Southeast Side Neighborhood, Phase I Water Main Replacement

southeast side 1
southeast side 1

press to zoom
southeast side neighborhood
southeast side neighborhood

press to zoom
U1087 Map
U1087 Map

press to zoom
southeast side 1
southeast side 1

press to zoom
1/7

This project includes the installation of approximately 10,000 feet of new 4” and 8” water main pipe throughout the neighborhood between Hawthorne Avenue and Vann Avenue to the West and East, and Covert Avenue and Graham Avenue to the North and South.

Construction is anticipated to begin in Spring 2021.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Crawford, Murphy & Tilly, Inc. 

Evansville, IN

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Miller Pipeline, LLC

Indianapolis, IN

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

Recent Progress (September 12 to September 18) 

  • Miller Pipeline completed the connection of new ¾”-1” water services on McConnell between Graham and Sweetser, and on Sandee Acre northwest of McConnell. 

  • Miller Pipeline activated the new 8” C900 PVC water main on Hawthorne between Graham and Sweetser. 

  • Miller Pipeline began connecting new ¾”-1” water services on Hawthorne between Graham and Sweetser. 

  • Miller Pipeline completed the connection of the new 8” C900 PVC water main on Hawthorne to the existing 6” water main at Helmuth. 

 

Anticipated Activities for Upcoming Week (September 19 to September 25) 

  • Miller Pipeline intends to complete the connection of new ¾”-1” water services on Hawthorne between Graham and Sweetser. 

  • Miller Pipeline intends to begin connecting new ¾”-1” water services on Hawthorne between Graham and Sweetser. 

  • Miller Pipeline intends to begin installing new 8” C900 PVC water main on Hawthorne between Sweetser and Covert. 

 

Project Schedule

Graham Avenue, from Vann Avenue to McLeod Court, North of Graham Avenue

  • Water Main Installation - Complete

  • Water Service Line Installation (individual customer outages) - Complete

  • Water Main Final Connections (water main outages) - Complete

  • Restoration (pavement patching, lawn seeding) -Early September 2021

Graham Avenue, from McLeod Court to Hawthorne Avenue,South of Graham Avenue

  • Water Main Installation - Complete

  • Water Service Line Installation (individual customer outages) - Ongoing

  • Water Main Final Connections (water main outages) - Complete

  • Restoration (pavement patching, lawn seeding) -Early September 2021

Hawthorne Avenue, from Graham Avenue to Sweetser Avenue

  • Water Main Installation - Complete

  • Water Service Line Installation (individual customer outages) - Mid September 2021

  • Water Main Final Connections (water main outages) - Mid September 2021

  • Restoration (pavement patching, lawn seeding) -Early October 2021

Hawthorne Avenue, from Sweetser Avenue to Covert Avenue

  • Water Main Installation - Mid September 2021

  • Water Service Line Installation (individual customer outages) - Early October 2021

  • Water Main Final Connections (water main outages) - Early October 2021

  • Restoration (pavement patching, lawn seeding) - Mid October 2021

McConnell Avenue, from Graham Avenue to Sweetser Avenue
Sandee Acre Court, West of McConnell

  • Water Main Installation - Complete

  • Water Service Line Installation (individual customer outages) - Early September 2021

  • Water Main Final Connections (water main outages) - Early September 2021

  • Restoration (pavement patching, lawn seeding) - Mid September 2021

Southeast Boulevard, from Hawthorne Avenue to McConnell Avenue
McConnell Avenue, from Southeast Boulevard to Sweetser Avenue

  • Water Main Installation - Mid September 2021

  • Water Service Line Installation (individual customer outages) - Early October 2021

  • Water Main Final Connections (water main outages) - Early October 2021

  • Restoration (pavement patching, lawn seeding) - Early October 2021

 

Southeast Boulevard, from McConnell Avenue to Vann Avenue
Conlin Avenue from Southeast Boulevard to Vann Avenue

  • Water Main Installation - Ongoing

  • Water Service Line Installation (individual customer outages) - Early October 2021

  • Water Main Final Connections (water main outages) - Mid October 2021

  • Restoration (pavement patching, lawn seeding) - Late October 2021

McConnell Avenue, from Sweetser Avenue to Covert Avenue

  • Water Main Installation - Mid February 2022

  • Water Service Line Installation (individual customer outages) - Early March 2022

  • Water Main Final Connections (water main outages) - Early March 2022

  • Restoration (pavement patching, lawn seeding) - Mid March 2022

Sweetser Avenue, from Hawthorne Avenue to McConnell Avenue
S. Dexter Avenue, North of Sweetser Avenue

  • Water Main Installation - Late March 2022

  • Water Service Line Installation (individual customer outages) - Early April 2022

  • Water Main Final Connections (water main outages) - Mid April 2022

  • Restoration (pavement patching, lawn seeding) - Mid April 2022

Sweetser Avenue, from McConnell Avenue to Vann Avenue

  • Water Main Installation - Mid April 2022

  • Water Service Line Installation (individual customer outages) - Late April 2022

  • Water Main Final Connections (water main outages) - Late April 2022

  • Restoration (pavement patching, lawn seeding) - Early May 2022

Cass Avenue, from Hawthorne Avenue to McConnell Avenue

  • Water Main Installation - Late April 2022

  • Water Service Line Installation (individual customer outages) - Early May 2022

  • Water Main Final Connections (water main outages) - Early May 2022

  • Restoration (pavement patching, lawn seeding) - Mid May 2022