Maryland Street, Harmony Way to Wessel Lane Water Main Replacement




This project would include the installation of approximately 2,300 feet of 8” diameter water main pipe and related upgrades along the south side of West Maryland Street.
Construction is anticipated to begin in Late September 2021 with an estimated completion date of January 2022.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - Three I Design
Evansville, Indiana
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor- Blankenberger Brothers, Inc.
Cynthiana, Indiana

Road Closures
Click HERE for updated road closures.

Boil Advisory Information
Click HERE for the latest boil advisory information
Project Update
This project is substantially complete and is currently in the punchlist phase. If you have concerns about your specific property, please contact us at 812-402-4509.