Oak Hill, Lynch to St. George 

The proposed improvements include the relocation of approximately 6,080 feet of water main along Oak Hill Road between Lynch Road and St. George Road as part of the multiple phase road improvements  project by the Vanderburgh County Engineers Office.  The project is expected to include approximately seven fire hydrants, eight gate valves, and sixty-eight service connections.  Approximately 6,040 feet of existing water main will be abandoned upon completion of the improvements.
Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Evansville Water & Sewer Utility

Evansville, Indiana

Construction Engineering Services - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Blankenberger Brothers, Inc.

Cynthiana, IN

Road Closures and Boil Advisories

Click HERE

Project Update
  • Recent Progress (June 7 to June 13)

    • Blankenberger continued installing new ¾”-1” water service connection on Oak Hill Road between Lynch Road and Elmridge Drive.

    • Blankenberger completed the connection of the new 8” C900 PVC water main to the existing water main at the intersection of Oak Hill Road and Elmridge Drive.

  • Anticipated Activities for Upcoming Week (June 14 to June 20) 

    • Blankenberger intends to complete the installation of ¾”-1” water service connections on Oak Hill Road between Lynch Road and Elmridge Drive.

    • Blankenberger intends to continue installing new 8” C900 PVC water main on Oak Hill Road between Elmridge Drive and Aspen Drive.

Project Schedule

  • Water main installation is expected to take place from 3/23/26 to 9/4/26. 

Closures

  • Please note this is a Vanderburgh County Road reconstruction project including road improvements and utility relocations that are not affiliated with Evansville Water & Sewer Utility.