Maryland Street, Harmony Way to Wessel Lane Water Main Replacement
This project would include the installation of approximately 2,300 feet of 8” diameter water main pipe and related upgrades along the south side of West Maryland Street.
Construction is anticipated to begin in Late September 2021 with an estimated completion date of January 2022.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - Three I Design
Evansville, IN
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor- Blankenberger Brothers, Inc.
Cynthiana, IN

Road Closures
Click HERE for updated road closures.

Boil Advisory Information
Click HERE for the latest boil advisory information

Alerts and Announcements
Click HERE for alerts and announcements.
Project Update
Recent Progress (June 12 to June 18)
-
Elite Striping completed the installation of new centerline striping and stop bars on Maryland from Harmony Way to Wessel.
-
Blankenberger demobilized from the project site.
Anticipated Activities for Upcoming Week (June 19 to June 25)
-
No work anticipated on site this week.