top of page

Forest Ave. and Walker Ave.
Water Main Relocation

This project involves the relocation of existing water main with approximately 50 LF of 8" water main at Forest Avenue and Walker Avenue intersection.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

​

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

​

Project Designer - Evansville Water & Sewer Utility

Evansville, Indiana

​

Construction Engineering Services - American Structurepoint, Inc.

Evansville, Indiana

​

Contractor: BMB, Inc.

Newburgh, Indiana

​

Project Update

   ​​

This project is substantially complete and is currently in the closeout phase.  If you have concerns about your specific property, please contact us at 812-402-4509.