Morgan Ave. and Boeke Road



This project includes the installation of approximately 570 feet of 12” water main pipe and related improvements on Boeke Road from Morgan Avenue to Eichel Avenue.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - Clark Dietz
Evansville, Indiana
Construction Engineering Services - American Structurepoint, Inc.
Evansville, Indiana
Contractor- TBD

Road Closures and Boil Advisories
Click HERE
Project Update
-
Recent Progress (October 18 to October 24)
-
Koberstein continued mobilizing equipment and materials to the project site.
-
Koberstein installed traffic control devices on Morgan Avenue and Boeke Road.
-
-
Anticipated Activities for Upcoming Week (October 25 to October 31)
-
Koberstein intends to verify the locations and depths of existing utilities.
-
Koberstein intends to begin excavation of the bore pit and receiving pit on Boeke Road at the intersection with Morgan Avenue.
-
Active and Scheduled Closures
-
Morgan Avenue at Boeke Road - Lane Restriction
-
Boeke Road, North of Morgan to Eichel- Lane Restriction
Project Schedule
-
Water Main Installation (Jack & Bore) – Mid October to Late October 2026
-
Water Main Installation (Open Cut) – Late October to Late November 2026
-
Water Service Installation – Late November 2026
-
Final Connections – Early December 2026
-
Restoration – Early December to Mid December 2026