President's Neighborhood Water Main Replacement

This project involves the installation of approximately 21,000 feet of new 4”-8” PVC C900 and ductile iron water main pipe in the Presidents Neighborhood.  Work will include the installation of water main valves, 30 hydrant assemblies, 630 service taps and service lines, and connections to existing water mains. 

Work began in July of 2019 and should be complete by April 2020.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - United Consulting

Indianapolis, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractors -Deig Brothers Lumber and Construction Co., Inc.

Evansville, Indiana (Central Phase)

 

Infrastructure Systems, Inc.

Orleans, Indiana (West Phase, East Phase)

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (February 2 to February 8)

  • Deig completed the installation of new 8” PVC C900 water main on Rotherwood between Ravenswood and Covert. 

  • Deig completed the installation of new 8” PVC C900 water main across Covert at Rotherwood. 

  • Deig performed hydrostatic testing of the new 8” PVC C900 water main on Ravenswood between 
    Englewood and Rotherwood, and on Rotherwood between Ravenswood and Covert. 

  • Infrastructure Systems completed reconnecting ¾”-1” water services on Harlan between Madison and Monroe. 

  • Infrastructure Systems began reconnecting ¾”-1” water services on Harlan between Monroe and Ravenswood. 

  • Infrastructure Systems completed the installation of concrete pavement on Henning between Ravenswood and Monroe. 

  • Infrastructure Systems completed the installation of new 6” PVC C900 water main on Frederick 
    between Taylor and Ravenswood. 

  • Infrastructure Systems completed the installation of new 6” PVC C900 water main on Norman between Taylor and Ravenswood. 

  • Infrastructure Systems began reconnecting ¾”-1” water services on Monroe between Rotherwood 
    and Norman. 

Anticipated Activities for Upcoming Week (February 9 to February 15)

  • Deig intends to complete the connection of new 8” PVC C900 water main to the existing 6” water main at Covert and Rotherwood, pending water quality sampling results. 

  • Deig intends to install a new 8” gate valve on the existing 36” LCP water main at Covert and Rotherwood. 

  • Deig intends to complete the connection of new 8” PVC C900 water main to the existing 36” LCP water main at Covert and Rotherwood, pending water quality sampling results. 

  • Infrastructure Systems intends to complete ¾”-1” water service reconnections on Harlan between Adams and Ravenswood. 

  • Infrastructure Systems intends to complete the installation of concrete pavement on Henning between Washington and Ravenswood. 

  • Infrastructure Systems intends to begin installing 6” concrete base on Henning between Washington and Ravenswood. 

  • Infrastructure Systems intends to complete the reconnection of ¾”-1” water services on Monroe between Rotherwood and Norman. 

  • Infrastructure Systems intends to begin reconnecting ¾”-1” water services on Monroe between Norman and Frederick. 

  • Infrastructure Systems intends to activate the new 8” water main on Taylor between Rotherwood and Weinbach, pending water quality sampling results. 
     

Project Schedule

Please note the below will be updated as revised schedules are received from the construction contractor. Click HERE to view a project map that outlines the anticipated construction schedule. 

Adams Avenue

  • Water Main Installation – Mid August 2019 Complete

  • Water Service Line Installation (individual customer outages) – Mid September 2019 Complete

  • Restoration (pavement patching) – Complete

  • Restoration (lawn seeding) – Spring 2020

Brookside Drive

  • Water Main Installation – Early September 2019 Complete

  • Water Service Line Installation (individual customer outages) Late September 2019 Complete

  • Restoration (pavement patching) – Complete

  • Restoration (lawn seeding) – Spring 2020

Bennighof Avenue

  • Water Main Installation – Mid September 2019 Complete

  • Water Service Line Installation (individual customer outages) – Early October 2019 Complete

  • Restoration (pavement patching) – Complete

  • Restoration (lawn seeding) – Spring 2020

 

Englewood Court

  • Water Main Installation – Late September 2019 Complete

  • Water Service Line Installation (individual customer outages) Mid October 2019 Complete

  • Restoration (pavement patching) – Complete

  • Restoration (lawn seeding) – Spring 2020

Madison Avenue and Bennighof Avenue

  • Water Main Installation – Late October 2019 Complete

  • Water Service Line Installation (individual customer outages) Mid November 2019 Complete

  • Restoration (pavement patching) – Complete

  • Restoration (lawn seeding) – Spring 2020

Monroe Avenue

  • Water Main Installation – Late November 2019 Complete

  • Water Service Line Installation (individual customer outages) Early December 2019 Complete

  • Restoration (pavement patching) – Late January 2020 (weather permitting)

  • Restoration (lawn seeding) – Spring 2020

 

Jackson Avenue

  • Water Main Installation – Early December 2019 Complete

  • Water Service Line Installation (individual customer outages) Early January 2020 Complete

  • Restoration (pavement patching) – Late January 2020 (weather permitting)

  • Restoration (lawn seeding) – Spring 2020

 

Taylor Avenue

  • Water Main Installation Early January 2020 

  • Water Service Line Installation (individual customer outages) Mid January 2020

  • Restoration (pavement patching) – Late January 2020 (weather permitting)

  • Restoration (lawn seeding) – Spring 2020

 

Ravenswood Drive, Rotherwood Avenue to Covert Avenue

  • Water Main Installation – Late January 2020

  • Water Service Line Installation (individual customer outages) Mid February 2020

  • Restoration (pavement patching) – Late January 2020 (weather permitting)

  • Restoration (lawn seeding) – Spring 2020