William L. Brooks Drive, Oak Hill Road to Hedden Road

This project includes the installation of approximately 940 feet of 12" water main pipe and related improvements along William L. Brooks Drive from Oak Hill Road to Hedden Road. 

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

​

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

​

Project Designer -Evansville Water & Sewer Utility

Evansville, Indiana

​

Construction Engineering Services - American Structurepoint, Inc.

Evansville, Indiana

​

Contractor- Ragle, Inc.

Newburgh, Indiana

​

​

Road Closures and Boil Advisories

Click HERE

Project Update
  • Recent Progress

    • Ragle was awarded this contract on 12/16/25.

    • Work is expected to begin February 2026.

​

Active and Scheduled Closures

Scheduled

  • ​No closures currently scheduled

​

Project Schedule​

  • Mobilization - February 16, 2026

  • Install water main - February 16 to March 20, 2026

  • Test water main - March 21 to March 26, 2026

  • Tie in water main - March 27 to March 28 2026

  • Restoration - March 29 to April 15, 2026