This project includes the installation of approximately 2,500 feet of 8” diameter water main pipe. The installation will occur on Grove Street, south of Allens Lane.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Three I Design

Evansville, IN

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Miller Pipeline, LLC

Indianapolis, Indiana

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (May 30 to June 5) 

  • Miller Pipeline began verifying the existing ¾”-1” water services on Grove, south of Allens Lane. 

 

Anticipated Activities for Upcoming Week (June 6 to June 12) 

  • Miller Pipeline intends to activate the new 8” C900 PVC water main on Grove, south of Allens, pending the results of water quality sampling. 

  • Miller Pipeline intends to begin connecting the new ¾”-1” water services on Grove, south of Allens, pending the results of water quality sampling. 

Project Schedule

Water Main Installation- Ongoing

Water Service Line Installation (Individual Customer Outages)- Early June 2021

Water Main Final Connections (Water Main Outages)- Early June 2021

Restoration (Pavement Patching, Lawn Seeding)- Late June 2021