Bartels Drive South of Evergreen Road Water Main Replacement

bartels
bartels

Water Pipe_iStock_000014408747Large
Water Pipe_iStock_000014408747Large

DI pipe - ThinkstockPhotos-146839180
DI pipe - ThinkstockPhotos-146839180

bartels
bartels

1/3

This project includes the replacement of the existing water main located on Evergreen Road and along Bartels Drive in northern Vanderburgh County.  The project includes the replacement of approximately 1,250 feet of existing water main pipe
with new 8” C900 PVC water main pipe and will include new fire hydrants, valves, and water service connections

Project Team

 

Project Owner - Evansville Water & Sewer Utility

Evansville, Indiana

Program Manager - American Structurepoint, Inc.

Evansville, Indiana

Project Designer - Evansville Water & Sewer Utility

Evansville, Indiana

Construction Manager - American Structurepoint, Inc.

Evansville, Indiana

Contractor- Infrastructure Systems, Inc.

Orleans, Indiana

Road Closures

Click HERE for updated road closures.

Boil Advisory Information

Click HERE for the latest boil advisory information

Alerts and Announcements

Click HERE for alerts and announcements.

Project Update

 

 Recent Progress (May 2 to May 8) 

  • Infrastructure Systems completed the installation of new 8” C900 PVC RJ water main by directional bore on Bartels, south of Evergreen. 

  • Infrastructure Systems performed hydrostatic testing and chlorinated the new 8” C900 PVC water main on Bartels, south of Evergreen. 

  • Infrastructure Systems began installing HMA base patching on Bartels, south of Evergreen. 

 
 
Anticipated Activities for Upcoming Week (May 9 to May 15) 

  • Infrastructure Systems intends to activate the new 8” C900 PVC RJ water main on Bartels, south of Evergreen, pending the results of water quality sampling. 

  • Infrastructure Systems intends to begin connecting new ¾”-1” water services on Bartels, south of Evergreen, pending the results of water quality sampling. 

Project Schedule

  • Bartels Drive

    • Water Main Installation - Ongoing

    • Water Service Line Installation (individual customer outages) - April 2021

    • Water Main Final Connections (water main outages) - April-May 2021

    • Restoration (pavement patching, lawn seeding) - May 2021