Mount Auburn Road Water Main Replacement

The project involves the replacement of approximately 2,500 feet of 4” and 6” water mains with 4”, 6” and 8” C900 PVC mains.  New water service connections, gate valves and fire hydrants will also be installed on this project.  Work areas include Mt. Auburn Road between Bismark Avenue and Optimist Drive. 

This project is scheduled for completion in November, 2018.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer -  Crawford Murphy & Tilly, Inc.

Indianapolis, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor - BMB, Inc.

Evansville, Indiana

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

This project is complete.  If you have concerns with restoration on your property please contact us.  You may call 812-402-4509 or click here.