This project includes the installation of approximately 2,500 feet of new water main pipe along Rosewood Drive, Weaver Road, East Buena Vista Road, Herrmann Road, Walden Lane, and Karch Drive. Related improvements include new valves and fire hydrants throughout the project area.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Clark Dietz, Inc.

Evansville, IN

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- BMB, Inc.

Newburgh, Indiana

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (May 1 to May 8)​​

  • BMB completed the installation of a new 20” tapping saddle and 8” tapping valve at the intersection of Hermann and Rosewood. 

  • BMB completed the installation of new 8” C900 PVC RJ water main on Rosewood between Hermann and Weaver. 

  • BMB hydrostatically tested and chlorinated the new 8” C900 PVC RJ water main on Rosewood between Hermann and Weaver. 

  • BMB began connecting the new ¾”-1” water services on Karch, east of Hermann. 

Anticipated Activities for Upcoming Week (May 9 to May 15) 

  • BMB intends to begin connecting new ¾”-1” water services on Karch east of Hermann, pending the results of water quality sampling. 