top of page

Fares Avenue Water Main Relocation 

This project involves the installation of 750 feet of 8" water main on Fares Avenue from Diamond Ave. to US 41. This relocation is in preparation for road improvements planned for this area as part of the US 41 Lloyd to Lynch project.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

​

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

​

Project Designer - Evansville Water & Sewer Utility

Evansville, Indiana

​

Construction Engineering Services - American Structurepoint, Inc.

Evansville, Indiana

​

Contractor: SAMM Trucking and Excavating, Inc.

Newburgh, Indiana

​

​

Project Update​
  • Recent Progress (August 17 to August 23)

    • SAMM intends to reconnect services along Fares Ave. 

    • SAMM intends to perform final main connections on Fares Ave.

​

  • Anticipated Activities for Upcoming Week (August 24 to August 30) â€‹â€‹

    • SAMM intends to abandon the existing main on Fares Ave.

​

Active and Scheduled Closures
  • Please note this is an INDOT road reconstruction project including road improvements and utility relocations that are not affiliated with Evansville Water & Sewer Utility. 

​​​

Project Schedule​

  • Water main installation - June 30 to July 25, 2025

  • Testing water main - July 25 to July 30, 2025

  • Service reconnections - August 13 to August 22, 2025