Washington Avenue and SE Second Street Water Main Relocation

This project involves the installation of approximately 1,950 feet of new 8”-16” PVC C900 and ductile iron water main pipe in the Haynies Corner Arts District.  Work will include the installation of water main valves, hydrant assemblies, 30 service taps and service lines, and connections to existing water mains.  Work areas include new installations on Washington Avenue from  SE Eighth Street to SE Second Street.   Areas also include SE Second between Blackford Avenue and Adams Avenue, Adam Avenue between SE First Street and Parrett Street, and on Parrett Street from Washington Avenue to SE Third Street. 

Work is anticipated to begin in May of 2019 and should be complete by November 2019.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Evansville Water & Sewer Utility

Evansville, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor - Deig Brothers Lumber and Construction Co., Inc.

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

Recent Progress (November 17 to November 23)

  •  Elite Line Striping completed all pavement markings throughout the corridor of the project.  

  • Deig completed restoration, grading, and seeding throughout the project.  

  • Deig re-opened Washington Avenue and Adams Avenue to normal traffic.  

 

 

Anticipated Activities for Upcoming Week (November 24 to November 30)

  • No work is anticipated. A punchlist inspection is anticipated the week of December 9, 2019.

Project Schedule

Please note the below will be updated as revised schedules are received from the construction contractor.  The current final contract completion date for this project is September 19, 2019.

Adams Avenue, from SE 1st Street to Parrett Street

  • Water Main Installation - Mid June 2019 Complete 

  • Water Main Final Connections (water main outages) - Late June 2019 Complete 

  • Water Service Line Installation (individual customer outages) – Late June 2019 Complete 

  • Restoration (pavement patching, lawn seeding) - Early November 2019 Complete 

SE Second Street, from Adams Avenue to College

  • Water Main Installation - Late June 2019 Complete 

  • Water Main Final Connections (water main outages) - Early July 2019 Complete 

  • Water Service Line Installation (individual customer outages) - Early July 2019 Complete 

  • Restoration (pavement patching, lawn seeding) - July 2019 Complete 

Washington Avenue, from Parrett Street to 6th Street

  • Water Main Installation - Mid August 2019 Complete 

  • Water Main Final Connections (water main outages) - Early September 2019 Complete 

  • Water Service Line Installation (individual customer outages) - Mid September 2019 Complete 

  • Restoration (pavement patching, lawn seeding) - Early November 2019 Complete 

 

Washington Avenue, from 6th Street to 8th Street

  • Water Main Installation - Late August 2019 Complete 

  • Water Main Final Connections (water main outages) - Complete

  • Water Service Line Installation (individual customer outages) - Complete

  • Restoration (pavement patching, lawn seeding) - Early November 2019 Complete 

  • Twitter Social Icon

© 2017 American Structurepoint, Inc.