Sonntag Avenue, Golfmoor to Maryland Water Main Replacement

This project consists of the installation of approximately 1,200 feet of water main pipe along Sonntag Avenue, between Golfmoor Road and Maryland Street.  Related improvements include new valves, fire hydrants and water service replacements within the project area.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer -  Three i Design

Evansville, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Miller Pipeline, LLC 

Indianapolis, Indiana

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Project Update

 

Recent Progress 

  • No work completed onsite. 

 Anticipated Activities for Upcoming Week (March 19 to March 25)

  • No work anticipated onsite.  Final asphalt restoration is scheduled to be completed as weather conditions permit. 