Covert Avenue, Phase II and Wedge Avenue Water Main Replacement

This project is estimated to include the replacement of the existing water main along Covert Avenue between Marshall Avenue and Weinbach Avenue and Wedge Avenue south of Covert Avenue. The project will replace approximately 3,900 feet of water main as well as related upgrades throughout the project area including new hydrants, valves and service connections. Construction is anticipated to begin the Summer of 2020.

 Covert Avenue, Ph. II and Wedge Avenue Water Main Replacement Open House Presentation

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - United Consulting

Indianapolis, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Deig Brothers Lumber & Construction Co., Inc. 

Evansville, Indiana

Road Closures

Click HERE for updated road closures.

Road Closures

Click HERE for updated road closures.

Road Closures

Click HERE for updated road closures.

Project Update

Recent Progress (June 28 to July 4)

  • Deig began mobilizing to the project site. 

  • Crite performed construction staking throughout the project corridor. 

Anticipated Activities for Upcoming Week (July 5 to July 11)

  • Deig intends to receive materials and continue mobilizing to the project site. 

  • Road Safe intends to install Phase 1 traffic control devices on Covert between Weinbach and Lodge. 

  • Deig intends to perform advanced sawcutting of the existing pavement on Covert between Weinbach and Lodge. 

  • Deig intends to perform hydrostatic testing of the existing 6” and 8” gate valves at the intersection of Weinbach and Covert. 

  • Deig intends to begin installing the new 8” C900 PVC water main on Covert between Weinbach and Lodge. 

Project Schedule

  • Covert Avenue, Weinbach Avenue  to Lodge Avenue

    • Water Main Installation – Mid July 2020 to Mid August 2020

    • Water Service Line Installation (individual customer outages)  – Mid August 2020 to Early October 2020

    • Water Main Final Connections (water main outages) – Late October 2020

    • Restoration (pavement patching, lawn seeding)  – Early October 2020 to Late October 2020

 

  • Covert Avenue, Lodge Avenue to Wedge Avenue

    • Water Main Installation – Late October 2020

    • Water Main Final Connections (water main outages) – Late October 2020

    • Restoration (pavement patching, lawn seeding)  – Late November 2020 to Early December 2020

 

  • Wedge Avenue, Lodge Avenue  to Henning Avenue

    • Water Main Installation – Late October 2020 to Late November 2020

    • Water Main Final Connections (water main outages) –Late October 2020 

    • Water Service Line Installation (individual customer outages)  – Mid November 2020 to Late November 2020

    • Restoration (pavement patching, lawn seeding)  – Late November 2020 to Early December 2020

 

  • Henning Avenue, Wedge Avenue to Cass Avenue

    • Water Main Installation – Late October 2020 to Late November 2020

    • Water Main Final Connections (water main outages) – Late November 2020 

    • Restoration (pavement patching, lawn seeding)  – Late November 2020 to Early December 2020