perform hydrostatic testing and chlorinate the new 24” ductile iron water main on Indiana Street between Wabash Avenue and 10th Avenue.
-
Blankenberger intends to continue installing new 12” C900 PVC water main on 9th Avenue between Pennsylvania Street and Ohio Street.
-
​
Active and Scheduled Closures
Active
-
St. Joseph Avenue from Lloyd Expressway to north of Indiana Street - Closed nightly from 7/21/25 - 7/25/25
-
Closure will be from 6:30 PM - 6:00 AM nightly​
-
-
Wabash Avenue at Indiana Street – Northbound Lane- Open 7/18/25​
-
ï‚§9th Avenue from Ohio Street to Indiana Street - Closed
-
Indiana Street from 9th Ave. to 10th Ave.- Lane Restriction
-
10th Avenue at Indiana Street - Closed
-
11th Avenue at Indiana Street - Closed
-
12th Avenue at Indiana Street - Closed
​
Scheduled
-
No additional closures scheduled at this time.
​
Project Schedule​
-
9th Avenue – from Pennsylvania Street to Indiana Street
-
Water Main Installation, Jack & Bore - Complete
-
Water Main Installation, Open Cut – Complete
-
Final Connections – Late May to Late June 2025
-
Restoration, Lawns and Pavement – October 2025
-
​​
-
9th Avenue – Ohio Street to Pennsylvania Street
-
Water Main Installation – Late June to Early July 2025
-
Storm Sewer Installation – Late June to Late July 2025
-
Water Service Line Installation – Early July 2025
-
Final Connections – Early July 2025
-
Restoration, Lawns and Pavement - October 2025
-
​​
-
Ohio Street – 9th Avenue to Railroad Crossing (30 Day Full Closure)
-
Water Main Installation – Late June 2025 to Mid July 2025
-
Storm Sewer Installation – Late June to Late July 2025
-
Water Service Line Installation – Mid July to Late July 2025
-
Final Connections – Mid July to Late July 2025
-
Restoration, Lawns and Pavement – October 2025
-
​​
-
Indiana Street – 9th Avenue to Wabash Avenue
-
Water Main Installation – ONGOING
-
Water Service Line Installation – Late May to Early July 2025
-
Final Connections – Late May to Late June 2025
-
Restoration, Lawns and Pavement – October 2025
-
​
-
Indiana Street – Wabash Avenue to 10th Avenue
-
Water Main Installation – Late May to Late June 2025
-
Water Service Line Installation – Early July 2025
-
Final Connections – Early July 2025
-
Restoration, Lawns and Pavement – October 2025
-
​
-
Wabash Avenue – Indiana Street to Lloyd Expressway
-
Water Main Installation – Late May 2025
-
Water Service Line Installation – Late May to Early June 2025
-
Final Connections – Late May to Early June 2025
-
Restoration, Lawns and Pavement – October 2025​
-
​
-
10th Avenue, Indiana Street to Lloyd Expressway
-
Water Main Installation – Early June to Mid June 2025
-
Water Service Line Installation – Mid June 2025
-
Final Connections – Mid June 2025
-
Restoration, Lawns and Pavement – October 2025​
-
​
-
Indiana Street – 10th Avenue to 12th Avenue
-
Water Main Installation - Early June to Early July 2025
-
Water Service Connections – Early July 2025
-
Final Connections – Early July 2025
-
Restoration, Lawns and Pavement – October 2025
-
​
-
Indiana Street – 12th Avenue to St. Joseph Avenue
-
Water Main Installation - Early July to Late July 2025
-
Water Service Connections – Early August 2025
-
Final Connections – Early August 2025
-
Restoration, Lawns and Pavement – October 2025
-
​
-
12th Avenue – Indiana Street to Lloyd Expressway
-
Water Main Installation - Mid July to Late July 2025
-
Water Service Connections – Late July 2025
-
Final Connections – Late July 2025
-
Restoration, Lawns and Pavement – October 2025​
-
​
-
Indiana Street – St. Joseph Avenue to Lemcke Avenue
-
Water Main Installation – Mid August 2025 to Early September 2025
-
Water Service Installation – Mid September 2025
-
Final Connections – Mid September 2025
-
Restoration, Lawns and Pavement – October 2025​
-
​
-
St. Joseph Avenue – Indiana Street to Lloyd Expressway
-
Water Main Installation, Jack & Bore – Late July to Late August 2025
-
Water Main Installation, Open Cut – Late August to Mid September 2025
-
Water Service Connections – Mid September 2025
-
Final Connections – Mid September 2025
-
Restoration, Lawns and Pavement – October 2025
-
​
-
Lemcke Avenue – Indiana Street to Illinois Street
-
Water Main Installation – Early September to Mid September 2025
-
Water Service Installation – Late September 2025
-
Final Connections - Late September 2025
-
Restoration, Lawns and Pavement – November 2025
-
​
-
Lemcke Avenue – Illinois Street to Franklin Street
-
Water Main Installation – Late September to Early October 2025
-
Water Service Installation – Early October 2025
-
Final Connections – Early October 2025
-
Restoration, Lawns and Pavement – November 2025
-
​
-
Lemcke Avenue – Indiana Street to Pennsylvania Street (Lloyd Expressway)
-
Water Main Installation, Jack & Bore – Early August to Late August 2025
-
Water Main Installation, Open Cut – Late August to Early September 2025
-
Water Service Installation – Early September to Mid September 2025
-
Final Connections – Early September to Mid September 2025
-
Restoration, Lawns and Pavement – November 2025​
-
​
-
Franklin Street & Mt. Vernon Avenue – Lemcke Avenue to Michigan Street
-
Water Main Installation – Late September to Late October 2025
-
Water Service Installation – Late October 2025
-
Final Connections - Late October 2025
-
Restoration, Lawns and Pavement – November 2025​
-
​
-
Pennsylvania Street – Lemcke Avenue to Rick Davis Way
-
Water Main Installation –Mid August to Mid September 2025
-
Water Service Installation – Mid September to Late September 2025
-
Final Connections – Mid September to Late September 2025
-
Restoration, Lawns and Pavement – November 2025​
-
​
-
​Leslie Avenue, Forest Avenue to Igleheart Avenue
-
Water Main Installation – Mid November to Mid December 2025
-
Water Service Installation – Late December 2025 to Mid January 2026
-
Final Connections – Late December 2025 to Mid January 2026
-
Restoration, Lawns and Pavement – November 2025
-
​
-
Lloyd Expressway Off Ramp, Barker Avenue to Leslie Avenue
-
Lloyd Expressway, Leslie Avenue to Igleheart Avenue
-
Water Main Installation, Jack & Bore – Mid August to Mid September 2025
-
Water Main Installation, Directional Drilling – Mid August 2025
-
Water Main Installation, Open Cut – Mid October to Early November 2025
-
Water Service Installation – Early November 2025 to Mid November 2025
-
Final Connections – Early November 2025 to Mid November 2025
-
Restoration, Lawns and Pavement – November 2025
-