Covert Avenue, Phase II and Wedge Avenue Water Main Replacement

This project is estimated to include the replacement of the existing water main along Covert Avenue between Marshall Avenue and Weinbach Avenue and Wedge Avenue south of Covert Avenue. The project will replace approximately 3,900 feet of water main as well as related upgrades throughout the project area including new hydrants, valves and service connections. Construction is anticipated to begin the Summer of 2020.

 Covert Avenue, Ph. II and Wedge Avenue Water Main Replacement Open House Presentation

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - United Consulting

Indianapolis, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Deig Brothers Lumber & Construction Co., Inc. 

Evansville, Indiana

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

Recent Progress (October 11 to October 17)

  • Deig Brothers completed lawn restoration work along Covert between Weinbach and Lodge. 

  • Deig Brothers completed sidewalk repairs at the intersection of Covert and Wedge. 

  • Deig Brothers began installing HMA Base on Covert between Lodge and Wedge. 

  • Deig Brothers began installing concrete pavement on Wedge between Covert and Henning. 

  • Deig Brothers began installing concrete pavement on Henning between Wedge and Cass. 

  • Deig Brothers began installing HMA surface on Wedge between Covert and Henning.

Anticipated Activities for Upcoming Week (October 18 to October 24)

  • Deig Brothers intends to begin connecting new ¾”-1” water services on Covert, Wedge, and 
    Henning, pending results of water quality sampling. 

Project Schedule

  • Covert Avenue, Weinbach Avenue  to Lodge Avenue

    • Water Main Installation Complete

    • Water Service Line Installation (individual customer outages)  Complete

    • Water Main Final Connections (water main outages) Complete

    • Restoration (pavement patching, lawn seeding)  – Early October 2020 to Late October 2020 Ongoing

 

  • Covert Avenue, Lodge Avenue to Wedge Avenue

    • Water Main Installation – Mid September 2020

    • Water Main Final Connections (water main outages) – Late October 2020

    • Restoration (pavement patching, lawn seeding)  – Late November 2020 to Early December 2020

 

  • Wedge Avenue, Lodge Avenue  to Henning Avenue

    • Water Main Installation – Late October 2020 to Late November 2020

    • Water Main Final Connections (water main outages) –Late October 2020 

    • Water Service Line Installation (individual customer outages)  – Mid November 2020 to Late November 2020

    • Restoration (pavement patching, lawn seeding)  – Late November 2020 to Early December 2020

 

  • Henning Avenue, Wedge Avenue to Cass Avenue

    • Water Main Installation – Late October 2020 to Late November 2020

    • Water Main Final Connections (water main outages) – Late November 2020 

    • Restoration (pavement patching, lawn seeding)  – Late November 2020 to Early December 2020