Peerless Road from Upper Mount Vernon Road to Moye Drive


This project includes the installation of approximately 5,000 feet of 12” and 16" diameter water main pipe. The installation will occur along Peerless Road from Moye Drive to Upper Mount Vernon Road, as well as along Upper Mount Vernon Road from Peerless Road to West Wind Drive.
Project Team
Project Owner - Evansville Water & Sewer Utility
Evansville, Indiana
Program Manager - American Structurepoint, Inc.
Evansville, Indiana
Project Designer - Crawford, Murphy, and Tilly
Evansville, Indiana
Construction Engineering Services - American Structurepoint, Inc.
Evansville, Indiana
Contractor- Deig Brothers Construction
Evansville, Indiana

Road Closures and Boil Advisories
Click HERE
Project Update
-
Recent Progress (September 3 to September 9)
-
Powers Welding and Directional Drilling began the pilot bore for the installation of 24” steel casing on Peerless Road under the CSX Railroad via jack and bore.
-
Deig Brothers began concrete base pavement restoration on Upper Mount Vernon Rd
-
-
Anticipated Activities for Upcoming Week (September 10 to September 16)
-
Powers Welding and Directional Drilling intends to begin installation of 24” steel casing on Peerless Road under the CSX Railroad via jack and bore.
-
Deig Brothers intends to activate the 16” DI water main on Upper Mount Vernon Road between Peerless Road and West Wind Drive.
-
Deig Brothers intends to make final connections to the existing main on West Wind Drive.
-
Deig Brothers intends to make final connections to the existing main at the Water Tank on Upper Mount Vernon Road.
-
Deig Brothers intends to make final connections to the existing main on Upper Mount Vernon Road west of West Wind Drive.
-
Active and Scheduled Street Closures
- Active
- Upper Mount Vernon Road from Boehne Camp Road to Koring Road
-
Scheduled
-
Peerless Road from Hogue Road to Upper Mount Vernon Road
-
No scheduled dates yet
-
-
Project Schedule
-
Phase 1 (Upper Mount Vernon Road—West Wind Drive to Peerless Road)
-
July 24 to September 21, 2023
-
Jack and bore at the railroad tracks on Peerless Road: August 7, 2023 to September 1, 2023
-
-
Phase 2 (Peerless Road—Upper Mount Vernon Road to just north of Old Orchard Trail )
-
September 1 to November 15, 2023
-
-
Phase 3 (Peerless Road—Just north of Old Orchard Trail to Moye Drive)
-
November 16, 2023 to February 28, 2024
-