This project includes the installation of approximately 3,100 feet of 4" to 8" diameter water main pipe and related improvements throughout the project area which consists of New Harmony Road, from New Harmony Way to Allen Lane,  and Winterheimer Drive, from New Harmony Road to the Dead End.    

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Black and Veatch

Indianapolis, IN

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Debra-Kuempel, Inc.

Evansville, Indiana

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (May 1 to May 8) 

  • Debra Kuempel continued the installation of 8” C-900 water main on New Harmony Road from Harmony Way to Allens Lane. 

 
 Anticipated Activities for Upcoming Week (May 9 to May 15) 

  • Debra Kuempel intends to continue the installation of 8” C-900 water main on New Harmony Road from Harmony Way towards Kern Rd and Allens Lane. 

Project Schedule

The project schedule will be posted as information is received from the Contractor.