Bellaire Avenue, Oak Hill to Weinbach Water Main Replacement

U1059 Map
U1059 Map

U1059 Map
U1059 Map

1/1

This project includes the installation of approximately 820 feet of water main pipe along Bellaire Avenue between Oak Hill Road and Weinbach Avenue.

Construction is anticipated to begin in Spring 2021.

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Evansville Water & Sewer Utility

Evansville, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Koberstein Contacting, Inc. 

Evansville, IN

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

Recent Progress (May 2 to May 8) 

  • Koberstein continue mobilizing equipment and materials to the project site. 

  • Koberstein began performing advanced saw cutting operations throughout the project site. 

  • Koberstein performed a hydrostatic test on the 8” existing gate valve on Bellaire at Weinbach. 

  • Koberstein began installing new 8” C900 PVC water main on Bellaire between Weinbach and Hercules. 

Anticipated Activities for Upcoming Week (May 9 to May 15)  

  • Koberstein intends to complete the installation of new 8” C900 PVC water main on Bellaire between Weinbach and Hercules. 

  • Koberstein intends to perform hydrostatic testing and chlorinate the new 8” C900 PVC water main on Bellaire between Weinbach and Hercules. 

  • Koberstein intends to begin installing new 8” C900 PVC water main on Bellaire between Hercules and Oak Hill. 

Project Schedule

The project schedule will be posted as information is received from the Contractor.