Oak Hill, Lynch to St. George


The proposed improvements include the relocation of approximately 6,080 feet of water main along Oak Hill Road between Lynch Road and St. George Road as part of the multiple phase road improvements project by the Vanderburgh County Engineers Office. The project is expected to include approximately seven fire hydrants, eight gate valves, and sixty-eight service connections. Approximately 6,040 feet of existing water main will be abandoned upon completion of the improvements.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - Evansville Water & Sewer Utility
Evansville, Indiana
Construction Engineering Services - American Structurepoint, Inc.
Evansville, Indiana
Contractor- Blankenberger Brothers, Inc.
Cynthiana, IN

Road Closures and Boil Advisories
Click HERE
Project Update
-
Recent Progress (September 6 to September 12)
-
Blankenberger began installing new ¾”-1” water services on Oak Hill Road between Aspen Drive and Bergdolt Road.
-
-
Anticipated Activities for Upcoming Week (September 13 to September 19)
-
Blankenberger intends to continue installing new ¾”-1” water services on Oak Hill Road between Aspen Drive and Bergdolt Road.
-
Blankenberger intends to perform hydrostatic testing and chlorinate the new 8” C900 PVC water main on Oak Hill Road between Bergdolt Road and Ridgewood Drive.
-
Blankenberger intends to complete the connection of the new 8” C900 PVC water main to the existing 6” water main on Eastbrook Drive at Oak Hill Road.
-
Blankenberger intends to complete the connection of the new 8” C900 PVC water main to the existing 8” water main at Bergdolt Road west of Oak Hill Road.
-
Closures
-
Please note this is a Vanderburgh County Road reconstruction project including road improvements and utility relocations that are not affiliated with Evansville Water & Sewer Utility.