President's Neighborhood Water Main Replacement

This project involves the installation of approximately 21,000 feet of new 4”-8” PVC C900 and ductile iron water main pipe in the Presidents Neighborhood.  Work will include the installation of water main valves, 30 hydrant assemblies, 630 service taps and service lines, and connections to existing water mains. 

Work began in July of 2019 and should be complete by April 2020.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - United Consulting

Indianapolis, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractors -Deig Brothers Lumber and Construction Co., Inc.

Evansville, Indiana (Central Phase)

 

Infrastructure Systems, Inc.

Orleans, Indiana (West Phase, East Phase)

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (December 1 to December 7)

  • Deig completed installation of new 8” PVC C900 water main on Monroe between Bennighof and 
    Rotherwood. 

  • Deig began installation of new ¾”-1” water service connections on Jackson between Bennighof and 
    Rotherwood. 

  • Deig performed hydrostatic testing and chlorinated new 8” PVC C900 water main on Monroe between Bennighof and Rotherwood. 

  • Deig began installing concrete driveways and ADA ramps on Madison and Bennighof. 

  •  Infrastructure completed installation of concrete pavement on Marshall between Madison and Ravenswood. 

  • David Enterprises completed installation of HMA surface on Marshall between Washington and 
    Madison. 

  • Infrastructure completed installation of new 8” PVC C900 water main on Harlan between Ravenswood and Monroe. 

  • Infrastructure began installation of ¾”-1” water service reconnections on Henning between Madison and Monroe. 

Anticipated Activities for Upcoming Week (December 8 to December 14)

  • Deig intends to continue installing new ¾”-1” water service connections on Jackson between Bennighof and Rotherwood. 

  • Deig intends to complete installation of new concrete driveways and concrete ADA ramps on Madison and Bennighof. 

  • Infrastructure intends to install new 8” PVC C900 water main on Harlan between Monroe and Madison.    

  • Infrastructure intends to continue installation of new ¾”-1” water service connections on Henning between Madison and Monroe. 

  • Infrastructure intends to begin installation of new 8” PVC C900 water main on Harlan between Ravenswood and Madison. 

Project Schedule

Please note the below will be updated as revised schedules are received from the construction contractor. Click HERE to view a project map that outlines the anticipated construction schedule. 

Adams Avenue

  • Water Main Installation – Mid August 2019 Complete

  • Water Service Line Installation (individual customer outages) – Mid September 2019 Complete

  • Restoration (pavement patching, lawn seeding) – Timeline is currently being evaluated

Brookside Drive

  • Water Main Installation – Early September 2019 Complete

  • Water Service Line Installation (individual customer outages) Late September 2019 Complete

  • Restoration (pavement patching, lawn seeding) - Timeline is currently being evaluated

Bennighof Avenue

  • Water Main Installation – Mid September 2019 Complete

  • Water Service Line Installation (individual customer outages) – Early October 2019 Complete

  • Restoration (pavement patching, lawn seeding) - Timeline is currently being evaluated

 

Englewood Court

  • Water Main Installation – Late September 2019 Complete

  • Water Service Line Installation (individual customer outages) Mid October 2019 Complete

  • Restoration (pavement patching, lawn seeding) - Timeline is currently being evaluated

Madison Avenue and Bennighof Avenue

  • Water Main Installation – Late October 2019 Complete

  • Water Service Line Installation (individual customer outages) Mid November 2019 Complete

  • Restoration (pavement patching, lawn seeding) - Timeline is currently being evaluated

Monroe Avenue

  • Water Main Installation – Late November 2019

  • Water Service Line Installation (individual customer outages) Early December 2019

  • Restoration (pavement patching, lawn seeding) - Timeline is currently being evaluated

 

Jackson Avenue

  • Water Main Installation – Early December 2019

  • Water Service Line Installation (individual customer outages) Early January 2020

  • Restoration (pavement patching, lawn seeding) - Timeline is currently being evaluated

 

Taylor Avenue

  • Water Main Installation Late December 2019

  • Water Service Line Installation (individual customer outages) Mid January 2020

  • Restoration (pavement patching, lawn seeding) - Timeline is currently being evaluated

 

Ravenswood Drive, Rotherwood Avenue to Covert Avenue

  • Water Main Installation – Late January 2020

  • Water Service Line Installation (individual customer outages) Mid February 2020

  • Restoration (pavement patching, lawn seeding) - Timeline is currently being evaluated