Fendrich Neighborhood Water Main Replacement

fendrich 1_edited
fendrich 1_edited

fedrich
fedrich

U1027 Map
U1027 Map

fendrich 1_edited
fendrich 1_edited

1/5

This project includes the installation of over 7,000 feet of new 8” diameter water main pipe and will connect previously renewed areas of water main throughout the Fendrich Neighborhood in the area bound by Haven Drive to the west, Hercules Avenue to the east, Morgan Avenue to the south and Richardt Avenue to the north.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Beam, Longest & Neff, LLC

Indianapolis, IN

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Deig Brothers Lumber & Construction Co., LLC

Evansville, IN

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (July 11 to July 17) 

  • Deig verified the depths and locations of existing utilities on Enlow between Aviation and Haven. 

  • Deig verified existing water services on Enlow between Aviation and Haven. 

  • Deig began installing new 8” C900 PVC water main on Enlow between Aviation and Haven. 

 

 Anticipated Activities for Upcoming Week (July 18 to July 24) 

  • Deig intends to continue installing new 8” C900 PVC water main on Enlow between Aviation and Haven. 

Project Schedule

Richardt Avenue, from Hercules Avenue to Wedeking Avenue- Complete

 

Herndon Avenue, from Hercules Avenue to Haven Avenue

  • Water Main Installation - Complete

  • Water Service Line Installation (individual customer outages) - Complete

  • Water Main Final Connections (water main outages) - Complete

  • Restoration (pavement patching, lawn seeding) - Ongoing

Haven Avenue, from Keck Avenue to Wedeking Avenue

  • Water Main Installation - Complete

  • Water Service Line Installation (individual customer outages) - Complete

  • Water Main Final Connections (water main outages) - Complete

  • Restoration (pavement patching, lawn seeding) - Ongoing

Oakland Avenue, from Hercules Avenue to Herndon Avenue​- Complete

Oakland Avenue, from Herndon Avenue to Enlow Avenue

  • Water Main Installation - Ongoing

  • Water Service Line Installation (individual customer outages) - Mid July 2021

  • Water Main Final Connections (water main outages) - Late July 2021

  • Restoration (pavement patching, lawn seeding) - Early September 2021

Maxwell Avenue, from Oakland Avenue to Garrison Avenue

  • Water Main Installation - Early July 2021

  • Water Service Line Installation (individual customer outages) - Late July 2021

  • Water Main Final Connections (water main outages) - Late July 2021

  • Restoration (pavement patching, lawn seeding) - Early September 2021

Enlow Avenue, from Aviation Avenue to Haven Drive

  • Water Main Installation - Mid July 2021

  • Water Service Line Installation (individual customer outages) - Early August 2021

  • Water Main Final Connections (water main outages) - Late August 2021

  • Restoration (pavement patching, lawn seeding) - Early September 2021

Garrison Avenue, from Enlow Avenue to Morgan Avenue

  • Water Main Installation - Early August 2021

  • Water Service Line Installation (individual customer outages) - Late August 2021

  • Water Main Final Connections (water main outages) - Late August 2021

  • Restoration (pavement patching, lawn seeding) - Early September 2021