Schmitt, Whetstone and Bexley Water Main Replacement
This project would include the installation of approximately 4,800 feet of new 8” water main pipe and related upgrades throughout the project area.
Construction is anticipated to begin in Fall 2020.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - Crawford Murphy & Tilly, Inc.
Evansville, IN
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor- Miller Pipeline, LLC
Indianapolis, IN

Road Closures
Click HERE for updated road closures.

Boil Advisory Information
Click HERE for the latest boil advisory information

Alerts and Announcements
Click HERE for alerts and announcements.
Project Update
Recent Progress (January 10 to January 16)
-
Miller Pipeline continued ¾”-1” water service replacements on Bexley Court.
Anticipated Activities for Upcoming Week (January 17 to January 23)
-
Miller Pipeline intends to complete the connection the new ¾”-1” water services on Bexley.
-
Miller Pipeline intends to cut, cap, and abandon the existing water main on Bexley.
-
Miller Pipeline intends to continue performing lawn restoration activity on Bexley.
Project Schedule
-
Schmitt Lane Complete
-
Lakeland Drive Complete
-
Whetstone Road Complete
-
Bexley Court
-
Water Main Installation - Ongoing
-
Water Service Line Installation (individual customer outages) - January 2021
-
Water Main Final Connections (water main outages) - Complete
-
Restoration (pavement patching, lawn seeding) - Late January 2021
-