Oak Hill, Lynch to St. George 

The proposed improvements include the relocation of approximately 6,080 feet of water main along Oak Hill Road between Lynch Road and St. George Road as part of the multiple phase road improvements  project by the Vanderburgh County Engineers Office.  The project is expected to include approximately seven fire hydrants, eight gate valves, and sixty-eight service connections.  Approximately 6,040 feet of existing water main will be abandoned upon completion of the improvements.
Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Evansville Water & Sewer Utility

Evansville, Indiana

Construction Engineering Services - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Blankenberger Brothers, Inc.

Cynthiana, IN

Road Closures and Boil Advisories

Click HERE

Project Update
  • Recent Progress (August 23 to August 29)

    • Blankenberger continued installing new 8” C900 PVC water main on Oak Hill Road between Bergdolt Road and Ivy Meadow Drive.

    • Blankenberger activated the new 8” C900 PVC water main on Oak Hill Road between Elmridge Drive and Aspen Drive.

    • Blankenberger chlorinated the new 8” C900 PVC water main on Oak Hill Road between Aspen Drive and Bergdolt Road.

    • Blankenberger chlorinated the new 4” fire service at 4217 Oak Hill Road.

    • Blankenberger completed the installation of new ¾”-1” water services on Oak Hill Road between Elmridge Drive and Eastbrook Drive.

    • Blankenberger completed the installation of sanitary sewer manholes STR. 301, STR. 302, and STR. 303.

    • Blankenberger completed the installation of new 8” C900 PVC gravity sewer between STR. 301 and STR. 303.

    • Blankenberger began installing new 8” C900 PVC gravity sewer between STR. 303 and STR. 304.

  • Anticipated Activities for Upcoming Week (August 30 to September 5) 

    • Blankenberger intends to begin the installation of ¾”-1” water services on Oak Hill Road between Eastbrook Drive and Aspen Drive.

    • Blankenberger intends to complete the connection of the new 8” C900 PVC water main to the existing 6” water main on Oak Hill Road at Aspen Drive.

    • Blankenberger intends to complete the connection of the new 8” water main to the existing 4” fire service at 4217 Oak Hill Road, pending the results of water quality sampling.

    • Blankenberger intends to complete the installation of sanitary sewer manholes STR. 304, STR. 305, and STR. 306.

    • Blankenberger intends to complete the installation of new 8” C900 PVC gravity sewer between STR. 303 and STR. 306.

Closures

  • Please note this is a Vanderburgh County Road reconstruction project including road improvements and utility relocations that are not affiliated with Evansville Water & Sewer Utility.