Broadway Water Main Replacement

This project includes the installation of over 11,000 feet of 6"- 12" diameter Ductile Iron and C-900 PVC water main pipe along Broadway Avenue from Schutte Road to Red Bank Road, as well as along Frey Road from Broadway Avenue to the end of the public roadway. Related improvements include new valves and 26 fire hydrants throughout the corridor.  

Bids are currently being evaluated and construction is anticipate to begin in mid October 2019.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Clark Dietz, Inc.

Indianapolis, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- BMB, Inc.

Newburgh, IN

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

  • Recent Progress (December 1 to December 7)

    • BMB completed installation of 12” RJ C900 PVC water main on Broadway Avenue between Middle Mt. Vernon Road and Red Bank Road. 

    • BMB completed installation of the 12” tapping sleeve and 12” tapping valve at the intersection of Red Bank Road and Broadway Avenue.   

    • BMB completed installation of 12” RJ C900 PVC water main on Broadway Avenue between Johnson Lane and Speaker Road.  

    • BMB started installation of 12” C900 PVC water main on Broadway near Rollett Lane.  

 

 

  • Anticipated Activities for Upcoming Week (December 8 to December 14)

    • BMB intends to complete installation of 12” RJ C900 PVC water main on Broadway Avenue between Middle Mt. Vernon Road and Johnson Lane. 

    • BMB intends to complete installation of 12” C900 PVC water main on Broadway Avenue near Rollett Lane. 

    • BMB intends to complete installation of 8” C900 PVC water main on Broadway Avenue and Rollett Lane. 

    • BMB intends to complete installation of 12” C900 PVC water main on Middle Mount Vernon 
      Road. 

Project Schedule

Broadway Avenue, Red Bank Road to Johnson Lane

  • Water Main Installation – Late November 2019

  • Water Main Final Connections (water main outages) - Mid December 2019

  • Water Service Line Installation (individual customer outages) Mid December 2019

  • Restoration (pavement patching, lawn seeding) - Mid April 2020

Broadway Avenue, Speaker Road to Meadow Drive

  • Water Main Installation – Late December 2019

  • Water Main Final Connections (water main outages) - Mid January 2020

  • Water Service Line Installation (individual customer outages) – Mid January 2020

  • Restoration (pavement patching, lawn seeding) – Mid April 2020

Broadway Avenue, Johnson Lane to Speaker Road

  • Water Main Installation – Late December 2019 

  • Water Main Final Connections (water main outages) - Mid January 2020

  • Water Service Line Installation (individual customer outages) – Mid January 2020

  • Restoration (pavement patching, lawn seeding) - Mid April 2020

 

Broadway Avenue, Meadow Drive to Felstead Road

  • Water Main Installation – Mid December 2019

  • Water Main Final Connections (water main outages) - Late December 2019

  • Water Service Line Installation (individual customer outages) Early January 2020

  • Restoration (pavement patching, lawn seeding) - Mid April 2020

 

Broadway Avenue, Felstead Road to 6200 Broadway Avenue

  • Water Main Installation – Mid January 2020

  • Water Service Line Installation (individual customer outages) Early February 2020

  • Restoration (pavement patching, lawn seeding) - Mid April 2020

Broadway Avenue, 6200 Broadway Avenue to 6524 Broadway Avenue

  • Water Main Installation – Late January 2020

  • Water Service Line Installation (individual customer outages) Mid February 2020

  • Restoration (pavement patching, lawn seeding) - Mid April 2020

Broadway Avenue, 6524 Broadway Avenue to Nurrenbern Road

  • Water Main Installation – Early February 2020

  • Water Service Line Installation (individual customer outages) Late February 2020

  • Restoration (pavement patching, lawn seeding) - Mid April 2020

 

Broadway Avenue, Nurrenbern Road to Schutte Road

  • Water Main Installation Late - February 2020

  • Water Main Final Connections (water main outages) - Mid March 2020

  • Water Service Line Installation (individual customer outages) Late March 2020

  • Restoration (pavement patching, lawn seeding) - Mid April 2020

 

Frey Road, Broadway Avenue to 1705 Frey Road

  • Water Main Installation - Mid November 2019

  • Water Main Final Connections (water main outages) - Mid February 2020

  • Restoration (pavement patching, lawn seeding) - Mid April 2020

Frey Road, 1700 Frey Road to 1401 Frey Road

  • Water Main Installation – Mid November 2019

  • Water Main Final Connections (water main outages) - Mid February 2020

  • Restoration (pavement patching, lawn seeding) - Mid April 2020