Morgan Ave. and Boeke Road 

​This project includes the installation of approximately 570 feet of 12” water main pipe and related improvements on Boeke Road from Morgan Avenue to Eichel Avenue.
Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

​

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

​

Project Designer - Clark Dietz

Evansville, Indiana

​

Construction Engineering Services - American Structurepoint, Inc.

Evansville, Indiana

​

Contractor- TBD

​

​

​

Road Closures and Boil Advisories

Click HERE

Project Update
  • Recent Progress (October 18 to October 24)

    • Koberstein continued mobilizing equipment and materials to the project site.

    • Koberstein installed traffic control devices on Morgan Avenue and Boeke Road.

​

  • Anticipated Activities for Upcoming Week (October 25 to October 31) 

    • Koberstein intends to verify the locations and depths of existing utilities.

    • Koberstein intends to begin excavation of the bore pit and receiving pit on Boeke Road at the intersection with Morgan Avenue.

​

Active and Scheduled Closures
  • ​Morgan Avenue at Boeke Road - Lane Restriction 

  • Boeke Road, North of Morgan to Eichel- Lane Restriction

​

Project Schedule​​

  • Water Main Installation (Jack & Bore) – Mid October to Late October 2026

  • Water Main Installation (Open Cut) – Late October to Late November 2026

  • Water Service Installation – Late November 2026

  • Final Connections – Early December 2026

  • Restoration – Early December to Mid December 2026