top of page
Park Street, Shanklin Ave to Florida Street

Water Pipe_iStock_000014408747Large

Water Pipe_iStock_000014408747Large
1/1
This project includes the installation of approximately 1,400 feet of 6” to 12” water main pipe and related improvements along Park Street from Shanklin Avenue to Florida Street.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
​
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
​
Project Designer -Evansville Water & Sewer Utility
Evansville, Indiana
​
Construction Engineering Services - American Structurepoint, Inc.
Evansville, Indiana
​
Contractor- BMB, Inc.
Newburgh, Indiana
​
​

Road Closures and Boil Advisories
Click HERE
Project Update
-
Recent Progress
-
BMB was awarded this contract on 12/16/25.
-
Work is expected to begin in February 2026.
-
​
Active and Scheduled Closures
Scheduled
-
​No closures currently scheduled
​
Project Schedule​
-
Mobilization - February 16, 2026
-
Install water main - February 16 to March 13, 2026
-
Test water main - March 18 to March 30, 2026
-
Water main tie ins and services- March 6 to March 31, 2026
-
Restoration - April 1 to April 13, 2026
bottom of page

