Broadway Water Main Replacement

This project includes the installation of over 11,000 feet of 6"- 12" diameter Ductile Iron and C-900 PVC water main pipe along Broadway Avenue from Schutte Road to Red Bank Road, as well as along Frey Road from Broadway Avenue to the end of the public roadway. Related improvements include new valves and 26 fire hydrants throughout the corridor.  

Bids are currently being evaluated and construction is anticipate to begin in mid October 2019.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Clark Dietz, Inc.

Indianapolis, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- BMB, Inc.

Newburgh, IN

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

Recent Progress (May 24 to May 30)

  • BMB completed the connection of the new 12” C900 PVC water main to the existing water main at Broadway and Schutte. 

  • BMB completed cutting and capping the existing water main on Frey Road. 

Anticipated Activities for Upcoming Week (May 31 to June 6)

  • BMB intends to remove the abandoned valve boxes along Broadway. 

  • BMB intends to continue site restoration activities along Broadway.   

  • BMB intends to complete HMA patching along Broadway Avenue. 

Project Schedule

Broadway Avenue, Red Bank Road to Johnson Lane

  • Water Main Installation – Late November 2019 Complete

  • Water Main Final Connections (water main outages)  Complete

  • Water Service Line Installation (individual customer outages)  Complete

  • Restoration (pavement patching, lawn seeding) - Mid April 2020 Ongoing

Broadway Avenue, Speaker Road to Meadow Drive

  • Water Main Installation  Complete

  • Water Main Final Connections (water main outages) Complete

  • Water Service Line Installation (individual customer outages)  Complete

  • Restoration (pavement patching, lawn seeding)  Ongoing

Broadway Avenue, Johnson Lane to Speaker Road

  • Water Main Installation – Late December 2019 Complete

  • Water Main Final Connections (water main outages)  Complete

  • Water Service Line Installation (individual customer outages)  Complete

  • Restoration (pavement patching, lawn seeding)  Ongoing

 

Broadway Avenue, Meadow Drive to Felstead Road

  • Water Main Installation  Complete

  • Water Main Final Connections (water main outages)  Complete

  • Water Service Line Installation (individual customer outages)  Complete

  • Restoration (pavement patching, lawn seeding) - Late April 2020 Ongoing

 

Broadway Avenue, Felstead Road to 6200 Broadway Avenue

  • Water Main Installation Complete

  • Water Service Line Installation (individual customer outages) Complete

  • Restoration (pavement patching, lawn seeding) - Late April 2020 Ongoing

Broadway Avenue, 6200 Broadway Avenue to 6524 Broadway Avenue

  • Water Main Installation Complete

  • Water Service Line Installation (individual customer outages) Complete

  • Restoration (pavement patching, lawn seeding) - Late April 2020 Ongoing

Broadway Avenue, 6524 Broadway Avenue to Nurrenbern Road

  • Water Main Installation Complete

  • Water Service Line Installation (individual customer outages) Complete

  • Restoration (pavement patching, lawn seeding) - Late April 2020 Ongoing

 

Broadway Avenue, Nurrenbern Road to Schutte Road

  • Water Main Installation Late Complete

  • Water Main Final Connections (water main outages) Early May 2020 Complete

  • Water Service Line Installation (individual customer outages) Complete

  • Restoration (pavement patching, lawn seeding) - Late April 2020 Ongoing

 

Frey Road, Broadway Avenue to 1705 Frey Road

  • Water Main Installation Complete

  • Water Main Final Connections (water main outages) - Late April 2020 Complete

  • Restoration (pavement patching, lawn seeding) - Early May 2020 Ongoing

Frey Road, 1700 Frey Road to 1401 Frey Road

  • Water Main Installation Complete

  • Water Main Final Connections (water main outages) - Late April 2020 Complete

  • Restoration (pavement patching, lawn seeding) - Early May 2020 Ongoing