SR 62 from Tekoppel to Wabash




​This project involves the installation of 1,260 LF of 8", 3,710 LF of 12", and 2,940 LF of 24" water main from Tekoppel to 9th Avenue. This relocation is in preparation for road improvements planned for this area as part of the Lloyd4U project.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
​
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
​
Project Designer - United Consulting Engineers
Indianapolis, Indiana
​
Construction Engineering Services - American Structurepoint, Inc.
Evansville, Indiana
​
Contractor- Blankenberger Brothers, Inc.
Cynthiana, IN
​
​
Project Update
-
Recent Progress (January 18 to January 24)
-
Blankenberger completed the installation of new 12” C900 PVC water main on 9th Avenue between Pennsylvania Street and Ohio Street.
-
Blankenberger completed the installation of new 12” PVC water main on Lemcke Avenue between Indiana Street and Illinois Street.
-
Blankenberger completed Phase 3 of the Igleheart to Leslie Construction Sequencing, including the connection of a new 12”x12” MJ tee and 12” gate valve to the existing water main at Igleheart Avenue.
-
Blankenberger continued installing concrete curbs, sidewalks, and ADA ramps on Indiana Street between Wabash Avenue and St. Joseph Avenue.
-
​
-
Anticipated Activities for Upcoming Week (January 25 to January 31)
-
No work anticipated this week due to inclement weather.
-
​
Active and Scheduled Closures
Active​​
-
St. Joseph Avenue from Lloyd Expressway to Franklin Street- Lane Restriction​
-
ï‚§9th Avenue from Ohio Street to Indiana Street - Local traffic only
-
Indiana Street from 9th Ave. to St. Joseph Ave.- Lane Restriction
-
Indiana Street from Lemcke Ave. to St. Joseph Ave. - Local traffic only
-
10th Avenue at Indiana Street - Closed
-
11th Avenue at Indiana Street - Closed
-
12th Avenue at Indiana Street - Closed
-
Lloyd Expressway Off-ramp at Igleheart Avenue - Lane Restriction
-
Lemcke Avenue from St. Joseph Ave. to Franklin Street - Lane Restriction
​
Scheduled​
-
Ohio Street, Fulton to Wabash- Closed starting 2/2/26
​
Project Schedule​
-
9th Avenue – from Pennsylvania Street to Indiana Street
-
Water Main Installation, Jack & Bore - Complete
-
Water Main Installation, Open Cut – Complete
-
Final Connections – Complete
-
Restoration, Lawns and Pavement – Ongoing
-
-
9th Avenue – Ohio Street to Pennsylvania Street
-
Water Main Installation –January 2026
-
Storm Sewer Installation – January 2026
-
Water Service Line Installation – January 2026
-
Final Connections – January 2026
-
Restoration, Lawns and Pavement – January 2026
-
-
Ohio Street – 9th Avenue to Railroad Crossing (30 Day Full Closure)
-
Water Main Installation – January 2026
-
Storm Sewer Installation – January 2026
-
Water Service Line Installation –January 2026
-
Final Connections – January 2026
-
Restoration, Lawns and Pavement – January 2026
-
-
Indiana Street – 9th Avenue to Wabash Avenue
-
Water Main Installation – Complete
-
Water Service Line Installation – Complete
-
Final Connections – Complete
-
Restoration, Lawns and Pavement – Ongoing
-
-
Indiana Street – Wabash Avenue to 10th Avenue
-
Water Main Installation – Complete
-
Water Service Line Installation – Complete
-
Final Connections – Ongoing
-
Restoration, Lawns and Pavement – Ongoing
-
-
Wabash Avenue – Indiana Street to Lloyd Expressway
-
Water Main Installation – Complete
-
Water Service Line Installation – Complete
-
Final Connections – Complete
-
Restoration, Lawns and Pavement – Ongoing
-
-
10th Avenue, Indiana Street to Lloyd Expressway
-
Water Main Installation – Complete
-
Water Service Line Installation – Complete
-
Final Connections – Ongoing
-
Restoration, Lawns and Pavement – Ongoing
-
-
Indiana Street – 10th Avenue to 12th Avenue
-
Water Main Installation – Complete
-
Water Service Connections – Ongoing
-
Final Connections – Ongoing
-
Restoration, Lawns and Pavement – Ongoing
-
-
Indiana Street – 12th Avenue to St. Joseph Avenue
-
Water Main Installation - Complete
-
Water Service Connections – Complete
-
Final Connections – Ongoing
-
Restoration, Lawns and Pavement – Ongoing
-
-
12th Avenue – Indiana Street to Lloyd Expressway
-
Water Main Installation – Complete
-
Water Service Connections – Complete
-
Final Connections – Ongoing
-
Restoration, Lawns and Pavement – Ongoing
-
-
Indiana Street – St. Joseph Avenue to Lemcke Avenue
-
Water Main Installation – Mid December 2025
-
Water Service Installation –Early January 2026
-
Final Connections – Early January 2026
-
Restoration, Lawns and Pavement – Late January 2026​
-
-
St. Joseph Avenue – Indiana Street to Lloyd Expressway
-
Water Main Installation, Jack & Bore – Ongoing
-
Water Main Installation, Open Cut – Ongoing
-
Water Service Connections – January 2026
-
Final Connections – January 2026
-
Restoration, Lawns and Pavement – December 2025
-
-
St. Joseph Avenue – Indiana Street to Illinois Street
-
Water Main Installation, Open Cut – Mid December 2025
-
Water Service Connections – Early January 2026
-
Final Connections – Early January 2026
-
Restoration, Lawns and Pavement – Early January 2026
-
-
Lemcke Avenue – Indiana Street to Illinois Street
-
Water Main Installation – Mid December 2025
-
Water Service Installation – Late December 2025
-
Final Connections – Late December 2025
-
Restoration, Lawns and Pavement – Late December 2026​
-
-
Lemcke Avenue – Illinois Street to Franklin Street
-
Water Main Installation – Late December 2025
-
Water Service Installation – Early January 2026
-
Final Connections – Mid January 2026
-
Restoration, Lawns and Pavement – Mid January 2026​
-
-
Lemcke Avenue – Indiana Street to Pennsylvania Street (Lloyd Expressway)
-
Water Main Installation, Jack & Bore – Mid January 2026
-
Water Main Installation, Open Cut – Late January 2026
-
Water Service Installation – Mid February 2026
-
Final Connections – Mid February y 2026
-
Restoration, Lawns and Pavement – Late January 2026
-
-
Franklin Street & Mt. Vernon Avenue – Lemcke Avenue to Michigan Street
-
Water Main Installation – Mid January 2026
-
Water Service Installation – Late January 2026
-
Final Connections – Late January 2026
-
Restoration, Lawns and Pavement – Late January 2026​
-
-
Pennsylvania Street – Lemcke Avenue to Rick Davis Way
-
Water Main Installation – Mid January 2026
-
Water Service Installation – Late January 2026
-
Final Connections – Late January 2026
-
Restoration, Lawns and Pavement – Late January 2026
-
-
​Leslie Avenue, Forest Avenue to Igleheart Avenue
-
Water Main Installation – Early December2025
-
Water Service Installation – Late December 2025
-
Final Connections – Late December 2025
-
Restoration, Lawns and Pavement – January 2026​
-
-
Lloyd Expressway Off Ramp, Barker Avenue to Leslie Avenue
-
Lloyd Expressway, Leslie Avenue to Igleheart Avenue
-
Water Main Installation, Jack & Bore – Complete
-
Water Main Installation, Directional Drilling – Complete
-
Water Main Installation, Open Cut – Ongoing
-
Water Service Installation – Late December 2025
-
Final Connections – Late December 2025
-
Restoration, Lawns and Pavement – January 2026
-

