East Mill Road and Weaver Road
Water Main Replacement

This project involves the replacement of existing water mains with approximately 3,010 LF of 8" water main along E. Mill Road between Stringtown Road and Weaver Road and on Weaver Road from Hesmer Road to approximately 500 feet north of E Mill Road.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

​

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

​

Project Designer - Crawford, Murphy & Tilly, Inc.

Evansville, Indiana

​

Construction Engineering Services - American Structurepoint, Inc.

Evansville, Indiana

​

Contractor- Blankenberger Brothers, Inc.

Cynthiana, IN

​

Project Update

​

  •     Recent Progress (January 5 to January 11)
    •    No work performed on site due to inclement weather.

​

  •     Anticipated Activities for Upcoming Week (January 12 to January 18)  
    •    Blankenberger intends to complete the installation of new 8” C900 PVC water main pipe by open cut in lieu of directional bore on E. Mill Road between STA. 4+20 and 5+20.
    •    Blankenberger intends to install new fire hydrant assemblies and air relief assemblies on E. Mill Road between Stringtown Road and 313 E. Mill Road (STA. 7+30).
    •    Blankenberger intends to begin installing new 8” C900 PVC water main on E. Mill Road between 313 E. Mill Road (STA. 7+30) and Weaver Road.

     

Active and Scheduled Closures

Active

  • East Mill Road from Stringtown to Weaver Road - Closed to Through Traffic 

Scheduled

  • ​No additional closures scheduled in the immediate future. 

​

Project Schedule​

  • E. Mill Road, from Stringtown Road to Weaver Road

    • Water Main Installation – December 4, 2024 to January 30, 2025

    • Water Services Installation – January 21, 2025 to February 17, 2025

    • Final Connections (Stringtown Road Lane Restriction) – January 2, 2025 to January 7, 2025

    • Restoration (Pavement and Lawns) – February 17, 2025 to March 14, 2025

​

  • Weaver Road, from E. Mill Road to Hesmer Road

    • Water Main Installation – January 30, 2025 to February 28, 2024

    • Water Services Installation – February 24, 2025 to March 7, 2025

    • Final Connections – February 25, 2025 to March 10, 2025

    • Restoration (Pavement and Lawns) – February 17, 2025 to March 14, 2025