This project consists of the extension of the exiting water main west from Volkman Tank along Schroeder Road to the east side of US 41 and includes the installation of approximately 5,000 feet of 16" and 12" water main. 

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Clark Dietz, Inc. 

Evansville, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Miller Pipeline, LLC 

Indianapolis, IN

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (June 19 to June 25)

  • Miller Pipeline Pipeline activated the new 16” ductile iron water main on Cambridge Golf Course between Schroeder Road and STA. 36+75.

  • Miller Pipeline completed installation of new 16” ductile iron water main on Cambridge Golf Course between STA. 36+75 and STA. 47+10.

  • Miller Pipeline began installing new 16” ductile iron water main between STA. 47+10 and STA. 59+00 (Volkman Tank).

  • Miller Pipeline performed hydrostatic testing of the new 16” ductile iron water main on Cambridge Golf Course between STA. 36+75 and STA. 47+10.

 Anticipated Activities for Upcoming Week (June 26 to July 2) 

  • Miller Pipeline intends to continue installing the new 16” ductile iron water main between STA. 47+10 and STA. 59+00.

  • Miller Pipeline intends to chlorinate the new 16” ductile iron water main on Cambridge Golf Course between STA. 36+75 and STA. 47+10.