top of page

East Mill Road and Weaver Road
Water Main Replacement

This project involves the replacement of existing water mains with approximately 3,010 LF of 8" water main along E. Mill Road between Stringtown Road and Weaver Road and on Weaver Road from Hesmer Road to approximately 500 feet north of E Mill Road.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Crawford, Murphy & Tilly, Inc.

Evansville, Indiana

Construction Engineering Services - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Blankenberger Brothers, Inc.

Cynthiana, IN

Project Update

  •     Recent Progress (January 26 to February 1)
    •    Blankenberger continued installing new 8” C900 PVC water main on E. Mill Road between Stringtown Road and 408 E. Mill Rd. (STA. 9+99).

  • Anticipated Activities for Upcoming Week (February 2 to January 8)  
    •    Blankenberger intends to complete the installation of the new 12”x8” wet tap at the intersection of Stringtown Road and E. Mill Road.
    •    Blankenberger intends to complete the installation of new 8” C900 PVC water main on E. Mill Road between Stringtown Road and 408 E. Mill Road (STA. 9+99).
    •    Blankenberger intends to perform hydrostatic testing and chlorinate the new 8” C900 PVC water main on E. Mill Road between Stringtown Road and 408 E. Mill Road (STA. 9+99).

     

Active and Scheduled Closures

Active

  • East Mill Road from Stringtown to Weaver Road - Closed to Through Traffic 

  • Stringtown Road at the Intersection of E. Mill Road- Lane Restrictions
     

Scheduled

  • No additional closures scheduled in the immediate future. 

Project Schedule

  • E. Mill Road, from Stringtown Road to Weaver Road

    • Water Main Installation – ONGOING

    • Water Services Installation – Mid-February 2025 to Mid-March 2025

    • Final Connections (Stringtown Road Lane Restriction) – ONGOING

    • Restoration (Pavement and Lawns) – February 17, 2025 to March 14, 2025

​​

  • Weaver Road, from E. Mill Road to Hesmer Road

    • Water Main Installation – Mid March 2025 to Mid-April 2025

    • Water Services Installation – Mid April 2025 to Mid-May 2025

    • Final Connections – Mid-April 2025 to Mid May, 2025

    • Restoration (Pavement and Lawns) – Mid May 2025  to June 2025

  • Twitter Social Icon

© 2017 American Structurepoint, Inc.

bottom of page