Southeast Side Neighborhood, Phase I Water Main Replacement

U1087 Southeast Side (6)
U1087 Southeast Side (6)

press to zoom
southeast side 1
southeast side 1

press to zoom
U1087 Map
U1087 Map

press to zoom
U1087 Southeast Side (6)
U1087 Southeast Side (6)

press to zoom
1/8

This project includes the installation of approximately 10,000 feet of new 4” and 8” water main pipe throughout the neighborhood between Hawthorne Avenue and Vann Avenue to the West and East, and Covert Avenue and Graham Avenue to the North and South.

Construction is anticipated to begin in Spring 2021.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Crawford, Murphy & Tilly, Inc. 

Evansville, IN

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Miller Pipeline, LLC

Indianapolis, IN

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

Recent Progress (November 21 to November 27) 

  • Infrastructure Systems performed an 8” wet tap on Vann at Conlin. 

  • Miller Pipeline completed the installation of new 8” C900 PVC water main on Conlin between Southeast and Vann. 

  • Miller Pipeline continued connecting new ¾”-1” water services on Hawthorne between Sweetser and Covert. 

Anticipated Activities for Upcoming Week (November 28 to December 4) 

  • Miller Pipeline intends to complete the connection of new ¾”-1” water services on Hawthorne between Sweetser and Covert. 

  • Miller Pipeline intends to perform hydrostatic testing and chlorinate the new 8” C900 PVC water main on Southeast between McConnell and Vann, and on Conlin between Southeast and Vann. 

  • Miller Pipeline intends to begin installing new 8” C900 PVC water main on Southeast between Hawthorne and McConnell. 

 

Project Schedule

Graham Avenue, from Vann Avenue to McLeod Court, North of Graham Avenue​- Complete

Graham Avenue, from McLeod Court to Hawthorne Avenue,South of Graham Avenue​- Complete

Hawthorne Avenue, from Graham Avenue to Sweetser Avenue

  • Water Main Installation - Complete

  • Water Service Line Installation (individual customer outages) - Complete

  • Water Main Final Connections (water main outages) - Complete

  • Restoration (pavement patching, lawn seeding) -Ongoing

Hawthorne Avenue, from Sweetser Avenue to Covert Avenue

  • Water Main Installation - Complete

  • Water Service Line Installation (individual customer outages) - Ongoing

  • Water Main Final Connections (water main outages) - Complete

  • Restoration (pavement patching, lawn seeding) - Late December 2021

McConnell Avenue, from Graham Avenue to Sweetser Avenue
Sandee Acre Court, West of McConnell

  • Water Main Installation - Complete

  • Water Service Line Installation (individual customer outages) - Complete

  • Water Main Final Connections (water main outages) - Complete

  • Restoration (pavement patching, lawn seeding) - Ongoing

Southeast Boulevard, from Hawthorne Avenue to McConnell Avenue
McConnell Avenue, from Southeast Boulevard to Sweetser Avenue

  • Water Main Installation - Early December 2021

  • Water Service Line Installation (individual customer outages) - Mid December 2021

  • Water Main Final Connections (water main outages) - Mid December 2021

  • Restoration (pavement patching, lawn seeding) - Late December 2021

 

Southeast Boulevard, from McConnell Avenue to Vann Avenue
Conlin Avenue from Southeast Boulevard to Vann Avenue

  • Water Main Installation - Ongoing

  • Water Service Line Installation (individual customer outages) -Early December 2021

  • Water Main Final Connections (water main outages) - Mid December 2021

  • Restoration (pavement patching, lawn seeding) - Late December 2021

McConnell Avenue, from Sweetser Avenue to Covert Avenue

  • Water Main Installation - Mid February 2022

  • Water Service Line Installation (individual customer outages) - Early March 2022

  • Water Main Final Connections (water main outages) - Early March 2022

  • Restoration (pavement patching, lawn seeding) - Mid March 2022

Sweetser Avenue, from Hawthorne Avenue to McConnell Avenue
S. Dexter Avenue, North of Sweetser Avenue

  • Water Main Installation - Late March 2022

  • Water Service Line Installation (individual customer outages) - Early April 2022

  • Water Main Final Connections (water main outages) - Mid April 2022

  • Restoration (pavement patching, lawn seeding) - Mid April 2022

Sweetser Avenue, from McConnell Avenue to Vann Avenue

  • Water Main Installation - Mid April 2022

  • Water Service Line Installation (individual customer outages) - Late April 2022

  • Water Main Final Connections (water main outages) - Late April 2022

  • Restoration (pavement patching, lawn seeding) - Early May 2022

Cass Avenue, from Hawthorne Avenue to McConnell Avenue

  • Water Main Installation - Late April 2022

  • Water Service Line Installation (individual customer outages) - Early May 2022

  • Water Main Final Connections (water main outages) - Early May 2022

  • Restoration (pavement patching, lawn seeding) - Mid May 2022