Southeast Side Neighborhood, Phase I Water Main Replacement

U1087 Map
U1087 Map

U1087 Map
U1087 Map

1/1

This project includes the installation of approximately 10,000 feet of new 4” and 8” water main pipe throughout the neighborhood between Hawthorne Avenue and Vann Avenue to the West and East, and Covert Avenue and Graham Avenue to the North and South.

Construction is anticipated to begin in Spring 2021.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Crawford, Murphy & Tilly, Inc. 

Evansville, IN

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Miller Pipeline, LLC

Indianapolis, IN

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

Recent Progress (May 30 to June 5) 

  • Miller Pipeline began performing construction engineering and line staking activities at the project site. 

Anticipated Activities for Upcoming Week (June 6 to June 12) 

  • Miller Pipeline intends to begin performing advanced saw cutting operations at the project site. 

  • Miller Pipeline intends to begin mobilizing equipment and materials to the project site. 

Project Schedule

The project schedule will be posted as information is received from the Contractor.