Columbia Phase I, Fares, Columbia to Morgan Water Main Replacement

This project is estimated to include the installation of approximately 9,500 feet of new water main on N Governor Street, between Columbia Street and E Louisiana Street, Columbia Street, between Lafayette Avenue and Fares Avenue, and Fares Avenue, between Columbia Street and Eichel Avenue. Related upgrades throughout the project area include new hydrants, valves and service connections. Construction is anticipated to begin in May 2020.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Three i Design

Evansville, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Ragle, Inc.

Newburgh, Indiana

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (January 10 to January 16)​​

  • Ragle began installing the new 8” C900 PVC water main on Columbia between Governor and Lafayette.

  • Ragle completed the installation of HMA surface on Governor between Louisiana and Delaware.

  • Ragle completed concrete sidewalk, curb, and gutter restoration work on Governor between Louisiana and Delaware.

  • Ragle completed lawn restoration work on Governor between Louisiana and Governor.

Anticipated Activities for Upcoming Week (January 17 to January 23) 

  • Ragle intends to complete the installation of new 8” C900 PVC water main on Columbia between Governor and Lafayette.

  • Ragle intends to perform hydrostatic testing and chlorinate the new 8” C900 PVC water main on Columbia between Governor and Lafayette.

  • Ragle intends to complete the installation of new 8” C900 PVC water main on Columbia between Governor and Garvin.

  • Ragle intends to begin installing new 8” C900 PVC water main on Columbia between Garvin and Evans.

  • Ragle intends to begin installing new 12” C900 PVC water main on Columbia between Kerth and Evans.

Project Schedule

Fares Avenue, Eichel Avenue Louisiana Street Complete

 

Fares Avenue, Louisiana Street to Maryland Street​ Complete

 

Fares Avenue, Maryland Street to Columbia Street​ Complete

Columbia Street, Fares Avenue to Kerth Avenue​ Complete

Governor Street, Louisiana Avenue to Maryland Street

  • Water Main Installation – Mid October 2020 Complete

  • Water Main Final Connections (water main outages) – Late November 2020 Ongoing

  • Water Service Line Installation (individual customer outages)  – Complete 

  • Restoration (pavement patching, lawn seeding)  – Early December 2020 Ongoing

Governor Street, Maryland Street to Delaware Street

  • Water Main Installation – Mid October 2020 Complete

  • Water Main Final Connections (water main outages) –Late December 2020

  • Water Service Line Installation (individual customer outages)  – Mid December 2020 Complete

  • Restoration (pavement patching, lawn seeding)  – Mid December 2020 Ongoing

Columbia Street, Lafayette Avenue to Governor Street

  • Water Main Installation – Early January 2021

  • Water Main Final Connections (water main outages) – Mid January 2021

  • Water Service Line Installation (individual customer outages)  – Mid January 2021

  • Restoration (pavement patching, lawn seeding)  – Mid February 2021

Columbia Street, Governor Street to Elliott Street

  • Water Main Installation – Mid December 2020 Ongoing

  • Water Main Final Connections (water main outages) – Early January 2021

  • Water Service Line Installation (individual customer outages)  – Early January 2021

  • Restoration (pavement patching, lawn seeding)  – Mid February 2021

Columbia Street, Elliott Street to Evans Avenue

  • Water Main Installation – Early January 2021

  • Water Main Final Connections (water main outages) – Mid January 2021

  • Water Service Line Installation (individual customer outages)  – Late January 2021

  • Restoration (pavement patching, lawn seeding)  – Early February 2021

Columbia Street, Evans Avenue to 1015 E. Columbia Street

  • Water Main Installation – February 2021

  • Water Main Final Connections (water main outages) – March 2021

  • Water Service Line Installation (individual customer outages)  – April 2021

  • Restoration (pavement patching, lawn seeding)  – April 2021

Columbia Street, 1015 E. Columbia Street to Kerth Avenue

  • Water Main Installation – February/March 2021

  • Water Main Final Connections (water main outages) – March 2021

  • Water Service Line Installation (individual customer outages)  – March 2021

  • Restoration (pavement patching, lawn seeding)  – March 2021

  • Twitter Social Icon

© 2017 American Structurepoint, Inc.