Oak Hill, Lynch to St. George



The proposed improvements include the relocation of approximately 6,080 feet of water main along Oak Hill Road between Lynch Road and St. George Road as part of the multiple phase road improvements project by the Vanderburgh County Engineers Office. The project is expected to include approximately seven fire hydrants, eight gate valves, and sixty-eight service connections. Approximately 6,040 feet of existing water main will be abandoned upon completion of the improvements.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - Evansville Water & Sewer Utility
Evansville, Indiana
Construction Engineering Services - American Structurepoint, Inc.
Evansville, Indiana
Contractor- Blankenberger Brothers, Inc.
Cynthiana, IN

Road Closures and Boil Advisories
Click HERE
Project Update
-
Recent Progress (November 8 to November 14)
-
Blankenberger re-chlorinated the new 8” C900 PVC water main on Oak Hill Road between Ridgewood Drive and Bexley Court.
-
Blankenberger began performing low pressure air testing and vacuum testing on the new gravity sewer pipe and manholes.
-
-
Anticipated Activities for Upcoming Week (November 15 to November 21)
-
Blankenberger intends to re-chlorinate the new 8” C900 PVC water main on Oak Hill Road between Ridgewood Drive and Bexley Court.
-
Blankenberger intends activate the new 8” C900 PVC water main on Oak Hill Road between Ridgewood Drive and Bexley Court, pending the results of water quality sampling.
-
Blankenberger intends to continue performing low pressure air testing and manhole vacuum testing on the new gravity sewer pipe and manholes.
-
Closures
-
Please note this is a Vanderburgh County Road reconstruction project including road improvements and utility relocations that are not affiliated with Evansville Water & Sewer Utility.
