Sweetser Avenue and Rotherwood Avenue Area Water Main Replacement

This project includes the installation of over 15,000 feet of 8" diameter water main pipe and related improvements on Evansville's southeast side.      

Construction is anticipated to begin in late 2020.

Refresh Evansville Project Open Houses have been suspended due to concerns about COVID-19. The presentation has been recorded and can be viewed below. 

Sweetser Avenue and Rotherwood Avenue Water Main Replacement Open House Presentation

 


Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Wessler Engineering, Inc.

Indianapolis, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Infrastructure Systems, Inc.

Orleans, Indiana

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update
  • Recent Progress (October 11 to October 17)

    • Infrastructure Systems completed the connection of new ¾”-1” water services on Norman between Sweetser and Cass. 

    • Infrastructure Systems cut and capped the existing water mains on Norman at Sweetser and Cass.

  • Anticipated Activities for Upcoming Week (October 18 to October 24)

    • Infrastructure Systems intends to complete the installation of HMA base on Sweetser between Rotherwood and Weinbach. 

    • Infrastructure Systems intends to complete the installation of HMA surface on Sweetser between Rotherwood and Weinbach. 

    • Infrastructure Systems intends to complete concrete and lawn restoration on Sweetser between Rotherwood and Weinbach. 

Project Schedule

Phase 3- Conlin Avenue

  • Water Main Installation Complete

  • Water Main Final Connections (water main outages) Complete

  • Water Service Line Installation (individual customer outages)  Complete

  • Restoration (pavement patching, lawn seeding) Complete

Phase 3- Crystal Court

  • Water Main Installation Complete

  • Water Main Final Connections (water main outages) Complete

  • Water Service Line Installation (individual customer outages) Complete

  • Restoration (pavement patching, lawn seeding) Complete

Phase 3- Plantation Court

  • Water Main Installation Complete

  • Water Main Final Connections (water main outages) Complete

  • Water Service Line Installation (individual customer outages) Complete

  • Restoration (pavement patching, lawn seeding) Complete

Phase 1- Sweetser Avenue

  • Water Main Installation Complete

  • Water Main Final Connections (water main outages) Complete

  • Water Service Line Installation (individual customer outages) Complete

  • Restoration (pavement patching, lawn seeding) Complete

Phase 1- Cass Avenue

  • Water Main Installation Complete

  • Water Main Final Connections (water main outages) Complete

  • Water Service Line Installation (individual customer outages) Complete

  • Restoration (pavement patching, lawn seeding) Complete

Phase 1- Waggoner Avenue

  • Water Main Installation Complete

  • Water Main Final Connections (water main outages) Complete

  • Water Service Line Installation (individual customer outages) Complete

  • Restoration (pavement patching, lawn seeding) Complete

Phase 1- Rotherwood Avenue

  • Water Main Installation Complete

  • Water Main Final Connections (water main outages) Complete

  • Water Service Line Installation (individual customer outages) Late September 2020  

  • Restoration (pavement patching, lawn seeding) – Mid November 2020

Phase 2- Sweetser Avenue

  • Water Main Installation Complete

  • Water Main Final Connections (water main outages) Complete

  • Water Service Line Installation (individual customer outages) Early October 2020  Ongoing

  • Restoration (pavement patching, lawn seeding) – Mid November 2020

Phase 2- Ridgeway Avenue

  • Water Main Installation – Mid September 2020 Ongoing

  • Water Main Final Connections (water main outages) Complete

  • Water Service Line Installation (individual customer outages) Early October 2020  

  • Restoration (pavement patching, lawn seeding) – Mid November 2020

Phase 2- Cass Avenue

  • Water Main Installation Complete

  • Water Main Final Connections (water main outages) Complete

  • Water Service Line Installation (individual customer outages) Late September 2020  

  • Restoration (pavement patching, lawn seeding) – Mid November 2020

Phase 2- Norman Avenue

  • Water Main Installation Complete

  • Water Main Final Connections (water main outages) Complete

  • Water Service Line Installation (individual customer outages) Mid October 2020  

  • Restoration (pavement patching, lawn seeding) – Mid November 2020

Phase 2- Frederick Avenue

  • Water Main Installation Complete

  • Water Main Final Connections (water main outages) Complete

  • Water Service Line Installation (individual customer outages) Late October 2020  

  • Restoration (pavement patching, lawn seeding) – Mid November 2020

  • Twitter Social Icon

© 2017 American Structurepoint, Inc.