Strueh Hendricks Road, West of Broadway Water Main Extension

Water Pipe_iStock_000014408747Large
Water Pipe_iStock_000014408747Large

press to zoom
Water Pipe_iStock_000014408747Large
Water Pipe_iStock_000014408747Large

press to zoom
1/1

This project includes the installation of approximately 2,800 feet of new 8” and 12” water main pipe and related improvements on Charlotte Avenue, Russell Avenue and Bement Avenue area.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Evansville Water & Sewer Utility

Evansville, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor: Deig Brothers Lumber and Construction Co.,Inc.

Evansville, Indiana

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress 

  • The preconstruction meeting was held on August 25, 2022. 

Anticipated Activities for Upcoming Week (September 18 to September 24)

  • No work anticipated onsite.  

  • Work is tentatively scheduled to begin on or after October 6, 2022.