top of page

Park Street, Shanklin Ave to Florida Street 

This project includes the installation of approximately 1,400 feet of 6” to 12” water main pipe and related improvements along Park Street from Shanklin Avenue to Florida Street.
Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

​

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

​

Project Designer -Evansville Water & Sewer Utility

Evansville, Indiana

​

Construction Engineering Services - American Structurepoint, Inc.

Evansville, Indiana

​

Contractor- BMB, Inc.

Newburgh, Indiana

​

​

Road Closures and Boil Advisories

Click HERE

Project Update
  • Recent Progress

    • BMB was awarded this contract on 12/16/25.

    • Work is expected to begin in early 2026.

​

Active and Scheduled Closures

Scheduled

  • ​No closures currently scheduled

​

Project Schedule​

  • TBD

  • Twitter Social Icon

© 2017 American Structurepoint, Inc.

bottom of page