Columbia Phase I, Fares, Columbia to Morgan Water Main Replacement

This project is estimated to include the installation of approximately 9,500 feet of new water main on N Governor Street, between Columbia Street and E Louisiana Street, Columbia Street, between Lafayette Avenue and Fares Avenue, and Fares Avenue, between Columbia Street and Eichel Avenue. Related upgrades throughout the project area include new hydrants, valves and service connections. Construction is anticipated to begin in May 2020.

Refresh Evansville Project Open Houses have been suspended due to concerns about COVID-19. The presentation has been recorded and can be viewed below. 

Columbia Phase I, Fares, Columbia to Morgan Water Main Replacement Open House Presentation

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Three i Design

Evansville, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Ragle, Inc.

Newburgh, Indiana

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (October 11 to October 17)

  • Ragle completed the connection of the new 12” water main to the existing 12” water main at Fares and Columbia. 

  • Ragle began concrete and lawn restoration on Fares between Maryland and Columbia, and on Columbia between Fares and Kerth. 

  • Ragle began installing HMA Base on Fares between Maryland and Columbia, and on Columbia between Fares and Kerth. 

Anticipated Activities for Upcoming Week (October 18 to October 24)

  • Ragle intends to complete the installation of HMA Base on Fares between Maryland and Columbia, and on Columbia between Fares and Kerth. 

  • Ragle intends to complete concrete and lawn restoration on Fares between Maryland and Columbia, and on Columbia between Fares and Kerth. 

  • Ragle intends to complete the final connection to the existing 8” fire service at 810 N. Fares, pending the results of water quality sampling. 

  • Ragle intends to begin connecting new ¾”-1” water services on Governor between Louisiana and Maryland, pending the results of water quality sampling

Project Schedule

Fares Avenue, Eichel Avenue Louisiana Street 

  • Water Main Installation Complete

  • Water Main Final Connections (water main outages) Complete

  • Water Service Line Installation (individual customer outages) Complete

  • Restoration (pavement patching, lawn seeding)  – Mid August 2020 Ongoing 

 

Fares Avenue, Louisiana Street to Maryland Street

  • Water Main Installation Complete

  • Water Main Final Connections (water main outages) Complete

  • Water Service Line Installation (individual customer outages) Complete

  • Restoration (pavement patching, lawn seeding)  – Late September 2020 Ongoing

 

Fares Avenue, Maryland Street to Columbia Street

  • Water Main Installation – Mid October 2020 Ongoing

  • Water Main Final Connections (water main outages) – Early October 2020

  • Water Service Line Installation (individual customer outages)  – Late October 2020

  • Restoration (pavement patching, lawn seeding)  – Early November 2020

Columbia Street, Fares Avenue to Kerth Avenue

  • Water Main Installation – Mid October 2020 Ongoing

  • Water Main Final Connections (water main outages) – Early October 2020

  • Water Service Line Installation (individual customer outages)  – Late October 2020

  • Restoration (pavement patching, lawn seeding)  – Early November 2020

Governor Street, Maryland Street to Delaware Street

  • Water Main Installation – Mid October 2020 Ongoing

  • Water Main Final Connections (water main outages) – Early October 2020

  • Water Service Line Installation (individual customer outages)  – Late October 2020

  • Restoration (pavement patching, lawn seeding)  – Early November 2020

Columbia Street, Lafayette Avenue to Governor Street

  • Water Main Installation – Mid October 2020

  • Water Main Final Connections (water main outages) – Late October 2020

  • Water Service Line Installation (individual customer outages)  – Late October 2020

  • Restoration (pavement patching, lawn seeding)  – Mid December 2020

Columbia Street, Governor Street to Sherman Avenue

  • Water Main Installation – Late October 2020

  • Water Main Final Connections (water main outages) – Mid November 2020

  • Water Service Line Installation (individual customer outages)  – Mid November 2020

  • Restoration (pavement patching, lawn seeding)  – Mid December 2020

Columbia Street, Sherman Avenue to Evans Avenue

  • Water Main Installation – Mid November 2020

  • Water Main Final Connections (water main outages) – Early December 2020

  • Water Service Line Installation (individual customer outages)  – Mid December 2020

  • Restoration (pavement patching, lawn seeding)  – Late December 2020

Columbia Street, Evans Avenue to 1015 E. Columbia Street

  • Water Main Installation – Late December 2020

  • Water Main Final Connections (water main outages) – Early February 2021

  • Water Service Line Installation (individual customer outages)  – Mid February 2021

  • Restoration (pavement patching, lawn seeding)  – Early April 2021

Columbia Street, 1015 E. Columbia Street to Kerth Avenue

  • Water Main Installation – Mid February 2021

  • Water Main Final Connections (water main outages) – Mid March 2021

  • Water Service Line Installation (individual customer outages)  – Late March 2021

  • Restoration (pavement patching, lawn seeding)  – Mid April 2021

  • Twitter Social Icon

© 2017 American Structurepoint, Inc.