First Avenue Water Main Replacement
This project is estimated to include 7,900 feet of new 4” to 36” water main pipe and related improvements throughout the project area, which consists of First Avenue, between Morgan Avenue and Colonial Avenue, and along the railroad tracks west of First Avenue, near Morgan Avenue.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - HNTB Corporation
Indianapolis, IN
Construction Manager - American Structurepoint, Inc.
Evansville, Indiana
Contractor- MAC Construction & Excavating, Inc.
New Albany, IN

Road Closures
Click HERE for updated road closures.

Boil Advisory Information
Click HERE for the latest boil advisory information

Alerts and Announcements
Click HERE for alerts and announcements.
Project Update
Recent Progress (July 17 to July 23)
-
MAC performed work on preliminary punchlist items.
Anticipated Activities for Upcoming Week (July 24 to July 30)
-
MAC intends to continue performing work on preliminary punchlist items.
-
Elite Striping intends to complete lane striping on First Avenue from Diamond Avenue to Colonial