President's Neighborhood Water Main Replacement

This project involves the installation of approximately 21,000 feet of new 4”-8” PVC C900 and ductile iron water main pipe in the Presidents Neighborhood.  Work will include the installation of water main valves, 30 hydrant assemblies, 630 service taps and service lines, and connections to existing water mains. 

Work began in July of 2019 and should be complete by April 2020.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - United Consulting

Indianapolis, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractors -Deig Brothers Lumber and Construction Co., Inc.

Evansville, Indiana (Central Phase)

 

Infrastructure Systems, Inc.

Orleans, Indiana (West Phase, East Phase)

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (March 8 to March 14)

  • Deig completed the reconnection of ¾”-1” water services on Ravenswood between Lodge and Rotherwood.

  • Deig cut and capped the existing water main on Ravenswood.

  • Deig installed concrete base on Taylor between Lodge and Englewood.

  • Deig installed concrete base on Rotherwood between Covert and Ravenswood.

  • Rivertown Construction completed the installation of concrete curbs, sidewalks, and ADA ramps on Taylor between Rotherwood and Weinbach.

  • Rivertown Construction began installing new concrete curbs, sidewalks, and ADA ramps on Monroe
    between Rotherwood and Weinbach.

  • Infrastructure Systems began performing lawn restoration throughout the project site.

  • Infrastructure Systems completed lawn restoration work on Harlan between Ravenswood and Adams.

  • Infrastructure Systems removed all the recently abandoned valve boxes on Henning and Marshall.

Anticipated Activities for Upcoming Week (March 15 to March 21)

  • Deig intends to complete the installation of concrete base on Taylor between Englewood and Rotherwood.

  • Deig intends to begin installing concrete base on Ravenswood between Lodge and Rotherwood.

  • Rivertown Construction intends to complete the installation of concrete curbs, sidewalks, and ADA ramps on Monroe between Rotherwood and Weinbach.

  • Infrastructure Systems intends to begin installing HMA surface throughout the project site.

  • Rivertown Construction intends to complete the installation of concrete curb, sidewalk, and ADA ramp restoration on Monroe between Rotherwood and Weinbach.

  • Rivertown Construction intends to begin installing concrete curb, sidewalk, and ADA ramp restoration on Taylor between Rotherwood and Weinbach.

Project Schedule

Please note the below will be updated as revised schedules are received from the construction contractor. Click HERE to view a project map that outlines the anticipated construction schedule. 

Adams Avenue

  • Water Main Installation – Mid August 2019 Complete

  • Water Service Line Installation (individual customer outages) – Mid September 2019 Complete

  • Restoration (pavement patching) – Complete

  • Restoration (lawn seeding) – Spring 2020

Brookside Drive

  • Water Main Installation – Early September 2019 Complete

  • Water Service Line Installation (individual customer outages) Late September 2019 Complete

  • Restoration (pavement patching) – Complete

  • Restoration (lawn seeding) – Spring 2020

Bennighof Avenue

  • Water Main Installation – Mid September 2019 Complete

  • Water Service Line Installation (individual customer outages) – Early October 2019 Complete

  • Restoration (pavement patching) – Complete

  • Restoration (lawn seeding) – Spring 2020

 

Englewood Court

  • Water Main Installation – Late September 2019 Complete

  • Water Service Line Installation (individual customer outages) Mid October 2019 Complete

  • Restoration (pavement patching) – Complete

  • Restoration (lawn seeding) – Spring 2020

Madison Avenue and Bennighof Avenue

  • Water Main Installation – Late October 2019 Complete

  • Water Service Line Installation (individual customer outages) Mid November 2019 Complete

  • Restoration (pavement patching) – Complete

  • Restoration (lawn seeding) – Spring 2020

Monroe Avenue

  • Water Main Installation – Late November 2019 Complete

  • Water Service Line Installation (individual customer outages) Early December 2019 Complete

  • Restoration (pavement patching) – Late January 2020 (weather permitting)

  • Restoration (lawn seeding) – Spring 2020

 

Jackson Avenue

  • Water Main Installation – Early December 2019 Complete

  • Water Service Line Installation (individual customer outages) Early January 2020 Complete

  • Restoration (pavement patching) – Late January 2020 (weather permitting)

  • Restoration (lawn seeding) – Spring 2020

 

Taylor Avenue

  • Water Main Installation Early January 2020 

  • Water Service Line Installation (individual customer outages) Mid January 2020

  • Restoration (pavement patching) – Late January 2020 (weather permitting)

  • Restoration (lawn seeding) – Spring 2020

 

Ravenswood Drive, Rotherwood Avenue to Covert Avenue

  • Water Main Installation – Late January 2020

  • Water Service Line Installation (individual customer outages) Mid February 2020

  • Restoration (pavement patching) – Late January 2020 (weather permitting)

  • Restoration (lawn seeding) – Spring 2020

·         David Enterprises completed the installation of HMA surface on Henning between Washington and Ravenswood.

·         David Enterprises completed the installation of HMA surface on Harlan between Adams and Ravenswood.

·         Infrastructure Systems completed lawn grading and restoration work on Henning Avenue.

  • Twitter Social Icon

© 2017 American Structurepoint, Inc.