First Avenue Water Main Replacement
This project is estimated to include 7,900 feet of new 4” to 36” water main pipe and related improvements throughout the project area, which consists of First Avenue, between Morgan Avenue and Colonial Avenue, and along the railroad tracks west of First Avenue, near Morgan Avenue.
Construction is anticipated to begin in February 2021.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - HNTB Corporation
Indianapolis, IN
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor- MAC Construction & Excavating, Inc.
New Albany, IN

Road Closures
Click HERE for updated road closures.

Boil Advisory Information
Click HERE for the latest boil advisory information

Alerts and Announcements
Click HERE for alerts and announcements.
Project Update
Recent Progress (January 10 to January 16)
-
Safe-Ti-Co installed portable message boards providing advanced notification of upcoming lane closures on First Avenue between Morgan Avenue and Colonial Avenue.
Anticipated Activities for Upcoming Week (January 17 to January 23)
-
No work anticipated on site this week.
Project Schedule
The full project schedule will be posted as information is received from the Contractor.
W. Morgan Avenue, Third Avenue to First Avenue (Railroad Corridor)
-
Preliminary Utility Verificaiton - Februrary 1, 2021 to February 6, 2021
First Avenue, Morgan Avenue to Uhlhorn Street
-
Preliminary Utility Verificaiton - Februrary 8, 2021 to February 13, 2021
First Avenue, Uhlhorn Street to Diamond Avenue
-
Preliminary Utility Verificaiton - Februrary 8, 2021 to February 13, 2021
First Avenue, Landbridge Way to Idlewild Drive
-
Preliminary Utility Verificaiton - Februrary 15, 2021 to February 20, 2021
First Avenue, Idlewild Drive to Colonial Avenue
-
Preliminary Utility Verificaiton - Februrary 22, 2021 to February 26, 2021